State Crest
New South Wales Industrial Relations Commission
(Industrial Gazette)





spacer image spacer image

Transport Industry - General Carriers Contract Determination 2017
  
Date03/01/2024
Volume396
Part8
Page No.891
DescriptionAR - Award Reprint (Consolidation)
Publication No.C9828
CategoryContract Determination
Award Code 105  
Date Posted03/01/2024

spacer image spacer image

spacer image Click to download*
spacer image

(105)

SERIAL C9828

 

Transport Industry - General Carriers Contract Determination 2017

 

AWARD REPRINT

 

This reprint of the consolidated contract determination is published under the authority of the Industrial Registrar pursuant to section 390 of the Industrial Relations Act 1996, and under clause 6.6 of the Industrial Relations Commission Rules 2022.

 

I certify that the form of this reprint, incorporating the variations set out in the schedule, is correct as at 19 February 2024.

 

 

E. ROBINSON,  Industrial Registrar

 

 

Schedule of Variations Incorporated

 

Variation Serial No.

Date of Publication

Effective Date

Industrial Gazette Reference

 

 

 

Volume

Page No.

C9223

26 February 2021

15 March 2021

389

367

C9404

11 March 2022

1 March 2022

391

790

C9475

17 June 2022

18 April 2022

392

289

C9476

5 August 2022

16 May 2022

392

685

C9488

16 August 2022

20 June 2022

392

834

C9489

8 September 2022

18 July 2022

392

1049

C9500

8 September 2022

15 August 2022

392

1051

C9604

20 March 2023

19 September

393

1628

C9603

20 March 2023

3 October 2022

393

1617

C9605

20 March 2023

17 October 2022

393

1630

C9606

20 March 2023

14 November 2022

393

1632

C9609

20 March 2023

19 December 2022

393

1634

C9611

24 March 2023

16 January 2023

393

1664

C9614

24 March 2023

20 February 2023

393

1662

C9612

24 March 2023

20 February 2023

393

1666

C9620

31 March 2023

20 March 2023

393

1743

C9630

21 April 2023

20 February 2023

394

280

C9635

21 April 2023

17 April 2023

394

282

C9645

15 May 2023

12 May 2023

394

634

C9648

23 June 2023

19 June 2023

394

654

C9653

21 July 2023

17 July 2023

394

912

C9682

25 August 2023

21 August 2023

394

1796

C9729

6 October 2023

18 September 2023

395

462

C9741

13 October 2023

16 October 2023

395

499

C9767

17 November 2023

10 November 2023

395

1173

C9766

17 November 2023

20 November 2023

395

1193

C9796

15 December 2023

18 December 2023

396

145

C9805

12 January 2024

15 January 2024

396

432

C9818

2 February 2024

12 February 2024

396

619

 

DETERMINATION

 

Clause No.        Subject Matter

 

PART 1 -APPLICATION AND OPERATION

 

1.        Definitions

2.        Application

3.        Savings clause

4.        Promotion of Determination

 

PART 2 - OPERATIONAL MATTERS

 

5.        Vehicles

6.        Loading and Delivery

7.        Fatigue Management and Heavy Vehicle Compliance

8.        Uniforms

9.        Lunch Break

10.      Annual Leave

 

PART 3- RIGHTS AND RESPONSIBILITIES

 

11.      Contract Carrier Obligations

12.      Principal Contractors’ Obligations

13.      Termination

14.      Insurance

15.      Allocation of Work and Rostering

16.      Fleet Mix Change

17.      Selling of Vehicles

18.      Supervision of Personnel

 

PART 4 - RATES AND REMUNERATION

 

19.      Application of this Part

20.      Rates of Remuneration

21.      Alternative Remuneration Arrangements

22.      Mass Management

24.      Three Yearly Cost Reconciliation Review

25.      Tolls & Charges

 

PART 5- MISCELLANEOUS

 

26.      Disputes Procedure

27.      Union Delegates

28.      Record Keeping

29.      Leave Reserved

 

Schedule A - Rates of Remuneration

Schedule B - Waterfront and Container Depots

Schedule C - Procedure and Time for Adjustments of Rates

Schedule D - Nominated Contract Determinations

Schedule E Superannuation Contribution Arrangements Schedule F – Temporary Fuel Surcharge

 

PART 1 - APPLICATION AND OPERATION

 

1.  Definitions

 

1.1      In this Determination:

 

Act means the Industrial Relations Act 1996 (NSW);

 

Additional Amount has the meaning attributed to it in Schedule A;

 

Carrying Capacity in relation to a Vehicle means the mass of the maximum load which the Vehicle may legally carry;

 

Cartage Rate Schedule means a written schedule (which may be an electronic document) identifying:

 

(a)       the basis of calculation of the Cartage Rates (e.g. per hour, per km or some other basis);

 

(b)      the amount of remuneration to be paid to the Contract Carrier for the Cartage Work (e.g. $100 per hour); and

 

(c)       the timing of the payment of remuneration (e.g. the day of the week on which remuneration will be paid and the pay period).

 

Cartage Work means work performed under a Contract of Carriage;

 

Cost Model means the spreadsheet marked as Exhibit 1 in Matter No. 2019/48046;

 

Class of Vehicle means either a single axle drive prime mover or a bogie axle drive prime mover or, in the case of any other Vehicle, a Vehicle of a particular Carrying Capacity;

 

Contract of Carriage has the meaning given to that expression by the Act; Contract Carrier has the meaning given to that expression by the Act;

 

Delegate means a Union delegate of Contract Carriers based at a terminal and includes a co- delegate;

 

Determination means this Transport Industry - General Carriers Contract Determination;

 

Driver means a natural person operating the Contract Carrier’s Vehicle who is approved in accordance with clause 11.6;

 

Finishing Place means:

 

(a)       the sites or depots where the Contract Carrier is principally engaged (which may be a network of depots within reasonable proximity); or

 

(b)      where the Principal Contractor and the Contract Carrier have agreed on an alternative location, the agreed alternative location; or

 

(c)       a place specified by the Principal Contractor, but only if the Contract Carrier is not principally engaged at a site or depot, save that any agreed or specified Finishing Place must be reasonable in the circumstances;

 

IRC means the Industrial Relations Commission of New South Wales;

 

Light Vehicle means a Vehicle with a Carrying Capacity of up to and including 3 tonnes;

 

Light Vehicle Rates means the minimum rates of remuneration set out in Schedule A.3 in this Determination that are expressed to apply to Light Vehicles.

Misconduct means consuming alcohol immediately before, or while undertaking work for the Principal Contractor, being under the influence of alcohol or a drug while undertaking work for the Principal Contractor, being dishonest or abusive while undertaking work for the Principal Contractor or in dealings with the Principal Contractor or customers, consignors, consignees or their respective representatives, or falsifying documents submitted to the Principal Contractor;

 

Nominated Contract Determination means a determination listed in Schedule D and any successor to those determinations;

 

Principal Contractor has the meaning given to that expression by the Act;

 

Regular Contract Carrier means a Contract Carrier who operates under a contract with a Principal Contractor and who is wholly or principally engaged by that Principal Contractor;

 

Specialised Vehicle means:

 

(a)       a rigid Vehicle with a tipping body;

 

(b)      an articulated Vehicle with a tipping trailer;

 

(c)       a Vehicle combination with a tipping trailer;

 

(d)      a rigid Vehicle with a tanker;

 

(e)       an articulated Vehicle with a tanker trailer;

 

(f)       a Vehicle combination with a tanker trailer;

 

(g)      a rigid or articulated Vehicle with a premixed concrete agitator;

 

(h)      a rigid, articulated or combination Vehicle that utilises a forklift or crane that is used to load and/or unload the Vehicle carting bricks, roof tiles, precast concrete panels, masonry or pottery;

 

(i)       a Vehicle with a trailer designed for the carrying of motor Vehicles; and

 

(j)       a Vehicle with a trailer designed to carry heavy machinery, operating plant or wide loads (a float),

 

save that a Specialised Vehicle does not include a Vehicle listed above if the Vehicle is being used in a manner or to cart materials or products for which it would not customarily be used for;

 

Starting Place means:

 

(a)       the sites or depots where the Contract Carrier is principally engaged (which may be a network of depots within reasonable proximity); or

 

(b)      where the Principal Contractor and the Contract Carrier have agreed on an alternative location, the agreed alternative location; or

 

(c)       a place specified by the Principal Contractor, but only if the Contract Carrier is not principally engaged at a site or depot,

 

save that any agreed or specified Starting Place must be reasonable in the circumstances; Union means the Transport Workers' Union of New South Wales; and

 

Vehicle means a Vehicle used by a Contract Carrier for the purpose of a Contract of Carriage.

 

Work Distance means the distance necessarily travelled by a Contract Carrier in the course of performing a Contract of Carriage, counted from the moment of departure from the Starting Place to the completion of Cartage Work at the Finishing Place;

Work Time means the time during which a Contract Carrier is necessarily engaged performing a Contract of Carriage. To avoid doubt, Work Time includes all time during which the Contract Carrier is required by the Principal Contractor to be at their disposal and/or at their direction, but excluding time lost because of breakdowns or accidents and the time taken by the Contract Carrier for meal breaks;

 

2.  Application

 

2.1      This Determination applies to all Contracts of Carriage other than Contracts of Carriage:

 

(a)       which are covered by one of the Nominated Contract Determinations; and/or

 

(b)      which are performed using a Specialised Vehicle.

 

2.2      This Determination takes effect on and from 6 August 2019 and shall have a nominal term of 3 years.

 

3.  Savings Clause

 

3.1      No Contract Carrier shall suffer a reduction in their terms and conditions of engagement because of the making of this Determination.

 

3.2      This subclause applies to Contracts of Carriage entered into prior to 1 March 2022 that are performed by a Vehicle with a Carrying Capacity over 2 tonnes and up to and including 3 tonnes. No Contract Carrier shall suffer a reduction in the rates paid for such Contracts of Carriage (as were being paid immediately prior to the first pay period commencing on or after 1 March 2022) because of the introduction of Light Vehicle Rates.

 

4.  Promotion of Determination

 

4.1      Within fourteen days of the commencement of this determination the Principal Contractor shall provide every Contract Carrier it currently engages a copy of this Determination.

 

4.2      The Principal Contractor shall provide every new Contract Carrier it engages after this Determination commences with a copy of this Determination within seven days of the engagement.

 

4.3      A Principal Contractor shall provide every Contract Carrier it engages with a copy of any variation to this Determination within fourteen days of the commencement of the variation.

 

4.4      The obligations in paragraphs 4.1 to 4.3 of this clause may be satisfied by providing an electronic copy of the instrument by email or other electronic means. A Principal Contractor may require, and the Contract Carrier shall provide, a current email address for that purpose.

 

4.5      Notwithstanding the terms of paragraphs 4.1-4.3 a Principal Contractor is not obliged to provide a copy of the documents more than once in any 12 months.

 

4.6      A Principal Contractor shall display a copy of the determination and any variations then in force. at the Principal Contractor’s workplace.

 

PART 2 - OPERATIONAL MATTERS

 

5.  Vehicles

 

5.1      Supply and Suitability

 

The Contract Carrier must supply a Vehicle, which must:

 

(a)       meet the Vehicle specification required by the Principal Contractor; and

 

(b)      be approved by the Principal Contractor prior to performing Cartage Work.

 

5.2      Registration

 

The Contract Carrier must at the Contract Carrier’s own expense register their Vehicle.

 

5.3      Maintenance and Repair

 

The Contract Carrier must mechanically maintain and repair their Vehicle at their own expense.

 

5.4      Running Expenses

 

The Contract Carrier must pay all of the running costs associated with the Contract Carrier’s Vehicle.

 

5.5      Cease Using Vehicle

 

(a)       Where a Principal Contractor has a reasonable concern that a Contract Carrier’s Vehicle is not, or may not be, roadworthy to perform the Cartage Work, the Principal Contractor may:

 

(i)       direct the Contract Carrier to stop using the Vehicle (or any part of it) pending;

 

(A)      inspection and/or testing of the Vehicle; and/or

 

(B)      where necessary, the carrying out of any repairs and/or maintenance.

 

(b)      The Principal Contractor must not take any steps under clause 5.5(a) until the Principal Contractor has put its reasonable concern to the Contract Carrier.

 

(c)       The Contract Carrier will not suffer any loss of remuneration where they are directed to stop using their Vehicle under this clause, and where the inspection and/or testing of the Vehicle proves that the Vehicle was roadworthy to perform the Cartage Work.

 

5.6      Inspections and Tests

 

The Contract Carrier must make the Vehicle available for inspection or testing as and when reasonably required by the Principal Contractor.

 

5.7      Communication and Related Technology

 

(a)       The Principal Contractor may supply the Contract Carrier with communication and related technology for use in the Contract Carrier’s Vehicle.

 

(b)      Where such communication and/or related technology is supplied by the Principal Contractor:

 

(i)       The Principal Contractor must install and maintain the communication and related technology required by the Principal Contractor and the Contract Carrier must operate it efficiently as directed by the Principal Contractor.

 

(ii)      The Contract Carrier has full responsibility for the safe custody of the communication and related technology.

 

(iii)     The Contract Carrier must:

 

(A)      not add to, alter or modify the communication and related technology;

 

(B)      indemnify the Principal Contractor, and keep the Principal Contractor indemnified at all times, against destruction or loss of the communication and related technology;

 

(C)      not pledge the credit of the Principal Contractor in respect of, or create any lien upon, the communication and related technology; and

 

(D)      not without the prior written consent of the Principal Contractor use the communication and related technology for anything but the Cartage Work.

 

(c)       The Contract Carrier must stop using the communication and related technology (or any part of it) if the Principal Contractor so directs because in the Principal Contractor's opinion that is appropriate pending the carrying out of any repairs, maintenance, inspection or testing.

 

(d)      Immediately upon the ending or termination of any head contract under which the Contract Carrier performs the Cartage Work:

 

(i)       the Contract Carrier must return the communication and related technology to the Principal Contractor in good order and condition, save for any fair wear and tear only; and

 

(ii)      the Principal Contractor must make good any repairs to the Contract Carrier’s Vehicle arising from the removal of the communication and related technology.

 

5.8      Vehicles

 

(a)       The Principal Contractor has the right to specify the age and the Class of Vehicle used in the performance of Contracts of Carriage prior to the engagement of a Contract Carrier.

 

(b)      If a Principal Contractor reasonably believes that the Vehicle of the Contract Carrier is not suitable for undertaking the required Cartage Work, the Principal Contractor has the right to require an upgrade (which may include the purchase of a new or newer Vehicle) of the Contract Carrier’s Vehicle subject to the provision of a period which is reasonable in the circumstances and any such direction to upgrade being set out in writing.

 

(c)       The Contract Carrier must not replace the Vehicle used to perform Cartage Work without the prior written consent of the Principal Contractor.

 

5.9      Painting and sign-writing

 

(a)       Unless otherwise agreed, a Principal Contractor may paint and/or sign-write the Contract Carrier's Vehicle in the Principal Contractor's colours at the Principal Contractor's expense (but not before the Contract Carrier has completed three months continuous Cartage Work for the Principal Contractor).

 

(b)      In the case of a Contract Carrier ceasing to perform Work for the Principal Contractor, the Principal Contractor must bear the cost of reversing any painting and sign-writing and removing all equipment and signs supplied by the Principal Contractor and make good the affected areas of the Vehicle to the original specification.

 

(c)       A Principal Contractor must take, and a Contract Carrier must cooperate with, reasonable steps to minimise or avoid the loss of remuneration which would otherwise be suffered by the Contract Carrier because the Vehicle is being painted and/or sign-written at the request of the Principal Contractor, including by:

 

(i)       providing the Contract Carrier with an alternative vehicle with which to perform work; and/or

 

(ii)      by painting or sign-writing the Vehicle during a period in which the driver has previously arranged to take leave; and/or

 

(iii)     by the Principal Contractor compensating the Contract Carrier for any loss of remuneration suffered.

 

6.  Loading and Delivery

 

6.1      Report at Starting Place and Time

 

The Contract Carrier must report available for the Cartage Work with the Vehicle at the Starting Place.

 

6.2      Checking of Load

 

After loading the Vehicle and before leaving the loading place, the Contract Carrier must:

 

(a)       ensure that the load is secured; and

 

(b)      immediately report to the Principal Contractor if the Contract Carrier believes that the goods do not comply with the specification on the delivery docket or exceeds the maximum legal payload for the Vehicle.

 

6.3      Delivery

 

Immediately after checking the load the Contract Carrier must deliver the goods to whatever addresses the Principal Contractor instructs using:

 

(a)       the route directed by the Principal Contractor; or

 

(b)      if no such direction is given, using the shortest practicable route.

 

6.4      Unloading

 

The Contract Carrier must:

 

(a)       use every reasonable effort at the delivery site to obtain:

 

(i)       directions from the customer concerning the manner and position to unload the goods; and

 

(ii)      from the customer the signatures required by the Principal Contractor; and

 

(b)      unload the goods at the delivery site in the manner and position reasonably directed by the customer.

 

6.5      Unsafe Unloading

 

If the unloading of the goods at any delivery site will place the Driver in a position of imminent risk to their health and safety, the Contract Carrier must immediately notify the Principal Contractor prior to unloading the goods and comply with any instructions given by the Principal Contractor concerning the unloading of the goods.

 

6.6      Return

 

After completing the deliveries, the Contract Carrier must report to whatever site (if any) the Principal Contractor instructs using the shortest practicable route from the final unloading site.

 

6.7      Custody

 

The Contract Carrier shall:

 

(a)       be responsible for the equipment and gear and for the safe loading of the Vehicle and the securing and appropriate weather protection of the load and shall be present to supervise and assist in the loading and unloading of the Vehicle and/or the container loaded on the Vehicle;

 

(b)      in the case of pre-loaded Vehicles, be responsible for checking the load for safety and satisfactory method of loading; and

 

(c)       exercise all reasonable care and diligence in the carriage and safe keeping of the goods in charge.

 

7.  Fatigue Management and Heavy Vehicle Compliance

 

7.1      Fatigue management and heavy vehicle compliance

 

Fatigue management and heavy vehicle compliance is principally regulated in NSW by the:

 

(a)       Heavy Vehicle National Law, and associated regulations;

 

(b)      Work Health and Safety Act 2011 (NSW); and

 

(c)       Transport Industry Mutual Responsibility Contract Determination.

 

7.2      Taking of Fatigue Breaks

 

Each Contract Carrier must take fatigue breaks, without payment, as required by law.

 

8.  Uniforms

 

8.1      Supply of Uniform

 

If the Driver of the Contract Carrier’s Vehicle is required by the Principal Contractor to wear a special uniform when undertaking Cartage Work for the Principal Contractor, the uniform must be supplied by the Principal Contractor at no cost to the Contract Carrier.

 

8.2      Obligation to wear

 

Where a uniform is so provided, the Contract Carrier must ensure that it is worn by the Driver at all times while undertaking Cartage Work for the Principal Contractor.

 

8.3      Property

 

The uniform remains the property of the Principal Contractor.

 

8.4      Quantity

 

The Principal Contractor must provide a sufficient number of uniform articles to enable the Contract Carrier to wear a clean uniform at the start of each Cartage Working day.

 

8.5      Replacement

 

An item forming part of the uniform must be replaced by the Principal Contractor when required by fair wear and tear, provided that should loss or damage to an item forming part of the uniform occur due to the negligence of the Contract Carrier, the item must be repaired or replaced by the Contract Carrier at the Contract Carrier’s cost.

 

9.  Lunch Break

 

9.1      Entitlement

 

Each Contract Carrier is entitled to and must take a 30 minute unpaid lunch break on each day Cartage Work is performed for a Principal Contractor for more than 4 hours provided that where it is safe and reasonably practicable to do so, the Contract Carrier must take the lunch break in conjunction with a fatigue break.

 

9.2      Reporting

 

A Contract Carrier who ceases Cartage Work for a lunch break in accordance with clause 9.1 must report that fact to the Principal Contractor.

 

10.  Annual Leave

 

10.1    Entitlement

 

A Regular Contract Carrier may take four weeks' annual leave without payment.

 

10.2    When the Entitlement Falls Due

 

The leave entitlement falls due each year on the anniversary of the commencement date of the first Contract of Carriage between the Contract Carrier and the Principal Contractor.

 

10.3    Period to Take Leave

 

Such leave is to be taken by the Contract Carrier within 6 months of the leave falling due (or within such extended time as the Contract Carrier and the Principal Contractor may agree) and at a time mutually convenient to the Contract Carrier and the Principal Contractor.

 

10.4    Utilisation of Vehicle

 

To avoid any doubt, and unless otherwise agreed between the parties, during any period of annual leave the Contract Carrier has no obligation to present their Vehicle to the Principal Contractor for Cartage Work.

 

10.5    Lapse of Entitlement

 

If the leave is not taken within the time provided for in this clause, the entitlement to the leave will lapse.

 

PART 3 - RIGHTS AND RESPONSIBILITIES

 

11.  Contract Carrier Obligations

 

11.1    Core Obligations

 

The Contract Carrier must perform the Cartage Work and do everything connected with it:

 

(a)       with due care and skill and in a proper, co-operative and professional manner;

 

(b)      safely, and in accordance with the Principal Contractor's safety requirements;

 

(c)       in accordance with the day to day operational directions given by the Principal Contractor;

 

(d)      in accordance with any lawful and reasonable direction, policy, procedure or specifications provided by the Principal Contractor;

 

(e)       without jeopardising or damaging the Principal Contractor's business; and

 

(f)       in compliance with all relevant laws.

 

11.2    Compliance with Employment Laws

 

The Contract Carrier must comply with the provisions of any relevant employment law, including but not limited to laws concerning income tax, workers’ compensation, superannuation, annual leave, long service leave or any award, order, determination or agreement of a competent industrial tribunal.

 

11.3    Administration

 

The Contract Carrier must:

 

(a)       return to the Principal Contractor all delivery dockets, daily Cartage Work sheets or other records required by the Principal Contractor as and when required;

 

(b)      maintain up to date and accurate log books as required under any relevant law and/or by the Principal Contractor and make these available for inspection by the Principal Contractor on request;

 

(c)       ensure that the Driver maintains a system verifying Vehicle maintenance;

 

(d)      keep and retain for seven years comprehensive records in relation to the Cartage Work, including the records in subparagraphs (b) and (c) above; and

 

(e)       ensure that a copy of the records in subparagraphs (b), (c) and (d) are available for inspection at any time for audit purposes.

 

Notation: Any written material to be provided to the Principal Contractor in accordance with this clause must be appropriate and economical and designed to meet the requirements of this clause.

 

11.4    Medicals

 

(a)       The Contract Carrier must ensure that the Driver is at all times medically fit to perform the Cartage Work.

 

(b)      Where the Principal Contractor has a reasonable concern that the Driver is not medically fit to perform the Cartage Work, the Principal Contractor may require and direct the Driver to:

 

(i)       furnish particulars and/or medical evidence affirming the Driver’s fitness to undertake Cartage Work; and/or

 

(ii)      on reasonable terms, attend a medical examination to confirm their fitness (such direction may include the choice of medical practitioner).

 

(c)       The Principal Contractor must not take any steps under clause 11.4(b) until the Principal Contractor has put its concerns to the Contract Carrier in writing.

 

(d)      If the Driver attends a medical practitioner directed by the Principal Contractor, the Principal Contractor will pay the medical fees associated with the attendance.

 

(e)       The Driver will not suffer any loss of remuneration as a result of being directed to attend a medical examination under this clause, unless the medical examination demonstrates that the Driver was not medically fit to perform the Cartage Work.

 

11.5    Alcohol and Other Drugs Polices and Programs

 

Where the Principal Contractor has in place a drug and alcohol policy and/or program, applying to its employees and contractors, the Contract Carrier must ensure that the Driver participates in any testing required by the policy and/or program.

 

11.6    No One Else to Drive Vehicle The Contract Carrier must:

 

(a)       only use a Driver who is approved by the Principal Contractor, with such approval not being unreasonably withheld; and

 

(b)      make sure that no one except the approved Driver drives or otherwise operates the Vehicle for the Cartage Work.

 

11.7    Valid Driving License and Permits

 

The Contract Carrier must:

 

(a)       make sure that the approved Driver is at all times the holder of a current:

 

(i)       valid driver's licence appropriately endorsed or issued in respect of their Vehicle; and

 

(ii)      valid licence or permit of any other kind needed from time to time to perform the Cartage Work;

 

(b)      immediately notify the Principal Contractor if a licence or permit is cancelled or suspended for any reason; and

 

(c)       present any such licence or permit to the Principal Contractor upon request.

 

Note: Clause 11.7(a)(i) does not apply in relation to Contracts of Carriage performed exclusively by bicycle.

 

12.  Principal Contractors’ Obligations

 

The Principal Contractor must:

 

(a)       arrange whenever practicable for a representative of the Principal Contractor to attend accidents involving substantial load or equipment damage or personal injury;

 

(b)       advise Contract Carriers as early as possible of urgent or special delivery instructions arranged for particular work or particular goods;

 

(c)       where goods of a dangerous or hazardous nature are to be carried, notify the Contract Carrier of the nature of such goods and comply with all relevant requirements of the Dangerous Goods (Road and Rail) Act, accompanying Regulations and its related Codes of Practice;

 

(d)       pay the Contract Carrier any undisputed amount set out in a valid taxation invoice provided by the Contract Carrier, or generated for the Contract Carrier, for the Cartage Work performed, within 30 days of the date of receipt by the Principal Contractor of the invoice;

 

(e)       wherever the Contract Carrier is or is deemed to be for the purposes of the Workers Compensation Act a worker of the Principal Contractor, take out and maintain at all times a workers' compensation insurance policy in respect of the Contract Carrier;

 

(f)       comply with any laws affecting the Principal Contractor’s Cartage Work including licensing, road transport, fatigue management and work health and safety laws; and

 

(g)       provide to each Contract Carrier a Cartage Rate Schedule prior to commencing to perform Cartage Work and whenever there is a change to the basis of calculation of the Cartage Rates and/or a change to the Cartage Rates.

 

13.  Termination

 

(a)       Where a Contract Carrier commits Misconduct or is in breach of this Determination he/she may be terminated summarily by the Principal Contractor. An inquiry, if requested, will be held thereafter within one normal work day by the Principal Contractor, Delegate and, if available, a representative of the union.

 

(b)       Any other termination shall be on the basis of "last on-first off" for Contract Carriers operating vehicles of a particular class of vehicle.

 

14.  Insurance

 

14.1    Insurances

 

Prior to commencing any Cartage Work, the Contract Carrier must obtain, and maintain current at all relevant times, the following insurances at the Contract Carrier’s expense:

 

(a)       comprehensive and third party motor Vehicle insurance covering personal injury and property damage arising from the use of the Contract Carrier’s Vehicle or other mobile equipment, including compliance with any statutory requirements, of not less than $20,000,000 (or such other amount as the Principal Contractor may require from time to time) for each and every occurrence;

 

(b)      property insurance covering the full replacement value of the Contract Carrier’s Vehicle;

 

(c)       public and products liability insurance written on an occurrence basis covering the legal liability of the Contract Carrier and the Contract Carrier’s employees and agents (the "Insureds") to any third parties for bodily injury and/or property damage arising from acts or omissions of the Insureds in the course of, or arising from, the performance of the Cartage Works by the Contract Carrier or on the Contract Carrier’s behalf of not less than $20,000,000 (or such other amount as the Principal Contractor may require from time to time) for each and every occurrence; and

 

(d)      workers’ compensation insurance as required by any relevant law.

 

14.2    Endorsements

 

The Contract Carrier must ensure that, in respect of the insurance policies taken out, they contain clauses, endorsements or stipulations as reasonably required by the Principal Contractor.

 

14.3       Co-Operation

 

The Contract Carrier must:

 

(a)       not do, or omit to do, anything which might vitiate, impair or derogate from the cover under any insurance policy or other cover or which might prejudice any claim under any policy or other cover; and

 

(b)      fully co-operate with the Principal Contractor in relation to a claim under the insurances.

 

14.4    Provision of Currency

 

The Contract Carrier must upon the Principal Contractor’s request provide to the Principal Contractor certificates of currency evidencing the existence of the policies required to be effected under this clause and the certificates of currency must, as a minimum, show the insurer’s name, policy number and policy expiry date.

 

14.5    Other Insurances

 

If the Principal Contractor requires a Contract Carrier to obtain an insurance other than the insurances set out in clause 14.1 or to obtain different levels of insurance cover, the Principal Contractor must reasonably compensate the Contract Carrier for the cost of that insurance.

 

15.  Allocation of Work and Rostering

 

15.1    Allocation of Cartage Work

 

A Principal Contractor must allocate Cartage Work to Contract Carriers transparently, reasonably and lawfully.

 

15.2    Rostering

 

A Principal Contractor must roster Contract Carriers to perform work (including rostering on, return load and rostering off) transparently, reasonably and lawfully.

 

16.  Fleet Mix Change

 

16.1    Changing Fleet Mix - Mandatory Consultation

 

(a)       This clause applies where a Principal Contractor has made a definite decision to make a fleet mix change that is likely to have significant effects on Contract Carriers.

 

(b)      For a fleet mix change referred to in paragraph 16.1(a):

 

(i)       the Principal Contractor must notify the relevant Contract Carriers of the decision to change the fleet mix; and

 

(ii)      subclauses (c) to (h) apply.

 

(c)       The relevant Contract Carriers may appoint a representative for the purposes of the procedures in this clause.

 

(d)         If:

 

(i)       a relevant Contract Carrier appoints, or relevant Contract Carriers appoint, a representative for the purposes of consultation; and

 

(ii)      the Contract Carrier or Contract Carriers advise the Principal Contractor of the identity of the representative;

 

(ii)      the Principal Contractor must recognise the representative.

 

(e)       As soon as practicable after making its decision, the Principal Contractor must:

 

(i)       discuss with the relevant Contract Carriers:

 

(A)      the proposed change to the fleet mix; and

 

(B)      the effect the change is likely to have on the Contract Carriers; and

 

(C)      measures the Principal Contractor is taking to avert or mitigate the adverse effect of the change on the Contract Carriers; and

 

(ii)      for the purposes of the discussion, provide in writing to the relevant Contract Carriers:

 

(A)      all relevant information about the change including the nature of the change proposed; and

 

(B)      information about the expected effects of the change on the Contract Carriers; and

 

(C)      any other matters likely to affect the Contract Carriers.

 

(f)       However, the Principal Contractor is not required to disclose confidential or commercially sensitive information to the relevant Contract Carriers.

 

(g)       The Principal Contractor must give prompt and genuine consideration to matters raised about the change by the relevant Contract Carriers.

 

(h)       In this clause, a "fleet mix change" arises:

 

(i)       when a Principal Contractor decides to introduce a new transport type into their fleet being one or more of the following transport types:

 

(A)      Contract Carriers; or

 

(B)      Drivers employed by the Principal Contractor; or

 

(C)      third party transport providers;

 

(ii)      when a Principal Contractor introduces into their fleet a new Vehicle configuration.

 

17.  Selling of Vehicles

 

No circumstances shall exist where a Vehicle is sold with Cartage Work.

 

18.  Supervision of Personnel

 

The Contract Carrier must ensure that each and all of its Drivers:

 

(a)       performs the Cartage Work and does everything connected with it as is required of the Contract Carrier by this Determination; and

 

(b)       does not engage in any acts or omissions that give rise to a breach by the Contract Carrier of this Determination.

 

PART 4 - RATES OF REMUNERATION

 

19.  Application of this Part

 

19.1    This Part applies:

 

(a)       to all Contracts of Carriage from one place to another place, both of which are within the County of Cumberland; and

 

(b)      to all Contracts of Carriage for the transportation of goods from one place to another place, where the second place is no more than 50 kilometres from the first place.

 

19.2    This Part also applies to a Contract of Carriage involving a single journey commencing within the County of Cumberland and finishing within:

 

(a)       a 50 kilometre radius of the Newcastle GPO; or

 

(b)      a rectangular area being 50 kilometres North of the Wollongong GPO, 20 kilometres East of the Wollongong GPO, 50 kilometres South of the Wollongong GPO and 20 kilometres West of the Wollongong GPO.

 

20.  Rates of Remuneration

 

20.1    Subject to this clause, a Principal Contractor shall pay to a Contract Carrier:

 

(a)       the rate of remuneration per kilometre in the Schedules to this Determination applicable to the Contract Carrier’s Vehicle for the Work Distance; and

 

(b)      the rate of remuneration per hour in the Schedules to this Determination applicable to the Contract Carrier’s vehicle for the Work Time calculated to the nearest half hour; and

 

(c)       any additional rate prescribed in the Schedules to this Determination.

 

20.2    Annual Minimum Guarantee Cartage Rate - Small Trucks

 

(a)       This subclause applies on and from 1 January 2019, and only to the following classes of vehicle:

 

(i)       Rigid - carrying capacity over 2 and including 5 tonnes; and

 

(ii)      Rigid - carrying capacity over 5 and including 8 tonnes.

 

(b)      50 x 50 Arrangement - Subject to this subclause and subclause (c), if a Principal Contractor makes an agreement in writing with a Contract Carrier for a minimum of 50 hours each week for 50 weeks for a 12 month period, or periods, the Principal Contractor may pay the Contract Carrier 90% of the "Per Hour" rate in Schedule A Table A.1.1 or A.2.1 (whichever is applicable to the Contract Carrier’s Vehicle) for each hour that the Contract Carrier performs the Cartage Work during that period.

 

(c)       Subject to subclause (d), with respect to Contract Carriers engaged as at 31 December 2018, a Principal Contractor may utilise a 50 x 50 Arrangement of the kind described in subclause (b) where the Contract Carrier has been engaged by the Principal Contractor for a minimum of 50 hours each week for 50 weeks in the previous 12 month period (Existing Tied Contract Carrier), notwithstanding that there is no agreement in writing between the Principal Contractor and the Contract Carrier to that effect.

 

(d)      Where a Principal Contractor that engages an Existing Tied Contract Carrier wishes to utilise a 50 x 50 Arrangement in circumstances described in sub clause (c):

 

(i)       the Principal Contractor shall advise the Existing Tied Contract Carrier in writing of the Principal Contractor’s intention to utilise a 50 x 50 Arrangement. The notice shall include as a minimum:

 

(A)      the date from which the Principal Contractor intends to utilise a 50 x 50 Arrangement, which shall be at least 8 weeks prior to its commencement; and

 

(B)      the 12 month period, or periods, during which the Principal Contractor will apply those provisions; and

 

(C)      advising the Existing Tied Contract Carrier that they have 4 weeks from the receipt of the Principal Contractor’s notice to elect not to adopt a 50 x 50 Arrangement. If the Existing Tied Contract Carrier elects not to adopt a 50 x 50 arrangement, which election not to adopt must not be unreasonable, they must give the Principal Contractor a written notice of election to that effect;

 

(ii)      within 4 weeks of receiving the Existing Tied Contract Carrier’s notice of election, the Principal Contractor must either consent to or refuse the election, but must not unreasonably so refuse; and

 

(iii)     if the Principal Contractor consents to the election, a 50 x 50 Arrangement will not apply to the Existing Tied Contract Carrier.

 

(e)       Nothing in this subclause affects an obligation of a Principal Contractor to pay the per/km rate applicable in Schedule A Tables A.1.1 or A.2.1, or any of the rates in clauses A3,A4, A5 or A6 for the Cartage Work.

 

(f)       Minimum Earnings Guarantee - Reconciliation: If clause 20.2(b) or (c) applies to a Contract of Carriage and in an 8 week period the Contract Carrier has not worked at least 50 hours each week for whatever reason, then:

 

(i)       the Principal Contractor must ensure that the Contract Carrier receives an amount of pay (excluding any payment arising from the per/km rates in Schedule A Tables A.1.1 or A.2.1, or from any of the rates in clauses A3, A4, A5 or A6 equivalent to the Minimum Earnings Guarantee.

 

(ii)      If there is any shortfall between the amount of pay paid to the Contract Carrier (excluding any payment arising from the per/km rates in Schedule A clauses A.1.1 or A.2.1, or from any of the rates in clauses A3, A4, A5 or A6 and the Minimum Earnings Guarantee, the Principal Contractor must pay the shortfall to the Contract Carrier in the Principal Contractor’s next pay cycle.

 

(g)      Minimum Earnings Guarantee - Calculation: The Minimum Earnings Guarantee is calculated using the following formula:

 

(i)       (per hour rate from Table A.1.1 x 90%) x ((50 x 8) minus Unavailable Hours) for Vehicles less than six years old; or

 

(ii)      (per hour rate from Table A.2.1 x 90%) x ((50 x 8) minus Unavailable Hours) for Vehicles six or more years old.

 

(h)      "Unavailable Hours" are those hours that the Contract Carrier’s Vehicle is unavailable to perform the Cartage Work during the hours the Contract Carrier is required to make their Vehicle available in accordance with clause 20.2(b) above.

 

(i)       Early Termination of 50 x 50 Arrangement:

 

Where a Principal Contractor decides to terminate a 50 x 50 Arrangement prior to the expiration of the relevant 12 month period the Principal Contractor:

 

(i)       will notify the Contract Carrier in writing of its intention to terminate the 50 x 50 Arrangement. The notice will specify the date upon which the 50 x 50 Arrangement will terminate, which shall be no fewer than 4 weeks after the date of the notice; and

 

(ii)      will pay the Contract Carrier either:

 

(A)      the difference in remuneration the Contract Carrier would have earned had a 50 x 50 Arrangement not been entered into under this Part 4 for the relevant period, but capped at 50 hours per week; or

 

(B)      the difference in remuneration between what the Contract Carrier earns for the remainder of the relevant 12 month period (or periods) and what the Contract Carrier would have earned had the 50 x 50 Arrangement, entered into under this Part 4, not been terminated,

 

whichever is the lesser amount.

 

NOTE: The 50 x 50 Arrangement takes into account Unavailable Hours.

 

(j)       Termination of Engagement during 50 x 50 Arrangement:

 

Where a Principal Contractor terminates the engagement of a Contract Carrier to whom a 50 x 50 Arrangement applies, prior to the expiration of the relevant 12 month period (or periods), the Principal Contractor will pay to the Contract Carrier the difference in remuneration the Contract Carrier would have earned had a 50 x 50 Arrangement not been entered into under this Part 4 for the relevant period, but capped at 50 hours per week.

 

However this subclause will not apply in the case of a termination for misconduct (which misconduct will not be limited by clause 1.1), or a termination in circumstances where the Contract Carrier is entitled to the benefits of the Transport Industry - Redundancy (State) Contract Determination.

 

(k)      50 x 50 Arrangement not a Common Law Contract: For the avoidance of doubt, any arrangement made under this Part will not be construed as being, or forming, part of any common law contract or arrangement, collateral or otherwise, whether written or oral, which may exist between a Principal Contractor and a Contract Carrier with respect to Cartage Work to which this Determination applies.

 

(l)       Early Termination of 50 x 50 Arrangement - Reconciliation: the payment referred to in clause 20.2(i)(ii)(A) or (B) is to be calculated every 8 weeks, or part thereof, for the reminder of the relevant 12 month period (or periods).

 

20.3    The Rates will be varied in accordance with the procedure set out in Schedule C.

 

20.4    Introduction of Light Vehicle Rates

 

(a)       In matters 2019/268320, 2020/112760, 2020/112849 and 2020/133735, the IRC introduced new minimum rates applicable to Light Vehicles.

 

(b)      Subject to subclause 20.4(d), the Light Vehicle Rates set out in Schedule A include compensation for all fixed and running costs that may be incurred by a Contract Carrier.

 

(c)       The Light Vehicle Rates set out in Schedule A are to be increased if the charge percentage (as set out in the Superannuation Guarantee (Administration) Act 1992) increases above 10%. The Light Vehicle Rates in Schedule A shall be increased by 0.25% for each 0.5 percentage point increase to the charge percentage.

 

20.5    Subject to Schedule E, the cartage rates contained in this contract determination compensate contract carriers for the cost of contributing to their superannuation.

 

21.  Alternative Remuneration Arrangements

 

21.1    Despite clause 20, a Principal Contractor may pay a Contract Carrier based on a system or method of remuneration different to that required by clause 20 (an Alternative Remuneration Arrangement), provided that the Contract Carrier receives, over a sixty-day period, no less than the pay they would otherwise have received had they been paid in accordance with clause 20.1 for that period.

 

21.2    An Alternative Remuneration Arrangement must be in writing and:

 

(a)       be signed by the Contract Carrier and the Principal Contractor; and

 

(b)      identify the start date of the Alternative Remuneration Arrangement; and

 

(c)       require the Principal Contractor to undertake an assessment of the amount received by the Contract Carrier under the Alternative Remuneration Arrangement every sixty-days from the identified start date to ensure the Alternative Remuneration Arrangement complies with clause 21.1.

 

21.3    Where the amount paid to a Contract Carrier under an Alternative Remuneration Arrangement in a sixty- day period is less than the pay they would have received had they been paid in accordance with clause 20 for that period, the Principal Contractor shall pay an amount (the Top Up Amount) to the Contract Carrier to make up that difference.

 

21.4    The Top Up Amount is to be paid within the next pay cycle.

 

22.  Mass Management

 

22.1    If the Principal Contractor so directs, the Contract Carrier must do all things required and necessary to be accredited and remain accredited under:

 

(a)       the Principal Contractor’s accredited NHVAS Mass Management Module for Basic Fatigue Management or Advanced Fatigue Management (or any scheme replacing this); or

 

(b)      a NHVAS Mass Management Module for Basic Fatigue Management or Advanced Fatigue Management of the Contract Carrier.

 

22.2    In circumstances where clause 22.1 applies the Principal Contractor must reimburse the Contract Carrier for any reasonable costs directly arising from becoming accredited or at their election pay the lump sum allowance set out in clause A.4.2 of Schedule A to set up for the NHVAS Mass Management Scheme for Basic Fatigue Management or Advanced Fatigue Management.

 

22.3    In circumstances where clause 22.1 applies the Principal Contractor must reimburse the Contract Carrier for any reasonable costs directly arising from maintaining accreditation or at their election pay the allowance set out in clause A.4.3 of Schedule A per hour to cover costs associated with maintaining that NHVAS Mass Management Scheme for Basic Fatigue Management or Advanced Fatigue Management.

 

22.4    To avoid any doubt clause 22.2 and/or 22.3 shall not apply if the Contract Carrier has made their own decision to become and work under an accredited NHVAS Mass Management Scheme for Basic Fatigue Management or Advanced Fatigue Management.

 

23.  Three Yearly Cost Reconciliation Review

 

23.1    Reconciliation

 

Subject to an application being made to apply the Three Yearly True Cost reconciliation Review Process, the price entries in the "Price Table" and the table "Trailers" of the Key Data Variables sheet contained in the Cost Model should be updated using sourcing that are relevant to and reflect the cartage work being performed and such prices should reflect the lowest price available from a reputable vendor which is accessible to Contract Carriers in the open market.

 

23.2    Operative Date

 

Any rates shall be operative from such date as is determined by the Commission having regard to the need to inform Principal Contractors and Contract Carriers of any change.

 

23.3    This clause does not apply in relation to Light Vehicle Rates.

 

24.  Tolls & Charges

 

24.1    A Principal Contractor shall pay road tolls incurred by a Contract Carrier in the performance of Cartage Work for the Principal Contractor as a consequence of any mandatory legal obligations upon commercial vehicles to:

 

(a)       use certain toll roads; or

 

(b)      avoid certain roads including light limit roads which has the result of requiring the use of a toll road.

 

24.2    In all other circumstances, a Principal Contractor shall pay road tolls incurred by a Contract Carrier in the performance of Cartage Work for the Principal Contractor unless the Principal Contractor expressly directs the Contract Carrier in writing to not use a toll road.

 

An express direction may include:

 

(a)       a standing written direction issued by the Principal Contractor to Contract Carriers on an enterprise or fleet basis; or

 

(b)      individual written directions issued by the Principal Contractor to Contract Carriers.

 

24.3    This clause does not apply:

 

(a)       if the Principal Contractor can demonstrate that it already pays the Contract Carrier under an arrangement which factors in the payment of current road tolls, including by way of an alternative remuneration arrangement pursuant to clause 21; or

 

(b)      to a Principal Contractor and their Contract Carriers performing Ca1iage Work under a contract agreement that was approved by the Commission during the period of on or after 1 January 2018 and up to and including 5 February 2021.

 

For the avoidance of doubt, the exclusion provided for by 25.3(b) will not apply to any contract agreement that is approved or varied by the Commission after 5 February 2021.

 

24.4    The payment of a road toll can be made by a Principal Contractor:

 

(a)       in the next pay cycle following the Contract Carrier providing a receipt to the Principal Contractor; or

 

(b)      by providing the Contract Carrier with an E-Tag.

 

PART 5 - MISCELLANEOUS

 

26.  Disputes Procedure

 

25.1    Application of Procedure

 

Any dispute that arises between a Contract Carrier and a Principal Contractor must be dealt with in accordance with this clause.

 

25.2    Appointment of Representative

 

A Contract Carrier who is a party to a dispute may appoint a representative for the purposes of this clause which may include the Union.

 

25.3    Procedure

 

In the first instance, the parties to the dispute must try to resolve the dispute at the workplace level.

 

25.4    Notification to Commission

 

If the dispute remains unresolved it may be referred to the IRC.

 

25.5    Continue to Perform Cartage Work

 

Whilst the parties are trying to resolve the dispute using the procedure set out in this clause:

 

(a)       Contract Carrier must continue to perform Cartage Work as they normally would do unless they hold a reasonable concern about an imminent risk to their health or safety; and

 

(b)      a Contract Carrier must comply with a direction given by their Principal Contractor to perform other available Cartage Work, unless:

 

(i)       the Cartage Work is not safe; or

 

(ii)      applicable workplace health and safety legislation would not permit the Cartage Work to be performed; or

 

(iii)     the Cartage Work is not appropriate for the Contract Carrier to perform; or

 

(iv)     there are other reasonable grounds for the Contract Carrier to refuse to comply with the direction.

 

26.  Union Delegates

 

26.1    Appointment

 

A Contract Carrier appointed Delegate in a yard in which they are Contract Carrier must, upon notification to their Principal Contractor, be recognised as the accredited representative of the Union.

 

26.2    Opportunity to Meet

 

An accredited Delegate must be allowed a reasonable opportunity to meet the relevant manager of the Principal Contractor and Contract Carriers to discuss matters affecting Contract Carriers whom they represent.

 

26.3    Use of Notice Board

 

Accredited Delegates must be permitted to put Union notices on a notice board, signed or countersigned by the representative posting it.

 

27.  Record Keeping

 

27.1    Obligations

 

The Principal Contractor must record either in documentary form or electronic form, the following information for each Contract Carrier:

 

(a)       any Cartage Rate Schedule;

 

(b)      start and finish times;

 

(c)       hours worked per day;

 

(d)      kilometres travelled per day;

 

(e)       Starting Place and Finishing Place;

 

(f)       remuneration paid; and

 

(g)      a copy of any written contract entered into with the Contract Carrier; and

 

(h)      all trip schedules and driver rosters; and

 

(i)       all safe driving plans and risk assessments that relate to the fatigue of road transport drivers; and

 

(j)       all reported breaches and suspected breaches of the fatigue management law, including breaches and suspected breaches identified by the Principal Contractor; and

 

(k)      all breaches of fatigue management laws investigated by the Principal Contractor, the outcome and any remedial action taken.

 

27.2    Maintenance of Records

 

The Principal Contractor must maintain all the records arising from clause 28.1 for a period of seven years.

 

27.3    Contract Carrier to Assist

 

(a)       A Contract Carrier must do all things reasonably directed by the Principal Contractor to gather and record the information referred to in clause 28.1.

 

(b)      A Principal Contractor must not be liable for breach of this clause 28 because of the failure of a Contract Carrier to comply with clause (a).

 

28.  Leave Reserved

 

(a)       Leave is reserved to any party covered by this Determination to make an application to vary the conditions or rates of pay for "Long Distance Work" within the meaning of clause 13 of the Transport Industry (State) Award (Serial C7740).

 

(b)       Leave is reserved to any party covered by this Determination to apply to vary the application of this Determination in respect of the transport of pre-fabricated construction materials to and from construction sites.

 

SCHEDULE A - RATES OF REMUNERATION

 

NOTE: The rates of remuneration in this Schedule apply to Contracts of Carriage covered by Part 4 of this Determination.

 

A.1      Hourly and kilometre rates (other than for Light Vehicles) - new vehicles

 

A.1.1  A contract carrier performing work using a vehicle which is less than six years old must be paid at least the hourly and kilometre rates set out in the following table (rounded up to the nearest half hour, nearest kilometre and nearest cent). For the avoidance of confusion, the per kilometre rate payable is the Running Rate. The Running Rate is the total of the "Per km excluding fuel component" and the "Per km fuel component". The "Per km excluding fuel component" and the "Per km fuel component" columns have been included for ease of reference when updating rates.

 

From the first full pay period commencing on or after 12 February 2024:

 

Class of Vehicle

Per hour

Running Rate

Per km excluding fuel component running rate for the purposes of Schedule C

Per km fuel component of the running rate for the purposes Schedule C

($)

($/km)

($/km)

($/km)

Rigid-carrying capacity over 3 and including 5 tonnes

$55.15

$0.29

$0.12

$0.17

Rigid-carrying capacity 5 and including 8 tonnes

$62.83

$0.33

$0.14

$0.19

Rigid-carrying capacity over 8 and including 10 tonnes

$70.79

$0.44

$0.15

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$72.36

$0.48

$0.19

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$73.04

$0.47

$0.19

$0.28

Rigid-carrying capacity over 14 tonnes or more

$77.30

$0.57

$0.21

$0.36

Single Axle Prime Mover

$78.54

$0.54

$0.15

$0.38

Bogie Axle Prime Mover

$84.93

$0.66

$0.20

$0.46

 

From the first full pay period commencing on or after 10 November 2023:

 

Class of Vehicle

Per hour

Running Rate

Per km excluding fuel component running rate for the purposes of Schedule C

Per km fuel component of running rate for the purposes of Schedule C

($)

($/km)

($/km)

($/km)

Rigid-carrying capacity over 3 and including 5 tonnes

$52.15

$0.29

$0.12

$0.17

Rigid-carrying capacity over 5 and including 8 tonnes

$59.43

$0.32

$0.13

$0.19

Rigid-carrying capacity over 8 and including 10 tonnes

$66.95

$0.43

$0.15

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$68.43

$0.47

$0.19

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$69.07

$0.46

$0.18

$0.28

Rigid-carrying capacity over 14 tonnes or more

$73.12

$0.56

$0.20

$0.36

Single Axle Prime Mover

$74.28

$0.53

$0.15

$0.38

Bogie Axle Prime Mover

$80.30

$0.65

$0.19

$0.46

 

A.2      Hourly and kilometre rates (other than for Light Vehicles) - not new vehicles

 

A.2.1  A contract carrier performing work using a vehicle which is six or more years old must be paid at least the hourly and kilometre rates set out in the following table (rounded up to the nearest half hour, and nearest kilometre). For the avoidance of confusion, the per kilometre rate payable is the Running Rate. The Running Rate is the total of the "Per km excluding fuel component" and the "Per km fuel component". The "Per km excluding fuel component" and the "Per km fuel component" columns have been included for ease of reference when updating rates.

 

From the first full pay period commencing on or after 12 February 2024:

 

Class of Vehicle

Per hour

Running Rate

Per km excluding fuel component running rate for the purposes of Schedule C

Per km fuel component of the running rate for the purposes of Schedule C

($)

($/km)

($/km)

($/km)

Rigid-carrying capacity over 3 and including 5 tonnes

$50.96

$0.37

$0.20

$0.17

Rigid-carrying capacity over 5 and including 8 tonnes

$56.75

$0.42

$0.23

$0.19

Rigid-carrying capacity over 8 and including10 tonnes

$60.64

$0.51

$0.23

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$66.78

$0.56

$0.28

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$66.62

$0.55

$0.27

$0.28

Rigid-carrying capacity over 14 tonnes or more

$67.92

$0.65

$0.29

$0.36

Single Axle Prime Mover

$64.33

$0.59

$0.23

$0.36

Bogie Axle Prime Mover

$69.51

$0.72

$0.28

$0.44

 

From the first full pay period commencing on or after 10 November 2023:

 

Class of Vehicle

Per hour

Running Rate

Per km excluding fuel component running rate for the purposes of Schedule C

Per km fuel component of the running rate for the purposes of Schedule C

($)

($/km)

($/km)

($/km)

Rigid-carrying capacity over 3 and including 5 tonnes

$48.17

$0.36

$0.19

$0.17

Rigid-carrying capacity over 5 and including 8 tonnes

$53.65

$0.41

$0.21

$0.19

Rigid-carrying capacity over 8 and including10 tonnes

$57.32

$0.50

$0.22

$0.28

Rigid-carrying capacity over 10 and including 12 tonnes

$63.13

$0.55

$0.27

$0.28

Rigid-carrying capacity over 12 and including 14 tonnes

$62.98

$0.54

$0.25

$0.28

Rigid-carrying capacity over 14 tonnes or more

$64.21

$0.64

$0.28

$0.36

Single Axle Prime Mover

$60.78

$0.58

$0.22

$0.36

Bogie Axle Prime Mover

$65.67

$0.71

$0.27

$0.44

 

A.3      Light Vehicle Rates

 

A.3.1  A Contract Carrier performing work with a Light Vehicle must be paid at least the hourly rate set out in the following table (rounded up the nearest half hour).

 

From the first full pay period commencing on or after 1 March 2022:

 

Class of Vehicle

Per hour

$

Bicycle

$21.82

Motorcycles

$26.85

Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity of:

 

Up to 750kg

$29.85

Over 750kg and up to 1 tonne

$30.68

Over 1 tonne and up to 1.5 tonnes

$31.06

Over 1.5 tonnes and up to 3 tonnes

$32.71

 

From the first full pay period commencing on or after 1 July 2022:

 

Class of Vehicle

Per hour

$

Bicycle

$24.19

Motorcycles

$28.78

Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity of:

 

Up to 750kg

$31.84

Over 750kg and up to 1 tonne

$32.80

Over 1 tonne and up to 1.5 tonnes

$33.55

Over 1.5 tonnes and up to 3 tonnes

$35.47

 

From the first full pay period commencing on or after 1 July 2023:

 

Class of Vehicle

Per hour

$

Bicycle

$26.57

Motorcycles

$30.70

Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity of:

 

Up to 750kg

$33.82

Over 750kg and up to 1 tonne

$34.91

Over 1 tonne and up to 1.5 tonnes

$36.05

Over 1.5 tonnes and up to 3 tonnes

$38.22

 

From the first full pay period commencing on or after 1 July 2024:

 

Class of Vehicle

Per hour

$

Bicycle

$28.94

Motorcycles

$32.63

Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity of:

 

Up to 750kg

$35.81

Over 750kg and up to 1 tonne

$37.03

Over 1 tonne and up to 1.5 tonnes

$38.54

Over 1.5 tonnes and up to 3 tonnes

$40.98

 

From the first full pay period commencing on or after 1 July 2025:

 

Class of Vehicle

Per hour

$

Bicycle

$31.32

Motorcycles

$34.56

Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity of:

 

Up to 750kg

$37.80

Over 750kg and up to 1 tonne

$39.15

Over 1 tonne and up to 1.5 tonnes

$41.04

Over 1.5 tonnes and up to 3 tonnes

$43.74

 

NOTE: These Light Vehicle Rates are subject to any increases arising from changes to the superannuation guarantee charge percentage. See subclause 20.8(e) for details.

 

A.4      NHVR Training and Accreditation

 

A.4.1  NHVR Training and Accreditation System Set Up

 

A.4.2  The lump sum allowance referred to in clause 22.2 is:

 

(a)       From the first full pay period commencing on or after 12 February 2024:

 

$7,992.18; and

 

(b)       From the first full pay period commencing on or after 10 November 2023:

 

$7,619.78.

 

A.4.3  The allowance referred to in clause 22.3 is (rounded up to the nearest half hour):

 

From the first full pay period commencing on or after 12 February 2024:

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.48

Single Axle Prime Mover

$0.48

Rigid-carrying capacity over 14 tonnes or more

$0.48

Rigid-carrying capacity over 12 and including 14 tonnes

$0.48

Rigid-carrying capacity over 10 and including 12 tonnes

$0.48

Rigid-carrying capacity over 8 and including 10 tonnes

$0.48

Rigid-carrying capacity over 5 and including 8 tonnes

$0.48

Rigid-carrying capacity over 3 and including 5 tonnes

$0.48

Rigid-carrying capacity less than 3 tonnes

$0.48

 

From the first full pay period commencing on or after 10 November 2023;

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.46

Single Axle Prime Mover

$0.46

Rigid-carrying capacity over 14 tonnes or more

$0.46

Rigid-carrying capacity over 12 and including 14 tonnes

$0.46

Rigid-carrying capacity over 10 and including 12 tonnes

$0.46

Rigid-carrying capacity over 8 and including 10 tonnes

$0.46

Rigid-carrying capacity over 5 and including 8 tonnes

$0.46

Rigid-carrying capacity over 3 and including 5 tonnes

$0.46

Rigid-carrying capacity less than 3 tonnes

$0.46

 

A.5      Blue Card

 

A.5.1  A Contract Carrier who in order to perform a Contract of Carriage is required to obtain a blue card (or equivalent), after this Determination has come into operation, shall be paid the following amounts (rounded up to the nearest half hour):

 

From the first full pay period commencing on or after 12 February 2024:

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.05

Single Axle Prime Mover

$0.05

Rigid-carrying capacity over 14 tonnes or more

$0.05

Rigid-carrying capacity over 12 and including 14 tonnes

$0.05

Rigid-carrying capacity over 10 and including 12 tonnes

$0.05

Rigid-carrying capacity over 8 and including 10 tonnes

$0.05

Rigid-carrying capacity over 5 and including 8 tonnes

$0.05

Rigid-carrying capacity over 2 and including 5 tonnes

$0.05

Rigid-carrying capacity less than 3 tonnes

 

 

From the first full pay period commencing on or after 10 November 2023:

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.05

Single Axle Prime Mover

$0.05

Rigid-carrying capacity over 14 tonnes or more

$0.05

Rigid-carrying capacity over 12 and including 14 tonnes

$0.05

Rigid-carrying capacity over 10 and including 12 tonnes

$0.05

Rigid-carrying capacity over 8 and including 10 tonnes

$0.05

Rigid-carrying capacity over 5 and including 8 tonnes

$0.05

Rigid-carrying capacity over 2 and including 5 tonnes

$0.05

Rigid-carrying capacity less than 3 tonnes

 

 

A.5.2  However, a Principal Contractor will not be required to make any such payment in circumstance where the Principal Contractor has previously paid for a Contract Carrier to obtain the appropriate blue card (or equivalent).

 

A.6      Workwear and PPE

 

A.6.1  A Contract Carrier who, in order to perform a contract of carriage, is required by a Principal Contractor to wear certain type of workwear and/or personal protective equipment shall be paid the following amounts:

 

From the first full pay period commencing on or after 12 February 2024:

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.33

Single Axle Prime Mover

$0.33

Rigid-carrying capacity over 14 tonnes or more

$0.33

Rigid-carrying capacity over 12 and including 14 tonnes

$0.33

Rigid-carrying capacity over 10 and including 12 tonnes

$0.33

Rigid-carrying capacity over 8 and including 10 tonnes

$0.33

Rigid-carrying capacity over 5 and including 8 tonnes

$0.33

Rigid-carrying capacity over 2 and including 5 tonnes

$0.33

Rigid-carrying capacity less than 3 tonnes

 

 

From the first full pay period commencing on or after 10 November 2023:

 

Class of Vehicle

Per hour

$

Bogie Axle Prime Mover

$0.31

Single Axle Prime Mover

$0.31

Rigid-carrying capacity over 14 tonnes or more

$0.31

Rigid-carrying capacity over 12 and including 14 tonnes

$0.31

Rigid-carrying capacity over 10 and including 12 tonnes

$0.31

Rigid-carrying capacity over 8 and including 10 tonnes

$0.31

Rigid-carrying capacity over 5 and including 8 tonnes

$0.31

Rigid-carrying capacity over 2 and including 5 tonnes

$0.31

Rigid-carrying capacity less than 3 tonnes

 

 

A.6.2  A Principal Contractor will not be required to make any such payment in circumstance where the Principal Contractor provides the Contract Carrier with the certain type of workwear and/or personal protective equipment

 

A.7      Additional amounts

 

A.7.1  Ropes and Gear Allowance

 

A Contract Carrier who, in order to perform a contract of carriage, is required to supply tarpaulins, ropes, gates, chains and dogs for use in a Contract of Carriage must be paid the following allowance per day or part day during which the equipment is used for the purpose of the Contract of Carriage:

 

(a)       From the first full pay period on or after 12 February 2024: $5.01

 

(b)       From the first full pay period on or after 10 November 2023: $4.78

 

A.7.2  Twistlock Allowance

 

A Contract Carrier who, in order to perform a Contract of Carriage, is required to fit his trailer with twistlocks for the carriage of I.S.O. containers must be paid the following allowance per day or part day during which the equipment is used for the purpose of the Contract of Carriage:

 

(a)       From the first full pay period commencing on or after 12 February 2024: $3.76

 

(b)       from the first full pay period commencing on or after 10 November 2023: $3.58

 

A.7.3  Mechanical Lifting Equipment Allowance

 

A Contract Carrier who, in order to perform a contract of carriage, is required to supply rear or side- loading mechanical devices, shall be paid the following allowance for each day (and proportionately for part of a day) during which the equipment is used for the purpose of the Contract of Carriage:

 

From the first full pay period commencing on or after 12 February 2024:

 

Equipment type

Per day

$

Rear-Lift Platform up to and including 3,000 lbs capacity

$6.00

Rear-Lift Platform up to and including 6,000 lbs capacity

$8.24

Side loading device

$26.49

 

From the first full pay period commencing on or after 10 November 2023:

 

Equipment type

Per day

$

Rear-Lift Platform up to and including 3,000 lbs capacity

$5.72

Rear-Lift Platform up to and including 6,000 lbs capacity

$7.85

Side loading device

$25.26

 

SCHEDULE B - WATERFRONT AND CONTAINER DEPOTS

 

1.        The following conditions and allowances shall apply to contracts of carriage performed in or in connection with Container Depots and Waterfront areas, in addition to all other conditions provided for by this Contract Determination but in substitution for the rates in Schedule A.

 

From the first full pay period commencing on or after 12 February 2024:

 

Class of Vehicle

Rate

Rigid Vehicle

 

Not less than 8 and not greater than 10 tonnes

$67.85

Not less than 10 and not greater than 12 tonnes

$74.65

Not less than 12 and not greater than 14 tonnes

$74.29

Not less than 14 tonnes

$77.06

Single Axle Prime Mover

$72.65

Bogie Axle Prime Mover

$79.62

 

From the first full pay period commencing on or after 10 November 2023:

 

Class of Vehicle

Rate

Rigid Vehicle

 

Not less than 8 and not greater than 10 tonnes

$66.47

Not less than 10 and not greater than 12 tonnes

$72.92

Not less than 12 and not greater than 14 tonnes

$72.58

Not less than 14 tonnes

$75.86

Single Axle Prime Mover

$71.66

Bogie Axle Prime Mover

$78.88

 

The above rates of remuneration are calculated using the following formula:

 

(Hourly Rate x 221 x 7.6) + (Km Rate x 23,500)

(221 x 7.6)

where Hourly Rate and km Rate are the relevant per hour and per km rates for a 6 year+ vehicle in Schedule A - Rates of Remuneration.

 

This formula is based on a minimum distance travelled of 23,500 km per annum on contracts of carriage performed in or in connection with Container Depots and Waterfront areas.

 

2.        Trailer Allowance:

 

A Contract Carrier who, in order to perform a contract of carriage, is required to supply one of the trailers listed below (irrespective of axle configuration), shall be paid the following allowance for each day, (or part of a day) during the equipment is so used:

 

From the first full pay period commencing on or after 12 February 2024:

 

 

Rate A - Subsidy

Rate B - No Subsidy

40 ft Skel trailer

$58.60 per day

$59.80 per day

40 ft General Purpose trailer

$58.60 per day

$62.98 per day

Dog or Pig trailer

$43.87 per day

$47.12 per day

Pup trailer

$29.29 per day

$31.48 per day

20 ft Skel trailer

$52.75 per day

$56.69 per day

 

From the first full pay period commencing on or after 10 November 2023:

 

 

Rate A - Subsidy

Rate B - No Subsidy

40 ft Skel trailer

$55.42 per day

$56.55per day

40 ft General Purpose trailer

$55.42per day

$59.55 per day

Dog or Pig trailer

$41.48 per day

$44.56 per day

Pup trailer

$27.70 per day

$29.77 per day

20 ft Skel trailer

$49.88 per day

$53.61 per day

 

3.        Towing rates:

 

A Contract Carrier, whose vehicle is in the performance of a contract of carriage, is required to tow one of the trailers listed below (irrespective of axle configuration), shall be paid the following allowance for each hour (pro-rata for part of an hour) during which such trailer is towed:

 

From the first full pay period commencing on or after 12 February 2024:

 

40 ft trailer

$3.37 per hour

$3.29 per hour

Dog/Pig trailer

$6.61 per hour

$6.44 per hour

Pup trailer

$4.88 per hour

$4.76 per hour

 

From the first full pay period commencing on or after 10 November 2023:

 

40 ft trailer

$3.19 per hour

$3.11 per hour

Dog/Pig trailer

$6.25 per hour

$6.09 per hour

Pup trailer

$4.61 per hour

$4.50 per hour

 

4.        Adjustment of the allowances and rates in Clause 3 and 4 of this Schedule shall be by application of the movement of the Consumer Price Index (All Groups), Sydney.

 

5.        Contract Carriers who perform work pursuant to this Schedule shall have paid on their behalf by principal contractors who are members of the NSW Road Transport Association contributions into the TWU Superannuation Fund in the amounts prescribed by the Transport Industry (State) Superannuation Award.

 

6.        Clause 3, Savings clause, of this Determination shall apply to the above rates and conditions.

 

SCHEDULE C - PROCEDURE AND TIME FOR ADJUSTMENTS OF RATES

 

C.1      Procedure for adjustment of rates

 

C.1.1   The rates prescribed in Schedules B and C shall be adjusted with effect from 1 June and 1 December each year or as provided in this Schedule.

 

C.1.2   The union shall make application to the IRC for a variation in rates and amounts in sufficient time for the variation to be made on or before 1 June and 1 December each year. Notwithstanding anything contained in this Schedule, a variation shall not be retrospective in operation but shall operate from a date not earlier than the date upon which it is made.

 

C.1.3   The parties to this determination shall confer with a view to reaching agreement on the variation. In the absence of agreement, the rates and amounts shall be determined by the IRC in accordance with the Method of Adjustment outlined in this Schedule.

 

C.1.4   The adjustment to be made from 1 December shall take into account all movements in costs occurring and indices published up to the preceding 31 October and the adjustment from 1 June shall take into account all movements in costs occurring and indices published up to the preceding 30 April.

 

C.1.5   Each variation after the first variation shall be based upon the rates and amounts in the immediately preceding variation.

 

C.1.6   If any one of the below listed components, except for fuel, changes such that it causes an increase in the total remuneration of 5 per cent or more from the date of the last variation, an interim adjustment may be made.

 

C.1.7   The components of remuneration shall be adjusted upwards or downwards according to the following schedule:

 

Component

Method of Adjustment

1.  Total Labour Costs

Adjust according to the actual percentage change in the Minimum Weekly Rate for the relevant Transport Worker Grade in the Road Transport and Distribution Award 2010.

2.  Fuel

Adjust according to the percentage change in the Australian Institute of Petroleum NSW State weekly average for the retail price of diesel, excluding GST.

3.  Capital

Adjust by reference to the average percentage change in the TransEco Road Freight Cost Indices Report: Shorthaul cost change of Capital.

4. Service and Parts

Adjust by reference to the average percentage change in the TransEco Road Freight Cost Indices Report: Shorthaul cost change of Maintenance.

5.  Registration, Licensing and Insurances

Adjust by reference to the average percentage change in the TransEco Road Freight Cost Indices Report: Shorthaul cost change of Insurance.

6.  Training and compliance

Adjust by reference to the average percentage change in the TransEco Road Freight Cost Indices Report: Shorthaul cost change of Admin.

7.  Miscellaneous Fixed Costs

Adjust by reference to the average percentage change in the TransEco Road Freight Cost Indices Report: Shorthaul cost change of Admin.

 

C.1.8   The procedure outlined in subclause E.1 does not apply to Light Vehicle Rates.

 

C.2      Cost Recovery for variations in the Price of fuel

 

C.2.1   Due to the changeable nature of the pricing of fuel, including significant fluctuations in the price of fuel, it is necessary that variations to rates of remuneration to take into account changes in the price of fuel occur in a timely and efficient manner.

 

C.2.2   Any party to this determination may make an application to the IRC to vary rates of remuneration to account for changes in the price of fuel on the following basis:

 

(a)       an application to vary rates of remuneration for changes in the price of fuel may be made at any time, provided that the date upon which any rate adjustment is sought to become operative is at least one calendar month after the last occasion upon which a fuel rate adjustment became operative;

 

(b)       it is not a requirement of any such application that the rate adjustment sought for fuel only be one which is either below or above any minimum threshold amount; and

 

(c)       the benchmark for the price of fuel shall be the Australian Institute of Petroleum NSW weekly average for the retail price of diesel for the week ending immediately prior to the date of filing the application, excluding GST.

 

C.2.3   The parties to this determination shall take all necessary steps to enable an application made pursuant to this Schedule to be heard and determined at the earliest possible time, including but not limited to, consenting to have the IRC hear and determine any such application within 48 hours from the initial listing of the application.

 

SCHEDULE D - NOMINATED CONTRACT DETERMINATION

 

The Nominated Contract Determinations are:

 

1.              Transport Industry - Car Carriers (N.S.W.) Contract Determination;

2.              Transport Industry - Concrete Haulage Contract Determination;

3.              Transport Industry - Excavated Materials Contract Determination;

4.              Transport Industry - Quarried Materials Contract Determination;

5.              Transport Industry - Waste Collection and Recycling Contract Determination;

6.              Hanson Construction Materials Pty Limited Concrete Carriers Contract Determination;

7.              Transport Industry - Courier and Taxi Truck Contract Determination;

8.              Transport Industry - Concrete Haulage - Mini Trucks Contract Determination;

9.              Transport Industry - Readymix Holdings Pty Ltd Concrete Cartage Contract Determination;

10.           Boral Transport Limited Haulier Contract Determination;

11.           CEVA Logistics (Australia) Pty Ltd (NSW Vehicle Logistics Local Fleet) Contract Determination;

12.           Readymix Holding Pty Ltd Sydney Concrete Carriers Contract Determination;

13.           Readymix Holdings Pty Ltd Country Concrete Carriers Contract Determination;

14.           Transport Industry - Quarried Materials, &c., Carriers Interim Contract Determination;

15.           Australian Liquor Marketers Pty Limited Carriers Contract Determination;

16.           Boral Country - Concrete and Quarries Contract Determination;

17.           Boral Resources (NSW) Pty Limited Sydney Metropolitan Concrete Contract Determination;

18.           Transport Industry - Metromix Concrete Haulage Contract Determination;

19.           Transport Industry - Allied Express TWU Interim Contract Determination;

20.           Couriers Please Pty Ltd Contract Determination;

21.           Transport Industry - Mayne Logistics Contract Determination;

22.           Transport Industry - Penrith City Council Contract Determination;

23.           Boral GST Protocol (Facilitation and Compliance) Contract Determination;

24.           TNT Domestic & International Express Ancillary Contract Determination, The;

25.           Superior Premix Contract Determination No. 2;

26.           Superior Premix Contract Determination - Blacktown City Council Project;

27.           Transport Industry - General Carriers (The Smith Family) Contract Determination;

28.           Boral Transport Limited Quarried Materials Minimum Load Contract Determination; and

29.           Monier Roofing Limited and Reliance Roof Tiles Pty Ltd Contract Determination.

 

SCHEDULE E - SUPERANNUATION CONTRIBUTION ARRANGEMENTS

 

This Schedule is intended to ensure Principal Contractors are not subject to the cost of both providing rates that compensate for superannuation costs and separately making contributions upon a contract carrier’s behalf.

 

E.1      ARRANGEMENT BY AGREEMENT

 

E.1.1   A Principal Contractor and Contract Carrier may enter an arrangement whereby the Principal Contractor makes superannuation contributions for the benefit of the Contract Carrier.

 

E.1.2   A Principal Contractor may deduct from any remuneration payable to the Contract Carrier an amount no greater than the contributions that the Principal Contractor is required to make under such an arrangement.

 

E.2      Any such arrangement must be reduced to writing and must set out:

 

E.2.1   the amount of the contribution (whether as a fixed amount, a percentage of the Contract Carriers remuneration, or a combination of both);

 

E.2.2   in what period the contributions will be made (monthly, quarterly etc.); and

 

E.2.3   when the deductions are to be made.

 

E.3      Within 28 days of making superannuation contributions for a Contract Carrier’s benefit, the Principal Contractor must provide the Contract Carrier with a written statement setting out the amount of contributions made and the account into which they have been paid.

 

E.4      ARRANGEMENT BY DIRECTION

 

E.4.1   A Principal Contractor may implement a superannuation arrangement without the agreement of a Contract Carrier if:

 

E.4.2   the Contract Carrier is not an incorporated entity; and

 

E.4.3   the Principal Contractor has a reasonably held belief that the payment of superannuation contributions for the benefit of the Contract Carrier is required to reduce a Superannuation Guarantee Charge liability that would otherwise accrue to the Principal Contractor.

 

E.5      An arrangement entered into in accordance with subclause 2.1 is subject to the following terms:

 

E.5.1   any deductions from a Contract Carrier’s remuneration must be made in the same pay period for which the Contract Carrier is remunerated for the relevant cartage work;

 

E.5.2   superannuation contributions must be made no later than 28 days after the end of the quarter in which the relevant cartage work was performed; and

 

E.5.3   superannuation contributions must be paid into:

 

(a)       a complying superannuation fund chosen by the Contract Carrier;

 

(b)       the Contract Carrier's stapled superannuation fund (if the Contract Carrier does not choose a fund or if the Principal Contractor is not able to make contributions to the chosen fund); or

 

(c)       TWUSuper (in the absence of a chosen or stapled superannuation fund into which the Principal Contractor can make contributions).

 

E.6      Within 28 days of making superannuation contributions for a Contract Carrier’s benefit, the Principal Contractor must provide the Contract Carrier with a written statement setting out the amount of contributions made and the account into which they have been paid

 

E.7      Any disputes concerning the operation of this Schedule are to be dealt with using the dispute resolution procedures at clause 26.

 

SCHEDULE F - TEMPORARY FUEL SURCHAGE

 

F.1      APPLICATION

 

F.1.1   This Schedule applies to all Contracts of Carriage to which Part 4 of this Determination applies, other than Contracts of Carriage performed by a Light Vehicle.

 

F.2      BACKGROUND

 

F.2.1         This Schedule was introduced by the IRC in Matter No. 2022/77087 as a temporary measure to respond to significant fluctuations in the price of fuel arising from the war in Ukraine and the temporary inability for Contract Carriers to claim fuel tax credits.

 

F.3      THE SURCHARGE

 

F.3.1   In addition to all other amounts set out in this Determination, a Principal Contractor must pay a Contract Carrier an additional amount (the Temporary Fuel Surcharge).

 

F.3.2   For pay periods commencing between 19 February 2024 and 17 March 2024, the Temporary Fuel Surcharge shall be:

 

Vehicle Carrying Capacity

Surcharge (per km)

Rigid-carrying capacity over 3 and including 5 tonnes

$0.10

Rigid-carrying capacity over 5 and including 8 tonnes

$0.12

Rigid-carrying capacity over 8 and including 10 tonnes

$0.17

Rigid-carrying capacity over 10 and including 12 tonnes

$0.17

Rigid-carrying capacity over 12 and including 14 tonnes

$0.17

Rigid-carrying capacity over 14 tonnes or more

$0.22

Single Axle Prime Mover

$0.22

Bogie Axle Prime Mover

$0.27

 

For pay periods commencing between 15 January 2024 and 18 February 2024, the Temporary Fuel Surcharge shall be:

 

Vehicle Carrying Capacity

Surcharge (per km)

Rigid-carrying capacity over 3 and including 5 tonnes

$0.11

Rigid-carrying capacity over 5 and including 8 tonnes

$0.13

Rigid-carrying capacity over 8 and including 10 tonnes

$0.19

Rigid-carrying capacity over 10 and including 12 tonnes

$0.19

Rigid-carrying capacity over 12 and including 14 tonnes

$0.19

Rigid-carrying capacity over 14 tonnes or more

$0.25

Single Axle Prime Mover

$0.25

Bogie Axle Prime Mover

$0.30

 

F.3.3   Where Schedule C (which deals with waterfront and container depots) applies to a Contact of Carriage, the Principal Contractor may elect to pay the following Temporary Fuel Surcharge in lieu of the amount in clause 3.2:

 

For pay periods commencing between 19 February 2024 and 17 March 2024:

 

Vehicle Carrying Capacity

Surcharge (per km)

Rigid-carrying capacity over 8 and including 10 tonnes

$2.45

Rigid-carrying capacity over 10 and including 12 tonnes

$2.45

Rigid-carrying capacity over 12 and including 14 tonnes

$2.45

Rigid-carrying capacity over 14 tonnes or more

$3.14

Single Axle Prime Mover

$3.15

Bogie Axle Prime Mover

$3.82

 

For pay periods commencing between 15 January 2024 and 18 February 2024:

 

Vehicle Carrying Capacity

Surcharge (per hour)

Rigid-carrying capacity over 8 and including 10 tonnes

$2.71

Rigid-carrying capacity over 10 and including 12 tonnes

$2.71

Rigid-carrying capacity over 12 and including 14 tonnes

$2.71

Rigid-carrying capacity over 14 tonnes or more

$3.47

Single Axle Prime Mover

$3.49

Bogie Axle Prime Mover

$4.23

 

F.4      REVIEW

 

F.4.1   The Temporary Fuel Surcharge shall be reviewed on a monthly basis.

 

F.4.2   The Temporary Fuel Surcharge shall be calculated by updating the fuel component of the Cost Model with the mean of all weekly retail diesel prices (NSW State Average) published by the Australian Institute of Petroleum for weeks ending in the prior calendar month.

 

F.4.3   Parties shall calculate the Temporary Fuel Surcharge and provide the results to the IRC by the second Monday of each calendar month.

 

F.4.4     The revised Temporary Fuel Surcharge will apply from the third Monday in each calendar month.

 

F.4.5   As the Temporary Fuel Surcharge responds to fluctuations in fuel prices, it may increase or decrease from time to time.

 

F.5      OTHER PROVISIONS

 

F.5.1   The Temporary Fuel Surcharge may be offset by any payments made to a Contract Carrier in excess of the amounts prescribed elsewhere in this Determination.

 

F.5.2   Leave is reserved for any party to apply to vary the operation of this Schedule in circumstances where the Principal Contractor:

 

(a)       provides the Contract Carrier with fuel, either for free or at a cost below the prevailing market rate;

 

(b)       directly reimburses the Contract Carrier for some or all of their fuel costs; or

 

(c)       otherwise compensates the Contract Carrier for their fuel costs.

 

 

 

____________________

 

 

Printed by the authority of the Industrial Registrar.

 

* to download attachment
  
IE UsersRight click the attachment - Click 'Save Target As' - Select a location - Click 'Save'
Netscape UsersRight click the attachment - Select 'Save Link As' - Select a location - Click 'Save'