Transport Industry - General Carriers Contract Determination 2017
  
Date01/24/2025
Volume397
Part3
Page No.410
DescriptionVIRC - Variation by Industrial Relations Commission
Publication No.C9876
CategoryAward
Award Code 105  
Date Posted01/24/2025

spacer image spacer image

spacer image Click to download*
spacer image

(105)

SERIAL C9876

 

Transport Industry - General Carriers Contract Determination 2017

 

INDUSTRIAL RELATIONS COMMISSION OF NEW SOUTH WALES

 

Application by Transport Workers' Union of New South Wales

 

(Case No. 427934of 2024)

 

Before Commissioner McDonald

29 November 2024

 

VARIATION

 

1.      Delete subclauses (e) and (f) of subclause 20.2 of clause 20 Rates of Remuneration of the Award published 24 August 2020 (387 I.G. 924) and reprinted 1 March 2024 (396 I.G. 891) and insert in lieu the following:

 

(e)     Nothing in this subclause affects an obligation of a Principal Contractor to pay the per/km rate applicable in Schedule A Tables A.1.1 or A.2.1, or any of the rates in clauses A.2A, A4, A5 or A6 for the Cartage Work.

 

(f)     Minimum Earnings Guarantee - Reconciliation: If clause 20.2(b) or (c) applies to a Contract of Carriage and in an 8 week period the Contract Carrier has not worked at least 50 hours each week for whatever reason, then:

 

(i)      the Principal Contractor must ensure that the Contract Carrier receives an amount of pay (excluding any payment arising from the per/km rates in Schedule A Tables A.1.1 or A.2.1, or from any of the rates in clauses A.2A, A4, A5 or A6 equivalent to the Minimum Earnings Guarantee.

 

(ii)    If there is any shortfall between the amount of pay paid to the Contract Carrier (excluding any payment arising from the per/km rates in Schedule A clauses A.1.1 or A.2.1, or from any of the rates in clauses A.2A, A4, A5 or A6 and the Minimum Earnings Guarantee, the Principal Contractor must pay the shortfall to the Contract Carrier in the Principal Contractor’s next pay cycle.

 

2.      Delete tables in paragraph A.1.1 of subclause A.1 of Schedule A – Rates of Remuneration and insert the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Class of Vehicle

Per hour

Running Rate

Per km excluding

Per km fuel

 

 

fuel component

component of the

 

 

running rate for

running rate for

 

 

the purposes of

the purposes

 

 

Schedule C

Schedule C

($)

($/km)

($/km)

($/km)

Rigid-carrying capacity over

3 and including 5 tonnes

$57.30

$0.30

$0.13

$0.17

Rigid-carrying capacity 5

and including 8 tonnes

$65.32

$0.34

$0.14

$0.19

Rigid-carrying capacity over

8 and including 10 tonnes

$75.24

$0.44

$0.16

$0.28

Rigid-carrying capacity over

10 and including 12 tonnes

$75.27

$0.49

$0.20

$0.28

Rigid-carrying capacity over

12 and including 14 tonnes

$75.97

$0.48

$0.19

$0.28

Rigid-carrying capacity over

14 tonnes or more

$80.42

$0.58

$0.22

$0.36

Single Axle Prime Mover

$81.71

$0.54

$0.16

$0.38

Bogie Axle Prime Mover

$88.38

$0.67

$0.20

$0.46

 

From the first full pay period commencing on or after 1 June 2024:

 

Class of Vehicle

Per hour

 

 

 

 

 

($)

Running Rate

 

 

 

 


($/km)

Per km excluding fuel component running Rate for the purposes of Schedule C

($/km)

Per km fuel component
of the running rate for the purposes of Schedule C

($/km)

Rigid-carrying capacity up to and including 3 tonnes

Per Light Vehicle Schedule

Rigid-carrying capacity over 3 and including 5 tonnes

$55.46

$0.30

$0.13

$0.17

Rigid-carrying capacity over 5 and including 8 tonnes

$63.34

$0.33

$0.14

$0.19

Rigid-carrying capacity over 8 and including 10 tonnes

$71.45

$0.44

$0.16

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$73.06

$0.48

$0.20

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$73.75

$0.47

$0.19

$0.28

Rigid-carrying capacity over 14 tonnes or more

$78.12

$0.58

$0.21

$0.36

Single Axle Prime Mover

$79.35

$0.54

$0.16

$0.38

Bogie Axle Prime Mover

$85.86

$0.66

$0.20

$0.46

 

3.      Delete the tables in subclause A.2 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Class of Vehicle

Per hour

 

 

 

 

 

($)

Running Rate

($/km)

 

 

 

 

($)

Per km excluding fuel component running Rate for the purposes of Schedule C

($/km)$

Per km fuel component of the running rate for the purposes of Schedule C

 

($/km)

Rigid-carrying capacity up to and including 3 tonnes

Per Light Vehicle Schedule

Rigid-carrying capacity over 3 and including 5 tonnes

$52.94

$0.38

$0.21

$0.17

Rigid-carrying capacity over 5 and including 8 tonnes

$58.97

$0.43

$0.23

$0.19

Rigid-carrying capacity over 8 and including 10 tonnes

$64.65

$0.52

$0.24

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$69.44

$0.57

$0.29

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$69.28

$0.56

$0.28

$0.28

Rigid-carrying capacity over 14 tonnes or more

$70.63

$0.67

$0.30

$0.36

Single Axle Prime Mover

$66.87

$0.60

$0.24

$0.36

Bogie Axle Prime Mover

 

$72.29

$0.73

$0.29

$0.44

 

From the first full pay period commencing on or after 1 June 2024:

 

Class of Vehicle

Per hour

 

 

 

 

 

($)

Running Rate

($/km)

 

 

 

 

($)

Per km excluding fuel component running Rate for the purposes of Schedule C

($/km)$

Per km fuel component

of the running rate for the purposes of Schedule C

($/km)

Rigid-carrying capacity up to and including 3 tonnes

Per Light Vehicle Schedule

Rigid-carrying capacity over 3 and including 5 tonnes

$51.15

$0.37

$0.20

$0.17

Rigid-carrying capacity over 5 and including 8 tonnes

$57.07

$0.42

$0.23

$0.19

Rigid-carrying capacity over 8 and including 10 tonnes

$60.99

$0.52

$0.24

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$67.31

$0.57

$0.29

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$67.14

$0.55

$0.27

$0.28

Rigid-carrying capacity over 14 tonnes or more

$68.45

$0.66

$0.30

$0.36

Single Axle Prime Mover

$64.70

$0.60

$0.24

$0.36

Bogie Axle Prime Mover

$69.97

$0.73

$0.29

$0.44

 

4.         Insert the following new subclause A.2A after subclause A.2:

 

A.2A   A Contract Carrier who in order to perform a contract of carriage is required by the Principal Contractor to supply and tow a trailer of the kind described in the Trailer Type column below must be paid the following amounts (rounded up to the nearest half hour, and nearest kilometre):

 

From the first full pay period commencing on or after 1 December 2024:

 

Trailer Type

Per Hour

$

Per kilometre

($/km)

Semi Trailer

$9.87

$0.1840

 Double Lead Trailer

$9.16

$0.1840

Refrigerated

$15.32

$0.1840

5.      Delete Schedule A, subclause A.4.2 and insert in lieu the following:

 

The lump sum allowance referred to in clause 22.2 is:

 

(a)      From the first full pay period commencing on or after 1 December 2024: $8,315.03.

 

(b)      From the first full pay period commencing on or after 1 June 2024; $8,175.12 and

 

6.      Delete the table at Schedule A, subclause A.4.3 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.50

Single Axle Prime Mover

$0.50

Rigid-carrying capacity over 14 tonnes or more

$0.50

Rigid-carrying capacity over 12 and including 14 tonnes

$0.50

Rigid-carrying capacity over 10 and including 12 tonnes

$0.50

Rigid-carrying capacity over 8 and including 10 tonnes

$0.50

Rigid-carrying capacity over 5 and including 8 tonnes

$0.50

Rigid-carrying capacity over 3 and including 5 tonnes

$0.50

Rigid-carrying capacity less than 3 tonnes

$0.50

 

From the first full pay period commencing on or after 1 June 2024:

 

Class of Vehicle

Per hour
$

Bogie Axle Prime Mover

 $0.49

Single Axle Prime Mover

$0.49

Rigid-carrying capacity over 14 tonnes or more

$0.49

Rigid-carrying capacity over 12 and including 14 tonnes

$0.49

Rigid-carrying capacity over 10 and including 12 tonnes

$0.49

Rigid-carrying capacity over 8 and including 10 tonnes

$0.49

Rigid-carrying capacity over 5 and including 8 tonnes

$0.49

Rigid-carrying capacity over 3 and including 5 tonnes

$0.49

Rigid-carrying capacity less than 3 tonnes

$0.49

 

7.      Delete the table at Schedule A, subclause A.5 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Class of Vehicle

Per hour
$

Bogie Axle Prime Mover

$0.05

Single Axle Prime Mover

$0.05

Rigid-carrying capacity over 14 tonnes or more

$0.05

Rigid-carrying capacity over 12 and including 14 tonnes

$0.05

Rigid-carrying capacity over 10 and including 12 tonnes

$0.05

Rigid-carrying capacity over 8 and including 10 tonnes

$0.05

Rigid-carrying capacity over 5 and including 8 tonnes

$0.05

Rigid-carrying capacity over 2 and including 5 tonnes

$0.05

Rigid-carrying capacity less than 3 tonnes

From the first full pay period commencing on or after 1 June 2024:

 

Class of Vehicle

Per hour
$

Bogie Axle Prime Mover

$0.05

Single Axle Prime Mover

$0.05

Rigid-carrying capacity over 14 tonnes or more

$0.05

Rigid-carrying capacity over 12 and including 14 tonnes

$0.05

Rigid-carrying capacity over 10 and including 12 tonnes

$0.05

Rigid-carrying capacity over 8 and including 10 tonnes

$0.05

Rigid-carrying capacity over 5 and including 8 tonnes

$0.05

Rigid-carrying capacity over 2 and including 5 tonnes

$0.05

Rigid-carrying capacity less than 3 tonnes

 

8.      Delete the table at Schedule A, subclause A.6 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Class of Vehicle

Per-hour

$

Bogie Axle Prime Mover

$0.34

Single Axle Prime Mover

$0.34

Rigid-carrying capacity over 14 tonnes or more

$0.34

Rigid-carrying capacity over 12 and including 14 tonnes

$0.34

Rigid-carrying capacity over 10 and including 12 tonnes

$0.34

Rigid-carrying capacity over 8 and including 10 tonnes

$0.34

Rigid-carrying capacity over 5 and including 8 tonnes

$0.34

Rigid-carrying capacity over 2 and including 5 tonnes

$0.34

Rigid-carrying capacity less than 3 tonnes

 

 

From the first full pay period commencing on or after 1 June 2024:

 

Class of Vehicle

Per hour
$

Bogie Axle Prime Mover

$0.34

Single Axle Prime Mover

$0.34

Rigid-carrying capacity over 14 tonnes or more

$0.34

Rigid-carrying capacity over 12 and including 14 tonnes

$0.34

Rigid-carrying capacity over 10 and including 12 tonnes

$0.34

Rigid-carrying capacity over 8 and including 10 tonnes

$0.34

Rigid-carrying capacity over 5 and including 8 tonnes

$0.34

Rigid-carrying capacity over 2 and including 5 tonnes

$0.34

Rigid-carrying capacity less than 3 tonnes

 

9.      Delete Schedule A, subclause A.7.1 and insert in lieu the following:

 

A Contract Carrier who, in order to perform a contract of carriage, is required to supply tarpaulins, ropes, gates, chains and dogs for use in a Contract of Carriage must be paid the following allowance per day or part day during which the equipment is used for the purpose of the Contract of Carriage:

 

(a)     From the first full pay period on or after 1 December 2024: $5.31

 

(b)     From the first full pay period on or after 1 June 2024: $5.13

 

10.    Delete Schedule A, subclause A.7.2 and insert in lieu the following:

 

A Contract Carrier who, in order to perform a Contract of Carriage, is required to fit his trailer with twistlocks for the carriage of I.S.O containers must be paid the following allowance per day or part day during which the equipment is used for the purpose of the Contract of Carriage:

 

(a)     From the first full pay period commencing on or after 1 December 2024: $3.91

 

(b)     From the first full pay period on or after 1 June 2024: $3.84

 

11.    Delete the table at Schedule A, subclause A.7.3 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Equipment type

Per day

$

Rear-Lift Platform up to and including 3,000 lbs capacity

 $                      6.25

Rear-Lift Platform up to and including 6,000 lbs capacity

 $                      8.57

Side loading device

 $                    27.56

 

From the first full pay period commencing on or after 1 June 2024:

 

Equipment Type

Per day
$

Rear-Lift Platform up to and including 3,000 lbs capacity

 $                      6.14

Rear-Lift Platform up to and including 6,000 lbs capacity

 $                      8.42

Side loading device

 $                    27.10

 

12.    Delete the table at Schedule B, subclause B.1 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

Class of Vehicle

Rate

Rigid Vehicle

 

Not less than 8 and not greater than 10 tonnes

$71.99

Not less than 10 and not greater than 12 tonnes

$77.47

Not less than 12 and not greater than 14 tonnes

$77.10

Not less than 14 tonnes

$79.95

Single Axle Prime Mover

$75.34

Bogie Axle Prime Mover

$82.56

 

From the first full pay period commencing on or after 1 June 2024:

 

Class of Vehicle

Rate

Rigid Vehicle

 

Rigid-carrying capacity over 8 and including 10 tonnes

$68.28

Rigid-carrying capacity over 10 and including 12 tonnes

$75.27

Rigid-carrying capacity over 12 and including 14 tonnes

$74.90

Rigid-carrying capacity over 14 tonnes or more

$77.70

Single Axle Prime Mover

$73.10

Bogie Axle Prime Mover

$80.18

 

13.    Delete the table at Schedule B, subclause B.2 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

 

Rate A - Subsidy

Rate B –

No Subsidy

40 ft Skel trailer

$60.70 per day

$61.95 per day

40 ft General Purpose trailer

$60.70 per day

$65.24 per day

Dog or Pig trailer

$45.46 per day

$48.82 per day

Pup trailer

$30.37 per day

$32.64 per day

20 ft Skel trailer

$54.65 per day

$58.73 per day

 

From the first full pay period commencing on or after 1 June 2024:

 

 

Rate A - Subsidy

Rate B –

No Subsidy

40 ft Skel trailer

$58.65 per day

$59.85 per day

40 ft General Purpose trailer

$58.65 per day

$63.03 per day

Dog or Pig trailer

$43.92 per day

$47.17 per day

Pup trailer

$29.34 per day

$31.53 per day

20 ft Skel trailer

$52.80 per day

$56.74 per day

 

14.    Delete the table at Schedule B, subclause B.3 and insert in lieu the following:

 

From the first full pay period commencing on or after 1 December 2024:

 

40 ft trailer

$3.54 per hour

$3.46 per hour

Dog/Pig trailer

$6.89 per hour

$6.72 per hour

Pup trailer

$5.10 per hour

$4.98 per hour

 

From the first full pay period commencing on or after 1 June 2024:

 

40 ft trailer

$3.42 per hour

$3.34 per hour

Dog/Pig trailer

$6.66 per hour

$6.49 per hour

Pup trailer

$4.93 per hour

$4.81 per hour

 

15.    Replace subclause C.1.1 with the following wording:

 

C.1.1   The rates prescribed in Schedules A and B shall be adjusted with effect from 1 June and 1             December each year or as provided in this Schedule.

 

16.    Replace subclause C.1.8 with the following wording:

 

C.1.8   The procedure outlined in subclause C.1 does not apply to Light Vehicle Rates.

 

 

 

J. McDONALD, Commissioner.

 

____________________

 

Printed by the authority of the Industrial Registrar.

 

* to download attachment
  
IE UsersRight click the attachment - Click 'Save Target As' - Select a location - Click 'Save'
Netscape UsersRight click the attachment - Select 'Save Link As' - Select a location - Click 'Save'