Transport Industry - General
Carriers Contract Determination 2017
AWARD REPRINT
This reprint of the
consolidated contract determination is published under the authority of the
Industrial Registrar pursuant to section 390 of the Industrial Relations Act
1996, and under clause 6.6 of the Industrial Relations Commission
Rules 2022.
I certify that the form of
this reprint, incorporating the variations set out in the schedule, is correct
as at 19 February 2024.
E.
ROBINSON, Industrial Registrar
Schedule of Variations Incorporated
Variation Serial No.
|
Date of Publication
|
Effective Date
|
Industrial Gazette Reference
|
|
|
|
Volume
|
Page No.
|
C9223
|
26 February 2021
|
15 March 2021
|
389
|
367
|
C9404
|
11 March 2022
|
1 March 2022
|
391
|
790
|
C9475
|
17 June 2022
|
18 April 2022
|
392
|
289
|
C9476
|
5 August 2022
|
16 May 2022
|
392
|
685
|
C9488
|
16 August 2022
|
20 June 2022
|
392
|
834
|
C9489
|
8 September 2022
|
18 July 2022
|
392
|
1049
|
C9500
|
8 September 2022
|
15 August 2022
|
392
|
1051
|
C9604
|
20 March 2023
|
19 September
|
393
|
1628
|
C9603
|
20 March 2023
|
3 October 2022
|
393
|
1617
|
C9605
|
20 March 2023
|
17 October 2022
|
393
|
1630
|
C9606
|
20 March 2023
|
14 November 2022
|
393
|
1632
|
C9609
|
20 March 2023
|
19 December 2022
|
393
|
1634
|
C9611
|
24 March 2023
|
16 January 2023
|
393
|
1664
|
C9614
|
24 March 2023
|
20 February 2023
|
393
|
1662
|
C9612
|
24 March 2023
|
20 February 2023
|
393
|
1666
|
C9620
|
31 March 2023
|
20 March 2023
|
393
|
1743
|
C9630
|
21 April 2023
|
20 February 2023
|
394
|
280
|
C9635
|
21 April 2023
|
17 April 2023
|
394
|
282
|
C9645
|
15 May 2023
|
12 May 2023
|
394
|
634
|
C9648
|
23 June 2023
|
19 June 2023
|
394
|
654
|
C9653
|
21 July 2023
|
17 July 2023
|
394
|
912
|
C9682
|
25 August 2023
|
21 August 2023
|
394
|
1796
|
C9729
|
6 October 2023
|
18 September 2023
|
395
|
462
|
C9741
|
13 October 2023
|
16 October 2023
|
395
|
499
|
C9767
|
17 November 2023
|
10 November 2023
|
395
|
1173
|
C9766
|
17 November 2023
|
20 November 2023
|
395
|
1193
|
C9796
|
15 December 2023
|
18 December 2023
|
396
|
145
|
C9805
|
12 January 2024
|
15 January 2024
|
396
|
432
|
C9818
|
2 February 2024
|
12 February 2024
|
396
|
619
|
DETERMINATION
Clause No. Subject
Matter
PART 1 -APPLICATION AND OPERATION
1. Definitions
2. Application
3. Savings clause
4. Promotion
of Determination
PART 2 - OPERATIONAL MATTERS
5. Vehicles
6. Loading and Delivery
7. Fatigue Management and Heavy Vehicle
Compliance
8. Uniforms
9. Lunch Break
10. Annual Leave
PART 3- RIGHTS AND RESPONSIBILITIES
11. Contract Carrier
Obligations
12. Principal Contractors’ Obligations
13. Termination
14. Insurance
15. Allocation of Work and Rostering
16. Fleet Mix Change
17. Selling of
Vehicles
18. Supervision of Personnel
PART 4 - RATES
AND REMUNERATION
19. Application of this Part
20. Rates of Remuneration
21. Alternative Remuneration Arrangements
22. Mass Management
24. Three Yearly
Cost Reconciliation Review
25. Tolls
& Charges
PART 5- MISCELLANEOUS
26. Disputes
Procedure
27. Union Delegates
28. Record
Keeping
29. Leave Reserved
Schedule A -
Rates of Remuneration
Schedule B - Waterfront and Container Depots
Schedule C - Procedure
and Time for Adjustments of Rates
Schedule D -
Nominated Contract Determinations
Schedule E – Superannuation Contribution Arrangements Schedule F – Temporary Fuel Surcharge
PART 1 - APPLICATION AND OPERATION
1. Definitions
1.1 In this
Determination:
Act means the Industrial Relations Act 1996 (NSW);
Additional Amount has the meaning
attributed to it in Schedule
A;
Carrying Capacity in relation to a Vehicle
means the mass of the maximum load which the Vehicle may legally carry;
Cartage Rate Schedule
means a written schedule (which
may be an electronic document) identifying:
(a) the basis of calculation of the Cartage
Rates (e.g. per hour, per km or some other basis);
(b) the amount
of remuneration to be paid to the Contract Carrier
for the Cartage
Work (e.g. $100 per
hour); and
(c) the timing
of the payment of remuneration (e.g.
the day of the week on which remuneration will be
paid and the pay period).
Cartage Work means work performed
under a Contract
of Carriage;
Cost Model means the spreadsheet marked as Exhibit
1 in Matter No. 2019/48046;
Class of Vehicle
means either a single axle drive prime mover or a bogie axle drive prime mover or, in the case of any other
Vehicle, a Vehicle of a particular Carrying Capacity;
Contract of Carriage
has the meaning given to that expression by the Act; Contract Carrier has the meaning
given to that expression by the Act;
Delegate means a Union delegate
of Contract Carriers
based at a terminal and includes a co-
delegate;
Determination means this Transport Industry
- General Carriers
Contract Determination;
Driver means a natural person operating the Contract Carrier’s Vehicle who is approved in accordance with clause 11.6;
Finishing Place means:
(a) the sites or depots
where the Contract Carrier is principally engaged (which may be a network of
depots within reasonable proximity); or
(b) where the
Principal Contractor and the Contract Carrier have agreed on an alternative
location, the agreed alternative location; or
(c) a place
specified by the Principal Contractor, but only if the Contract Carrier is not
principally engaged at a site or depot,
save that any agreed or specified
Finishing Place must be reasonable in the circumstances;
IRC means the Industrial Relations Commission of New South Wales;
Light Vehicle means a Vehicle
with a Carrying Capacity of up to and including
3 tonnes;
Light Vehicle Rates means the minimum rates of
remuneration set out in Schedule A.3 in this Determination that are expressed
to apply to Light Vehicles.
Misconduct means consuming alcohol immediately before,
or while undertaking work for the Principal Contractor, being under the
influence of alcohol or a drug while undertaking work for the Principal
Contractor, being dishonest or
abusive while undertaking work for the Principal
Contractor or in dealings with the Principal Contractor or customers,
consignors, consignees or their respective representatives, or falsifying
documents submitted to the Principal Contractor;
Nominated Contract Determination means a determination listed in Schedule
D and any successor to those determinations;
Principal Contractor has the meaning
given to that expression by the Act;
Regular Contract Carrier means a Contract Carrier who
operates under a contract with a Principal Contractor and who is wholly or
principally engaged by that Principal Contractor;
Specialised Vehicle means:
(a) a rigid Vehicle with a tipping
body;
(b) an articulated Vehicle with a tipping trailer;
(c) a Vehicle
combination with a tipping trailer;
(d) a rigid Vehicle with a tanker;
(e) an articulated Vehicle with a tanker trailer;
(f) a Vehicle
combination with a tanker trailer;
(g) a rigid or articulated Vehicle with a premixed concrete
agitator;
(h) a rigid, articulated or combination Vehicle
that utilises a forklift or crane that is used to load and/or
unload the Vehicle carting bricks, roof tiles, precast concrete panels, masonry
or pottery;
(i) a Vehicle
with a trailer designed for the carrying
of motor Vehicles; and
(j) a Vehicle
with a trailer designed to carry heavy machinery, operating
plant or wide loads (a float),
save that a Specialised Vehicle
does not include
a Vehicle listed
above if the Vehicle is being used in a manner or to cart materials or
products for which it would not customarily be used for;
Starting Place means:
(a) the sites or depots
where the Contract
Carrier is principally engaged (which may be a network of depots within reasonable
proximity); or
(b) where the Principal Contractor and the Contract
Carrier have agreed
on an alternative location, the agreed alternative location; or
(c) a place specified by the Principal Contractor, but only if the Contract Carrier is not
principally engaged at a site or depot,
save that any agreed or specified Starting
Place must be reasonable in the circumstances; Union means the Transport
Workers' Union of New South Wales; and
Vehicle means a Vehicle used by a Contract Carrier
for the purpose
of a Contract of Carriage.
Work Distance means the distance necessarily travelled
by a Contract Carrier in the course of performing a Contract of Carriage,
counted from the moment of departure from the Starting Place to the completion
of Cartage Work at the Finishing Place;
Work Time means the time during which a Contract
Carrier is necessarily engaged performing a Contract of Carriage. To avoid
doubt, Work Time includes all time during which the Contract Carrier is
required by the Principal Contractor to be at their disposal and/or at their
direction, but excluding time lost because of breakdowns or accidents and the time taken by the
Contract Carrier for meal breaks;
2. Application
2.1 This Determination applies to all Contracts of Carriage other than Contracts
of Carriage:
(a) which are covered by one of the Nominated Contract Determinations; and/or
(b) which are performed
using a Specialised Vehicle.
2.2 This Determination takes effect on and from 6 August
2019 and shall
have a nominal term of 3 years.
3. Savings Clause
3.1 No Contract Carrier
shall suffer a reduction in their terms and conditions of engagement because of
the making of this Determination.
3.2 This subclause applies to Contracts of Carriage entered into prior
to 1 March 2022 that are performed by a Vehicle with a Carrying
Capacity over 2 tonnes and up to and including
3 tonnes. No Contract Carrier
shall suffer a reduction
in the rates paid for such Contracts of Carriage (as were being paid immediately prior to the first pay
period commencing on or after 1 March 2022) because of the introduction of
Light Vehicle Rates.
4. Promotion of
Determination
4.1 Within fourteen
days of the commencement of this determination the Principal Contractor shall
provide every Contract Carrier it currently engages a copy of this
Determination.
4.2 The Principal
Contractor shall provide every new Contract Carrier it engages after this Determination
commences with a copy of this Determination within seven days of the
engagement.
4.3 A Principal Contractor shall provide every Contract
Carrier it engages with a copy of any variation to this Determination
within fourteen days of the commencement of the variation.
4.4 The obligations in paragraphs 4.1 to 4.3 of this clause may be satisfied by providing an electronic copy of the instrument by email or other electronic
means. A Principal Contractor may require, and the Contract Carrier shall provide,
a current email address for that purpose.
4.5 Notwithstanding the terms of paragraphs 4.1-4.3 a
Principal Contractor is not obliged
to provide a copy of
the documents more than once in any 12 months.
4.6 A Principal
Contractor shall display a copy of the determination and any variations then in
force. at the Principal Contractor’s workplace.
PART 2 - OPERATIONAL MATTERS
5. Vehicles
5.1 Supply and Suitability
The Contract Carrier
must supply a Vehicle, which must:
(a) meet the Vehicle specification required by the Principal Contractor; and
(b) be approved
by the Principal Contractor prior to performing Cartage Work.
5.2 Registration
The Contract Carrier
must at the Contract Carrier’s own expense register
their Vehicle.
5.3 Maintenance and Repair
The Contract Carrier
must mechanically maintain
and repair their Vehicle at their own expense.
5.4 Running Expenses
The Contract Carrier
must pay all of the running costs associated with the Contract
Carrier’s Vehicle.
5.5 Cease Using Vehicle
(a) Where a
Principal Contractor has a reasonable concern that a Contract Carrier’s Vehicle
is not, or may not be, roadworthy to perform the Cartage Work, the Principal
Contractor may:
(i) direct the Contract Carrier
to stop using the Vehicle
(or any part of it) pending;
(A) inspection and/or
testing of the Vehicle; and/or
(B) where necessary, the carrying out of any repairs and/or
maintenance.
(b) The Principal Contractor must not take any steps under clause 5.5(a) until
the Principal Contractor has put its
reasonable concern to the Contract Carrier.
(c) The Contract
Carrier will not suffer any loss of remuneration where they are directed to stop using their Vehicle under this clause, and where the
inspection and/or testing of the Vehicle proves that the Vehicle was roadworthy
to perform the Cartage Work.
5.6 Inspections and Tests
The Contract Carrier
must make the Vehicle available for inspection or testing as and when reasonably
required by the Principal Contractor.
5.7 Communication and Related Technology
(a) The Principal
Contractor may supply the Contract Carrier with communication and related
technology for use in the Contract Carrier’s Vehicle.
(b) Where such communication and/or
related technology is supplied by the Principal Contractor:
(i) The
Principal Contractor must install and maintain the communication and related
technology required by the Principal Contractor and the Contract Carrier must
operate it efficiently as directed by the Principal Contractor.
(ii) The Contract
Carrier has full responsibility for the safe custody of the communication and related technology.
(iii) The Contract
Carrier must:
(A) not add to, alter or modify
the communication and related technology;
(B) indemnify the Principal Contractor, and keep the Principal Contractor indemnified at all
times, against destruction or loss of the communication and related technology;
(C) not pledge
the credit of the Principal Contractor in respect
of, or create any lien upon,
the communication and related technology; and
(D) not without
the prior written
consent of the Principal Contractor use the communication
and related technology for anything but the Cartage Work.
(c) The Contract
Carrier must stop using the communication and
related technology (or any part of
it) if the Principal Contractor so directs because
in the Principal Contractor's opinion
that is appropriate pending the carrying out of any repairs,
maintenance, inspection or testing.
(d) Immediately upon the ending or termination of any head contract
under which the Contract
Carrier performs the Cartage Work:
(i) the Contract
Carrier must return
the communication and related technology to the Principal Contractor in good order and
condition, save for any fair wear and tear only; and
(ii) the Principal Contractor must make good any repairs to the Contract
Carrier’s Vehicle arising
from the removal of the communication and related technology.
5.8 Vehicles
(a) The Principal
Contractor has the right to specify the age and the Class of Vehicle used in
the performance of Contracts of Carriage prior to the engagement of a Contract
Carrier.
(b) If a Principal Contractor reasonably believes that the Vehicle
of the Contract Carrier is not
suitable for undertaking the required Cartage Work, the Principal Contractor
has the right to require an upgrade (which may include the purchase of a new or
newer Vehicle) of the Contract Carrier’s Vehicle subject to the provision of a period which is reasonable in the circumstances and any such direction to upgrade
being set out in writing.
(c) The Contract
Carrier must not replace
the Vehicle used to perform
Cartage Work without the prior written consent of the Principal
Contractor.
5.9 Painting and sign-writing
(a) Unless
otherwise agreed, a Principal Contractor may paint and/or sign-write the
Contract Carrier's Vehicle in the Principal Contractor's colours at the
Principal Contractor's expense (but not before the Contract Carrier has
completed three months continuous Cartage Work for the Principal Contractor).
(b) In the case of a Contract
Carrier ceasing to perform Work for the Principal Contractor, the Principal
Contractor must bear the cost of reversing
any painting and sign-writing and removing
all equipment and signs supplied
by the Principal Contractor and make good the affected areas of the Vehicle to
the original specification.
(c) A Principal
Contractor must take, and a Contract Carrier must cooperate with, reasonable
steps to minimise or avoid the loss of remuneration which would otherwise be
suffered by the Contract Carrier because the Vehicle is being painted and/or
sign-written at the request of the Principal Contractor, including by:
(i) providing the Contract Carrier
with an alternative vehicle
with which to perform work; and/or
(ii) by painting
or sign-writing the Vehicle during
a period in which the driver has previously
arranged to take leave; and/or
(iii) by the Principal Contractor compensating the Contract
Carrier for any loss of remuneration
suffered.
6. Loading and
Delivery
6.1 Report at Starting Place and Time
The Contract Carrier
must report available for the Cartage
Work with the Vehicle at the Starting
Place.
6.2 Checking of Load
After loading the Vehicle and before leaving
the loading place,
the Contract Carrier
must:
(a) ensure that the load is secured;
and
(b) immediately
report to the Principal
Contractor if the Contract Carrier
believes that the goods do not
comply with the specification on the delivery
docket or exceeds
the maximum legal
payload for the Vehicle.
6.3 Delivery
Immediately after checking
the load the Contract Carrier
must deliver the goods to whatever addresses the Principal Contractor instructs using:
(a) the route
directed by the Principal Contractor; or
(b) if no such direction is given, using
the shortest practicable route.
6.4 Unloading
The Contract Carrier
must:
(a) use every
reasonable effort at the delivery
site to obtain:
(i) directions from the customer
concerning the manner
and position to unload the goods; and
(ii) from the customer the signatures required
by the Principal Contractor; and
(b) unload the goods at the delivery
site in the manner and position reasonably directed by the customer.
6.5 Unsafe Unloading
If the unloading of the goods at any delivery site will
place the Driver in a position of imminent risk to their health and safety, the
Contract Carrier must immediately notify the Principal Contractor prior to
unloading the goods and comply with any instructions given by the Principal
Contractor concerning the unloading of the goods.
6.6 Return
After completing the deliveries, the Contract Carrier
must report to whatever site (if any) the Principal Contractor instructs using the
shortest practicable route from the final unloading site.
6.7 Custody
The Contract Carrier
shall:
(a) be responsible for
the equipment and gear and for the safe loading of the Vehicle and the securing
and appropriate weather protection of the load and shall be present to
supervise and assist in the loading and unloading of the Vehicle and/or the
container loaded on the Vehicle;
(b) in the case of
pre-loaded Vehicles, be responsible for checking the load for safety and
satisfactory method of loading; and
(c) exercise all reasonable care and diligence in the carriage
and safe keeping
of the goods in charge.
7. Fatigue Management and Heavy Vehicle
Compliance
7.1 Fatigue management and heavy vehicle
compliance
Fatigue management and heavy vehicle
compliance is principally regulated in NSW by the:
(a) Heavy Vehicle
National Law, and associated regulations;
(b) Work Health
and Safety Act 2011 (NSW); and
(c) Transport Industry Mutual Responsibility Contract Determination.
7.2 Taking of Fatigue Breaks
Each Contract Carrier
must take fatigue
breaks, without payment,
as required by law.
8. Uniforms
8.1 Supply of Uniform
If the Driver of the Contract Carrier’s Vehicle is
required by the Principal Contractor to wear a special uniform when undertaking Cartage
Work for the Principal Contractor, the uniform must be supplied
by the Principal Contractor
at no cost to the Contract Carrier.
8.2 Obligation to wear
Where a uniform is so provided, the Contract
Carrier must ensure
that it is worn
by the Driver at all times while undertaking Cartage
Work for the Principal Contractor.
8.3 Property
The uniform remains
the property of the Principal
Contractor.
8.4 Quantity
The Principal Contractor must provide a sufficient number of uniform articles to enable the
Contract Carrier to wear a clean uniform at the start of each Cartage Working
day.
8.5 Replacement
An item forming part of the uniform must be replaced by
the Principal Contractor when required by fair wear and tear, provided
that should loss or damage
to an item forming part of the uniform
occur due to the negligence of the Contract Carrier, the item must be repaired
or replaced by the Contract Carrier at the Contract Carrier’s cost.
9. Lunch Break
9.1 Entitlement
Each Contract Carrier is entitled to and must take a 30 minute unpaid lunch break on each day Cartage Work is
performed for a Principal Contractor for more than 4 hours provided that where
it is safe and reasonably practicable to do so, the Contract
Carrier must take the lunch break in conjunction with a fatigue break.
9.2 Reporting
A Contract Carrier who ceases Cartage Work for a lunch break in accordance with clause 9.1 must
report that fact to the Principal Contractor.
10. Annual Leave
10.1 Entitlement
A Regular Contract
Carrier may take four weeks'
annual leave without
payment.
10.2 When the Entitlement Falls Due
The leave entitlement falls due each year on the anniversary of the commencement date of the first Contract of Carriage between the Contract Carrier
and the Principal Contractor.
10.3 Period to Take Leave
Such leave is to be taken by the Contract Carrier
within 6 months of the leave falling due (or within such extended time as the
Contract Carrier and the Principal Contractor may agree) and at a time mutually
convenient to the Contract Carrier and the Principal Contractor.
10.4 Utilisation of Vehicle
To avoid any doubt, and unless otherwise agreed between
the parties, during any period of annual leave the Contract Carrier has no obligation to present their Vehicle to the Principal
Contractor for Cartage
Work.
10.5 Lapse of Entitlement
If the leave
is not taken within the time provided
for in this clause, the entitlement to the leave will lapse.
PART 3 - RIGHTS
AND RESPONSIBILITIES
11. Contract Carrier Obligations
11.1 Core Obligations
The Contract Carrier
must perform the Cartage Work and do everything connected
with it:
(a) with due care and skill and in a proper, co-operative and professional manner;
(b) safely, and in accordance with the Principal
Contractor's safety requirements;
(c) in accordance with the day to day operational directions given by the Principal Contractor;
(d) in accordance with any lawful
and reasonable direction, policy, procedure or specifications provided by the Principal Contractor;
(e) without jeopardising or damaging
the Principal Contractor's
business; and
(f) in compliance with all relevant
laws.
11.2 Compliance with Employment Laws
The Contract Carrier must comply with the
provisions of any relevant
employment law, including but not limited to laws concerning income tax, workers’
compensation, superannuation, annual
leave, long service leave or any award, order, determination or agreement of a competent industrial
tribunal.
11.3 Administration
The Contract Carrier
must:
(a) return to the Principal Contractor all delivery
dockets, daily Cartage
Work sheets or other records required by the Principal
Contractor as and when required;
(b) maintain up to
date and accurate log books as required under any
relevant law and/or by the Principal Contractor and make these available for inspection by the Principal Contractor on request;
(c) ensure that the Driver
maintains a system
verifying Vehicle maintenance;
(d) keep and retain
for seven years comprehensive records in relation to the Cartage Work,
including the records in subparagraphs (b) and (c) above; and
(e) ensure that a copy of the records in subparagraphs (b), (c) and (d) are available for inspection at any
time for audit purposes.
Notation: Any written
material to be provided to the Principal Contractor in accordance with this clause must be appropriate and economical and designed to meet the requirements of this clause.
11.4 Medicals
(a) The Contract
Carrier must ensure
that the Driver
is at all times medically fit to perform the Cartage
Work.
(b) Where the
Principal Contractor has a reasonable concern that the Driver is not medically
fit to perform the Cartage Work, the Principal Contractor may require and
direct the Driver to:
(i) furnish particulars and/or medical evidence
affirming the Driver’s
fitness to undertake Cartage Work; and/or
(ii) on reasonable terms, attend a medical examination to confirm their fitness (such direction
may include the choice of medical practitioner).
(c) The Principal
Contractor must not take any steps under clause 11.4(b)
until the Principal
Contractor has put its concerns to the Contract Carrier in writing.
(d) If the Driver
attends a medical practitioner directed by the Principal Contractor, the
Principal Contractor will pay the medical fees associated with the attendance.
(e) The Driver
will not suffer
any loss of remuneration as a result
of being directed to attend a medical
examination under this clause, unless
the medical examination demonstrates that the Driver was not
medically fit to perform the Cartage Work.
11.5 Alcohol and Other Drugs
Polices and Programs
Where the Principal Contractor has in place a drug and
alcohol policy and/or program, applying to its employees and contractors, the
Contract Carrier must ensure that the Driver participates in any testing
required by the policy and/or program.
11.6 No One Else to Drive Vehicle The
Contract Carrier must:
(a) only use a
Driver who is approved by the Principal Contractor, with such approval not
being unreasonably withheld; and
(b) make sure that
no one except the approved Driver
drives or otherwise operates the Vehicle for the Cartage Work.
11.7 Valid Driving
License and Permits
The Contract Carrier
must:
(a) make sure that the approved Driver
is at all times the holder of a current:
(i) valid driver's
licence appropriately endorsed
or issued in respect of their Vehicle;
and
(ii) valid licence
or permit of any other kind needed from time to time to perform
the Cartage Work;
(b) immediately notify
the Principal Contractor if a licence
or permit is cancelled or suspended for any
reason; and
(c) present any such licence
or permit to the Principal Contractor upon request.
Note:
Clause 11.7(a)(i) does not apply in relation to Contracts of Carriage performed exclusively by bicycle.
12. Principal
Contractors’ Obligations
The Principal Contractor must:
(a) arrange whenever
practicable for a representative of the
Principal Contractor to attend
accidents involving substantial
load or equipment damage or personal injury;
(b) advise Contract
Carriers as early as possible of urgent or special delivery instructions
arranged for particular work or particular goods;
(c) where goods
of a dangerous or hazardous
nature are to be carried, notify the Contract Carrier
of the nature of such goods and comply with all relevant requirements
of the Dangerous Goods (Road and Rail) Act, accompanying Regulations and its
related Codes of Practice;
(d) pay the Contract Carrier
any undisputed amount
set out in a valid taxation invoice
provided by the Contract
Carrier, or generated for the
Contract Carrier, for the Cartage Work performed, within 30 days
of the date of receipt by the
Principal Contractor of the invoice;
(e) wherever the
Contract Carrier is or is deemed to be for the purposes of the Workers
Compensation Act a worker of the Principal Contractor, take out and maintain at
all times a workers' compensation insurance policy in respect of the Contract Carrier;
(f) comply with any
laws affecting the Principal Contractor’s Cartage Work including licensing,
road transport, fatigue management and work health and safety laws; and
(g) provide to each Contract Carrier a Cartage Rate
Schedule prior to commencing to
perform Cartage Work and whenever there is a change to the basis of calculation
of the Cartage Rates and/or a change to the Cartage Rates.
13. Termination
(a) Where a
Contract Carrier commits Misconduct or is in breach of this Determination
he/she may be terminated summarily by the Principal
Contractor. An inquiry, if requested, will be
held thereafter within one normal work day by the Principal
Contractor, Delegate and, if available, a representative of the union.
(b) Any other
termination shall be on the basis of "last on-first off" for Contract Carriers
operating vehicles of a particular class of vehicle.
14. Insurance
14.1 Insurances
Prior to commencing any Cartage Work, the Contract
Carrier must obtain, and maintain current at all relevant times, the following
insurances at the Contract Carrier’s expense:
(a) comprehensive
and third party motor Vehicle insurance covering
personal injury and property damage arising from the use of the Contract Carrier’s Vehicle or other
mobile equipment, including compliance with any statutory requirements, of not less than $20,000,000
(or such other amount as the Principal Contractor may require
from time to time) for each and every occurrence;
(b) property insurance covering the full replacement value of the Contract Carrier’s
Vehicle;
(c) public and products
liability insurance written on an occurrence basis covering the legal liability of the Contract Carrier and the Contract Carrier’s employees and
agents (the "Insureds") to any third parties for bodily injury and/or
property damage arising from acts or omissions of the Insureds in the course
of, or arising from, the performance of the Cartage Works by the
Contract Carrier or on the Contract Carrier’s behalf of not less than
$20,000,000 (or such other amount as the Principal Contractor may require from
time to time) for each and every occurrence; and
(d) workers’ compensation insurance as required
by any relevant law.
14.2 Endorsements
The Contract Carrier
must ensure that, in respect
of the insurance policies taken out,
they contain clauses, endorsements or stipulations as reasonably
required by the Principal Contractor.
14.3 Co-Operation
The Contract Carrier
must:
(a) not do, or omit
to do, anything which might vitiate, impair or derogate from the cover under
any insurance policy or other cover or which might prejudice any claim under any policy
or other cover; and
(b) fully co-operate with the Principal
Contractor in relation
to a claim under the insurances.
14.4 Provision of Currency
The Contract Carrier must upon the Principal
Contractor’s request provide to the Principal Contractor certificates of
currency evidencing the existence of the policies required to be effected under this clause and the certificates of currency
must, as a minimum, show the insurer’s name, policy number and policy expiry
date.
14.5 Other Insurances
If the Principal Contractor requires a Contract Carrier
to obtain an insurance other than
the insurances set out in clause 14.1 or to obtain
different levels of insurance cover,
the Principal Contractor must reasonably
compensate the Contract Carrier for the cost of that insurance.
15. Allocation of Work
and Rostering
15.1 Allocation of Cartage Work
A Principal Contractor must allocate Cartage
Work to Contract Carriers transparently, reasonably and lawfully.
15.2 Rostering
A Principal Contractor must roster Contract
Carriers to perform
work (including rostering on, return load and rostering off) transparently, reasonably and lawfully.
16. Fleet Mix Change
16.1 Changing Fleet Mix - Mandatory Consultation
(a) This clause
applies where a Principal Contractor has made a definite decision
to make a fleet mix change
that is likely to have significant effects on Contract Carriers.
(b) For a fleet mix change referred to in paragraph 16.1(a):
(i) the Principal Contractor must notify the relevant
Contract Carriers of the decision
to change the fleet mix; and
(ii) subclauses (c) to (h) apply.
(c) The relevant
Contract Carriers may appoint a representative for the purposes
of the procedures in this
clause.
(d) If:
(i) a relevant
Contract Carrier appoints, or relevant Contract
Carriers appoint, a representative
for the purposes of consultation; and
(ii) the Contract
Carrier or Contract
Carriers advise the Principal Contractor of the identity
of the representative;
(ii) the Principal
Contractor must recognise
the representative.
(e) As soon as practicable after making its decision, the Principal Contractor must:
(i) discuss with the relevant
Contract Carriers:
(A) the proposed
change to the fleet mix; and
(B) the effect the change is likely to have on the Contract
Carriers; and
(C) measures
the Principal Contractor is taking to avert or mitigate the adverse effect
of the change on the Contract Carriers; and
(ii) for the purposes of the discussion, provide in writing
to the relevant Contract Carriers:
(A) all relevant
information about the change including the nature of the change proposed; and
(B) information about the expected
effects of the change on the Contract
Carriers; and
(C) any other matters likely
to affect the Contract Carriers.
(f) However, the Principal Contractor is not required
to disclose confidential or commercially sensitive information to the relevant
Contract Carriers.
(g) The Principal Contractor must give prompt and genuine consideration to matters raised about the change by the relevant Contract
Carriers.
(h) In this clause, a "fleet mix change" arises:
(i) when a Principal Contractor decides to introduce
a new transport type into their fleet being
one or more of the following transport types:
(A) Contract Carriers; or
(B) Drivers employed
by the Principal Contractor; or
(C) third party transport providers;
(ii) when a Principal Contractor introduces into their fleet
a new Vehicle configuration.
17. Selling of
Vehicles
No circumstances shall exist where a Vehicle
is sold with Cartage Work.
18. Supervision of
Personnel
The Contract Carrier
must ensure that each and all of its Drivers:
(a) performs the Cartage Work and does everything connected with it as is required
of the Contract Carrier by this Determination; and
(b) does not engage in any acts or omissions that give rise to a breach by the Contract
Carrier of this Determination.
PART 4 - RATES OF REMUNERATION
19. Application of
this Part
19.1 This Part applies:
(a) to all Contracts of Carriage from one place to another
place, both of which are within the County
of Cumberland; and
(b) to all Contracts of Carriage for the transportation of goods from one place
to another place, where the second place is no more than 50
kilometres from the first place.
19.2 This Part also applies
to a Contract of Carriage
involving a single
journey commencing within
the County of Cumberland and
finishing within:
(a) a 50 kilometre radius of the Newcastle GPO; or
(b) a rectangular area being 50 kilometres
North of the Wollongong GPO, 20 kilometres East of the Wollongong GPO, 50
kilometres South of the Wollongong GPO
and 20 kilometres West of the
Wollongong GPO.
20. Rates of
Remuneration
20.1 Subject to this clause,
a Principal Contractor shall pay to a Contract
Carrier:
(a) the rate of
remuneration per kilometre in the Schedules to this Determination applicable to
the Contract Carrier’s Vehicle for the Work Distance; and
(b) the rate
of remuneration per hour in the Schedules to
this Determination applicable
to the Contract Carrier’s vehicle
for the Work Time calculated to the nearest half hour; and
(c) any additional rate prescribed in the Schedules
to this Determination.
20.2 Annual Minimum
Guarantee Cartage Rate - Small Trucks
(a) This subclause applies on and from 1 January 2019, and only to the following classes
of vehicle:
(i) Rigid - carrying capacity
over 2 and including 5 tonnes; and
(ii) Rigid - carrying capacity
over 5 and including 8 tonnes.
(b) 50 x 50 Arrangement - Subject to this subclause and subclause (c), if a Principal Contractor makes an agreement
in writing with a Contract
Carrier for a minimum
of 50 hours each week for 50 weeks
for a 12 month period,
or periods, the Principal Contractor may pay the Contract Carrier
90% of the "Per Hour" rate in Schedule A Table A.1.1 or A.2.1
(whichever is applicable to the Contract Carrier’s Vehicle) for each hour that
the Contract Carrier performs the Cartage Work during that period.
(c) Subject to
subclause (d), with respect to Contract Carriers engaged as at 31 December
2018, a Principal Contractor may utilise a 50 x 50 Arrangement of the kind described in subclause (b) where
the Contract Carrier has been engaged by the Principal Contractor for a minimum
of 50 hours each week for
50 weeks in the previous 12 month period (Existing Tied Contract Carrier),
notwithstanding that there is no agreement in writing between the Principal
Contractor and the Contract Carrier to that effect.
(d) Where a
Principal Contractor that engages an
Existing Tied Contract Carrier wishes
to utilise a 50 x 50 Arrangement in circumstances described in sub clause (c):
(i) the
Principal Contractor shall advise the Existing Tied Contract Carrier in writing
of the Principal Contractor’s intention to utilise a 50 x 50 Arrangement. The notice shall include as a minimum:
(A) the date from which
the Principal Contractor intends to utilise
a 50 x 50 Arrangement, which shall be at least 8
weeks prior to its commencement; and
(B) the 12 month period, or periods, during which the Principal
Contractor will apply those provisions; and
(C) advising the
Existing Tied Contract Carrier that they have 4 weeks from the receipt of the
Principal Contractor’s notice to elect not to adopt a 50 x 50 Arrangement. If
the Existing Tied Contract Carrier elects not to adopt a 50 x 50 arrangement,
which election not to adopt must not be unreasonable, they must give the
Principal Contractor a written notice of election to that effect;
(ii) within 4 weeks of
receiving the Existing Tied Contract Carrier’s notice of election, the
Principal Contractor must either consent
to or refuse the election, but must not unreasonably
so refuse; and
(iii) if the Principal Contractor consents to the
election, a 50 x 50 Arrangement will not apply to the Existing Tied Contract Carrier.
(e) Nothing in this
subclause affects an obligation of a Principal Contractor to pay the per/km
rate applicable in Schedule A Tables
A.1.1 or A.2.1, or any of the rates
in clauses A3,A4, A5 or A6 for the Cartage Work.
(f) Minimum Earnings Guarantee -
Reconciliation: If clause 20.2(b) or (c) applies to a Contract of Carriage and
in an 8 week period the Contract Carrier has not
worked at least 50 hours each week for whatever reason, then:
(i) the
Principal Contractor must ensure that the Contract Carrier receives an amount
of pay (excluding any payment arising from the
per/km rates in Schedule A Tables A.1.1 or A.2.1,
or from any of the rates in clauses A3, A4, A5 or A6 equivalent to the Minimum
Earnings Guarantee.
(ii) If there is any
shortfall between the amount of pay paid to the Contract Carrier (excluding any payment
arising from the per/km rates
in Schedule A clauses A.1.1 or A.2.1,
or from any of
the rates in clauses A3, A4, A5 or A6 and the Minimum Earnings
Guarantee, the Principal Contractor must pay the
shortfall to the Contract Carrier in the Principal Contractor’s next pay cycle.
(g) Minimum Earnings
Guarantee - Calculation: The Minimum Earnings
Guarantee is calculated using the following formula:
(i) (per
hour rate from Table A.1.1 x 90%) x ((50 x 8) minus Unavailable Hours) for
Vehicles less than six years old; or
(ii) (per hour rate
from Table A.2.1 x 90%) x ((50 x 8) minus Unavailable Hours) for Vehicles six
or more years old.
(h) "Unavailable
Hours" are those hours that the Contract Carrier’s Vehicle is unavailable
to perform the Cartage Work during
the hours the Contract Carrier is required to make their Vehicle available in accordance with clause 20.2(b) above.
(i) Early Termination of 50 x 50 Arrangement:
Where a Principal
Contractor decides to terminate a 50 x 50 Arrangement prior to the expiration of the relevant 12
month period the Principal Contractor:
(i) will
notify the Contract Carrier in writing of its intention to terminate the 50 x
50 Arrangement. The notice will
specify the date upon which the 50 x 50 Arrangement will terminate, which shall
be no fewer than 4 weeks after the date of the notice; and
(ii) will pay the Contract
Carrier either:
(A) the difference in remuneration the Contract Carrier would have earned had a 50 x 50 Arrangement not been entered into under
this Part 4 for the relevant period, but capped at 50 hours per week; or
(B) the difference
in remuneration between what the Contract Carrier earns for the remainder of the relevant
12 month period (or periods)
and what the Contract Carrier would have earned had the 50 x 50 Arrangement, entered
into under this Part 4, not been terminated,
whichever is the lesser amount.
NOTE: The 50 x 50 Arrangement takes into account Unavailable Hours.
(j) Termination of Engagement during
50 x 50 Arrangement:
Where a Principal Contractor terminates the engagement
of a Contract Carrier to whom a 50 x 50 Arrangement applies, prior to the
expiration of the relevant 12 month period (or periods), the Principal
Contractor will pay to the Contract Carrier the difference in remuneration the
Contract Carrier would have earned had a 50 x 50 Arrangement not been entered
into under this Part 4 for the relevant period, but capped at 50 hours per
week.
However this subclause will
not apply in the case of a termination for misconduct (which misconduct will not be limited by clause 1.1), or
a termination in circumstances where the Contract Carrier is entitled to the
benefits of the Transport Industry - Redundancy (State) Contract Determination.
(k) 50 x 50 Arrangement
not a Common Law Contract: For the avoidance of doubt, any
arrangement made under this Part will not be construed as being, or forming,
part of any common law contract or arrangement, collateral or otherwise,
whether written or oral, which may exist between a Principal Contractor and a
Contract Carrier with respect to Cartage Work to which this Determination
applies.
(l) Early
Termination of 50 x 50 Arrangement - Reconciliation: the payment referred to in clause 20.2(i)(ii)(A) or (B) is to be calculated every 8 weeks, or part thereof, for the reminder of the relevant
12 month period (or periods).
20.3 The Rates
will be varied in accordance with the procedure set out in Schedule C.
20.4 Introduction of Light Vehicle
Rates
(a) In matters
2019/268320, 2020/112760, 2020/112849 and 2020/133735, the IRC introduced new
minimum rates applicable to Light Vehicles.
(b) Subject to
subclause 20.4(d), the Light Vehicle Rates set out in Schedule A include
compensation for all fixed and running costs that may be incurred by a Contract
Carrier.
(c) The Light
Vehicle Rates set out in Schedule A are to be increased if the charge
percentage (as set out in the Superannuation Guarantee (Administration) Act 1992)
increases above 10%. The Light Vehicle Rates
in Schedule A shall be increased by 0.25% for each 0.5 percentage point increase to the charge percentage.
20.5 Subject to
Schedule E, the cartage rates contained in this contract determination
compensate contract carriers for the cost of contributing to their
superannuation.
21. Alternative
Remuneration Arrangements
21.1 Despite clause
20, a Principal Contractor may pay a Contract Carrier based on a system or
method of remuneration different to that required
by clause 20 (an Alternative Remuneration Arrangement), provided that the Contract Carrier
receives, over a sixty-day
period, no less than the pay they would otherwise have received had they been paid in accordance with clause 20.1
for that period.
21.2 An Alternative Remuneration Arrangement must be in writing and:
(a) be signed
by the Contract Carrier and the Principal
Contractor; and
(b) identify the start date of the Alternative Remuneration Arrangement; and
(c) require the Principal Contractor to undertake an assessment of the amount received by the Contract Carrier under the Alternative Remuneration Arrangement every sixty-days from the identified start date to ensure the Alternative Remuneration Arrangement
complies with clause 21.1.
21.3 Where the amount paid
to a Contract Carrier under an Alternative Remuneration Arrangement in a sixty-
day period is less than the pay they
would have received had they been
paid in accordance with clause 20 for that period, the
Principal Contractor shall pay an amount (the Top Up Amount) to the Contract
Carrier to make up that difference.
21.4 The Top Up Amount
is to be paid within the next pay cycle.
22. Mass Management
22.1 If the Principal Contractor so directs, the Contract
Carrier must do all things required
and necessary to be accredited and remain accredited under:
(a) the Principal
Contractor’s accredited NHVAS Mass Management Module for Basic Fatigue
Management or Advanced Fatigue Management (or any scheme replacing this); or
(b) a NHVAS Mass
Management Module for Basic Fatigue Management or Advanced Fatigue Management
of the Contract Carrier.
22.2 In circumstances
where clause 22.1 applies the Principal Contractor must reimburse the Contract
Carrier for any reasonable costs directly arising from becoming accredited or
at their election pay the lump sum allowance set out in clause A.4.2 of Schedule A to set up for the NHVAS Mass
Management Scheme for Basic Fatigue Management or Advanced Fatigue Management.
22.3 In circumstances
where clause 22.1 applies the Principal Contractor must reimburse the Contract
Carrier for any reasonable costs directly arising from maintaining
accreditation or at their election pay the allowance set out in clause A.4.3 of
Schedule A per hour to cover costs associated with maintaining that NHVAS Mass
Management Scheme for Basic Fatigue Management or Advanced Fatigue Management.
22.4 To avoid any
doubt clause 22.2 and/or 22.3 shall not apply if the Contract Carrier has made
their own decision to become and work under an accredited NHVAS Mass Management
Scheme for Basic Fatigue Management or Advanced Fatigue Management.
23. Three Yearly Cost
Reconciliation Review
23.1 Reconciliation
Subject to an
application being made to apply the Three
Yearly True Cost reconciliation Review
Process, the price entries
in the "Price Table" and the table
"Trailers" of the Key Data
Variables sheet contained in the Cost
Model should be updated using sourcing that are relevant to and reflect the
cartage work being performed and such prices should reflect the lowest price
available from a reputable vendor which is accessible to Contract Carriers in
the open market.
23.2 Operative Date
Any rates shall be operative from such date as is determined by the Commission having regard to the need to inform Principal Contractors and
Contract Carriers of any change.
23.3 This clause
does not apply in relation
to Light Vehicle
Rates.
24. Tolls &
Charges
24.1 A Principal
Contractor shall pay road tolls incurred by a Contract Carrier in the
performance of Cartage Work for the Principal Contractor as a
consequence of any mandatory
legal obligations upon commercial vehicles to:
(a) use certain
toll roads; or
(b) avoid certain
roads including light limit roads which has the result of requiring the use of a toll road.
24.2 In all other
circumstances, a Principal Contractor shall pay road tolls incurred
by a Contract Carrier in the
performance of Cartage
Work for the Principal Contractor unless the Principal Contractor expressly directs the Contract Carrier in writing
to not use a toll road.
An express direction
may include:
(a) a standing
written direction issued
by the Principal Contractor to Contract Carriers
on an enterprise or fleet basis; or
(b) individual written
directions issued by the Principal Contractor to Contract
Carriers.
24.3 This clause
does not apply:
(a) if the
Principal Contractor can demonstrate that it already pays the Contract Carrier
under an arrangement which factors in the payment of current road tolls,
including by way of an alternative remuneration arrangement
pursuant to clause 21; or
(b) to a Principal
Contractor and their Contract Carriers performing Ca1iage Work under a contract
agreement that was approved by the Commission during the period of on or after
1 January 2018 and up to and including 5 February 2021.
For the avoidance of doubt, the exclusion provided
for by 25.3(b) will not apply to any contract
agreement that is approved or varied by the Commission after 5 February
2021.
24.4 The payment
of a road toll can be made by a Principal Contractor:
(a) in the next pay cycle following the Contract Carrier
providing a receipt
to the Principal Contractor;
or
(b) by providing the Contract Carrier
with an E-Tag.
PART 5 - MISCELLANEOUS
26. Disputes Procedure
25.1 Application of Procedure
Any dispute that arises between
a Contract Carrier
and a Principal Contractor must be dealt with in accordance with this clause.
25.2 Appointment of Representative
A Contract Carrier
who is a party to a dispute
may appoint a representative for the purposes
of this clause which may include the Union.
25.3 Procedure
In the first instance, the parties to the dispute
must try to resolve the dispute at the workplace level.
25.4 Notification to Commission
If the dispute
remains unresolved it may be referred to the IRC.
25.5 Continue to Perform Cartage
Work
Whilst the parties
are trying to resolve the dispute using the procedure
set out in this clause:
(a) Contract Carrier
must continue to perform Cartage
Work as they normally would do unless they hold a reasonable concern
about an imminent risk to their health or safety; and
(b) a Contract
Carrier must comply
with a direction given by their Principal
Contractor to perform
other available Cartage Work, unless:
(i) the Cartage
Work is not safe; or
(ii) applicable workplace
health and safety
legislation would not permit the Cartage Work to be performed; or
(iii) the Cartage
Work is not appropriate for the Contract
Carrier to perform;
or
(iv) there are other
reasonable grounds for the Contract
Carrier to refuse to comply
with the direction.
26. Union Delegates
26.1 Appointment
A Contract Carrier
appointed Delegate in a yard in which they are Contract Carrier
must, upon notification to their Principal
Contractor, be recognised as the accredited representative of the Union.
26.2 Opportunity to Meet
An accredited Delegate must be allowed a reasonable opportunity
to meet the relevant manager of the Principal Contractor and Contract Carriers
to discuss matters affecting Contract Carriers whom they represent.
26.3 Use of Notice Board
Accredited Delegates must be permitted to put Union
notices on a notice board, signed or countersigned by the representative
posting it.
27. Record Keeping
27.1 Obligations
The Principal Contractor must record either in
documentary form or electronic form, the following information for each
Contract Carrier:
(a) any Cartage
Rate Schedule;
(b) start and finish times;
(c) hours worked
per day;
(d) kilometres travelled per day;
(e) Starting Place and Finishing Place;
(f) remuneration paid; and
(g) a copy of any written contract
entered into with the Contract
Carrier; and
(h) all trip schedules and driver rosters;
and
(i) all safe driving plans and risk assessments that relate to the fatigue
of road transport drivers; and
(j) all reported
breaches and suspected
breaches of the fatigue
management law, including breaches and suspected breaches identified by the Principal
Contractor; and
(k) all breaches
of fatigue management laws investigated by the Principal
Contractor, the outcome
and any remedial action taken.
27.2 Maintenance of Records
The Principal Contractor must maintain all the records
arising from clause
28.1 for a period of seven years.
27.3 Contract Carrier
to Assist
(a) A Contract
Carrier must do all things
reasonably directed by the Principal
Contractor to gather
and record the information referred to in clause 28.1.
(b) A Principal
Contractor must not be liable for breach
of this clause 28 because
of the failure of a Contract Carrier to comply with clause
(a).
28. Leave Reserved
(a) Leave is reserved to any party covered by this Determination to make an application to vary the conditions
or rates of pay for "Long Distance
Work" within the meaning of clause 13 of the Transport Industry
(State) Award (Serial C7740).
(b) Leave is
reserved to any party covered by this Determination to apply to vary the
application of this Determination in respect of the transport of pre-fabricated construction materials to and from
construction sites.
SCHEDULE A - RATES OF REMUNERATION
NOTE: The rates of remuneration in this Schedule
apply to Contracts of Carriage covered
by Part 4 of this Determination.
A.1 Hourly and kilometre rates (other than for Light Vehicles) - new vehicles
A.1.1 A contract carrier
performing work using a vehicle which is less
than six years old must be paid at
least the hourly and kilometre rates set out in the following table (rounded up
to the nearest half hour, nearest kilometre and nearest cent).
For the avoidance of confusion, the per kilometre
rate payable is the Running Rate. The Running Rate is the
total of the "Per km excluding fuel component" and the "Per km
fuel component". The "Per
km excluding fuel component" and the "Per km fuel component" columns have been included for ease of reference when
updating rates.
From the first full pay period commencing on or after 12
February 2024:
Class of Vehicle
|
Per
hour
|
Running
Rate
|
Per
km excluding fuel component running rate for the purposes of Schedule C
|
Per
km fuel component of the running rate for the purposes Schedule C
|
($)
|
($/km)
|
($/km)
|
($/km)
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$55.15
|
$0.29
|
$0.12
|
$0.17
|
Rigid-carrying capacity 5 and including 8 tonnes
|
$62.83
|
$0.33
|
$0.14
|
$0.19
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$70.79
|
$0.44
|
$0.15
|
$0.28
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$72.36
|
$0.48
|
$0.19
|
$0.28
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$73.04
|
$0.47
|
$0.19
|
$0.28
|
Rigid-carrying capacity over 14 tonnes or more
|
$77.30
|
$0.57
|
$0.21
|
$0.36
|
Single Axle Prime Mover
|
$78.54
|
$0.54
|
$0.15
|
$0.38
|
Bogie Axle Prime Mover
|
$84.93
|
$0.66
|
$0.20
|
$0.46
|
From the first full pay period commencing on or after 10
November 2023:
Class of Vehicle
|
Per
hour
|
Running
Rate
|
Per
km excluding fuel component running rate for the purposes of Schedule C
|
Per
km fuel component of running rate for the purposes of Schedule C
|
($)
|
($/km)
|
($/km)
|
($/km)
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$52.15
|
$0.29
|
$0.12
|
$0.17
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$59.43
|
$0.32
|
$0.13
|
$0.19
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$66.95
|
$0.43
|
$0.15
|
$0.28
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$68.43
|
$0.47
|
$0.19
|
$0.28
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$69.07
|
$0.46
|
$0.18
|
$0.28
|
Rigid-carrying capacity over 14 tonnes or more
|
$73.12
|
$0.56
|
$0.20
|
$0.36
|
Single Axle Prime Mover
|
$74.28
|
$0.53
|
$0.15
|
$0.38
|
Bogie Axle Prime Mover
|
$80.30
|
$0.65
|
$0.19
|
$0.46
|
A.2 Hourly and kilometre rates (other than for Light Vehicles) - not new vehicles
A.2.1 A contract carrier
performing work using a vehicle which is six or more years old must be paid at
least the hourly and kilometre
rates set out in the following table (rounded up to the nearest half hour,
and nearest kilometre). For the avoidance of confusion, the per kilometre
rate payable is the Running Rate. The Running Rate is the total
of the "Per km excluding fuel component" and the "Per km fuel component".
The "Per km excluding fuel component" and the "Per km fuel
component" columns have been included for ease of reference when updating
rates.
From the first full pay period commencing on or after 12
February 2024:
Class of Vehicle
|
Per
hour
|
Running
Rate
|
Per
km excluding fuel component running rate for the purposes of Schedule C
|
Per
km fuel component of the running rate for the purposes of Schedule C
|
($)
|
($/km)
|
($/km)
|
($/km)
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$50.96
|
$0.37
|
$0.20
|
$0.17
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$56.75
|
$0.42
|
$0.23
|
$0.19
|
Rigid-carrying capacity over 8 and including10 tonnes
|
$60.64
|
$0.51
|
$0.23
|
$0.28
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$66.78
|
$0.56
|
$0.28
|
$0.28
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$66.62
|
$0.55
|
$0.27
|
$0.28
|
Rigid-carrying capacity over 14 tonnes or more
|
$67.92
|
$0.65
|
$0.29
|
$0.36
|
Single Axle Prime Mover
|
$64.33
|
$0.59
|
$0.23
|
$0.36
|
Bogie Axle Prime Mover
|
$69.51
|
$0.72
|
$0.28
|
$0.44
|
From the first full pay period commencing on or after 10
November 2023:
Class of Vehicle
|
Per hour
|
Running Rate
|
Per
km excluding fuel component running rate for the purposes of Schedule C
|
Per
km fuel component of the running rate for the purposes of Schedule C
|
($)
|
($/km)
|
($/km)
|
($/km)
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$48.17
|
$0.36
|
$0.19
|
$0.17
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$53.65
|
$0.41
|
$0.21
|
$0.19
|
Rigid-carrying capacity over 8 and including10 tonnes
|
$57.32
|
$0.50
|
$0.22
|
$0.28
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$63.13
|
$0.55
|
$0.27
|
$0.28
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$62.98
|
$0.54
|
$0.25
|
$0.28
|
Rigid-carrying capacity over 14 tonnes or more
|
$64.21
|
$0.64
|
$0.28
|
$0.36
|
Single Axle Prime Mover
|
$60.78
|
$0.58
|
$0.22
|
$0.36
|
Bogie Axle Prime Mover
|
$65.67
|
$0.71
|
$0.27
|
$0.44
|
A.3 Light Vehicle
Rates
A.3.1 A Contract
Carrier performing work with a Light Vehicle
must be paid at least the hourly
rate set out in the following
table (rounded up the nearest half hour).
From the first full pay period commencing on or after 1 March
2022:
Class of Vehicle
|
Per hour
$
|
Bicycle
|
$21.82
|
Motorcycles
|
$26.85
|
Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity
of:
|
|
Up to 750kg
|
$29.85
|
Over 750kg
and up to 1 tonne
|
$30.68
|
Over 1 tonne and
up to 1.5 tonnes
|
$31.06
|
Over 1.5 tonnes and up to 3 tonnes
|
$32.71
|
From the first full pay period commencing on or after
1 July 2022:
Class of Vehicle
|
Per hour
$
|
Bicycle
|
$24.19
|
Motorcycles
|
$28.78
|
Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity
of:
|
|
Up to 750kg
|
$31.84
|
Over 750kg
and up to 1 tonne
|
$32.80
|
Over 1 tonne and
up to 1.5 tonnes
|
$33.55
|
Over 1.5 tonnes and up to 3 tonnes
|
$35.47
|
From the first full pay period commencing on or after
1 July 2023:
Class of Vehicle
|
Per hour
$
|
Bicycle
|
$26.57
|
Motorcycles
|
$30.70
|
Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity
of:
|
|
Up to 750kg
|
$33.82
|
Over 750kg
and up to 1 tonne
|
$34.91
|
Over 1 tonne and
up to 1.5 tonnes
|
$36.05
|
Over 1.5 tonnes and up to 3 tonnes
|
$38.22
|
From the first full pay period commencing on or after
1 July 2024:
Class of Vehicle
|
Per hour
$
|
Bicycle
|
$28.94
|
Motorcycles
|
$32.63
|
Motor cars, vans,
utilities, trucks and other
rigid vehicles with a Carrying Capacity of:
|
|
Up to 750kg
|
$35.81
|
Over 750kg and up to 1 tonne
|
$37.03
|
Over 1 tonne and
up to 1.5 tonnes
|
$38.54
|
Over 1.5 tonnes and up to 3 tonnes
|
$40.98
|
From the first full pay period commencing on or after
1 July 2025:
Class of Vehicle
|
Per hour
$
|
Bicycle
|
$31.32
|
Motorcycles
|
$34.56
|
Motor cars, vans, utilities, trucks and other rigid vehicles with a Carrying Capacity
of:
|
|
Up to 750kg
|
$37.80
|
Over 750kg
and up to 1 tonne
|
$39.15
|
Over 1 tonne and
up to 1.5 tonnes
|
$41.04
|
Over 1.5 tonnes and up to 3 tonnes
|
$43.74
|
NOTE: These Light
Vehicle Rates are subject to any increases
arising from changes
to the superannuation guarantee charge percentage. See subclause
20.8(e) for details.
A.4 NHVR Training
and Accreditation
A.4.1 NHVR Training
and Accreditation System
Set Up
A.4.2 The lump sum allowance
referred to in clause 22.2
is:
(a) From the first
full pay period commencing on or after 12 February 2024:
$7,992.18; and
(b) From the first
full pay period commencing on or after 10 November 2023:
$7,619.78.
A.4.3 The allowance
referred to in clause 22.3 is (rounded
up to the nearest half hour):
From the first full pay period commencing on or
after 12 February 2024:
Class of Vehicle
|
Per hour
$
|
Bogie Axle
Prime Mover
|
$0.48
|
Single Axle Prime Mover
|
$0.48
|
Rigid-carrying capacity over 14 tonnes
or more
|
$0.48
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$0.48
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$0.48
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.48
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.48
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$0.48
|
Rigid-carrying capacity less than 3 tonnes
|
$0.48
|
From the first
full pay period commencing on or after 10 November
2023;
Class of
Vehicle
|
Per hour
$
|
Bogie Axle Prime
Mover
|
$0.46
|
Single Axle Prime
Mover
|
$0.46
|
Rigid-carrying capacity over
14 tonnes or more
|
$0.46
|
Rigid-carrying capacity over
12 and including 14 tonnes
|
$0.46
|
Rigid-carrying capacity over
10 and including 12 tonnes
|
$0.46
|
Rigid-carrying capacity over
8 and including 10 tonnes
|
$0.46
|
Rigid-carrying capacity over
5 and including 8 tonnes
|
$0.46
|
Rigid-carrying capacity over
3 and including 5 tonnes
|
$0.46
|
Rigid-carrying capacity less
than 3 tonnes
|
$0.46
|
A.5 Blue Card
A.5.1 A Contract Carrier
who in order to perform
a Contract of Carriage is required to obtain
a blue card (or equivalent), after this Determination has come into operation,
shall be paid the following amounts (rounded up to the nearest half hour):
From the first full pay period commencing on or
after 12 February 2024:
Class of Vehicle
|
Per hour
|
$
|
Bogie Axle
Prime Mover
|
$0.05
|
Single Axle
Prime Mover
|
$0.05
|
Rigid-carrying capacity over 14 tonnes
or more
|
$0.05
|
Rigid-carrying capacity over 12 and
including 14 tonnes
|
$0.05
|
Rigid-carrying capacity over 10 and
including 12 tonnes
|
$0.05
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.05
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.05
|
Rigid-carrying capacity over 2 and including 5 tonnes
|
$0.05
|
Rigid-carrying capacity less than 3 tonnes
|
|
From the first
full pay period
commencing on or after 10 November 2023:
Class of Vehicle
|
Per hour
|
$
|
Bogie Axle
Prime Mover
|
$0.05
|
Single Axle
Prime Mover
|
$0.05
|
Rigid-carrying capacity over 14 tonnes
or more
|
$0.05
|
Rigid-carrying capacity over 12 and
including 14 tonnes
|
$0.05
|
Rigid-carrying capacity over 10 and
including 12 tonnes
|
$0.05
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.05
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.05
|
Rigid-carrying capacity over 2 and including 5 tonnes
|
$0.05
|
Rigid-carrying capacity less than 3 tonnes
|
|
A.5.2 However, a
Principal Contractor will not be required to make any such payment in
circumstance where the Principal Contractor has previously paid for a Contract Carrier
to obtain the appropriate blue card (or equivalent).
A.6 Workwear and PPE
A.6.1 A Contract Carrier who, in order to perform a contract of carriage, is required by a Principal Contractor to wear certain
type of workwear and/or personal
protective equipment shall be paid the
following amounts:
From the first full pay period commencing on or
after 12 February 2024:
Class of Vehicle
|
Per hour
|
$
|
Bogie Axle
Prime Mover
|
$0.33
|
Single Axle
Prime Mover
|
$0.33
|
Rigid-carrying capacity over 14 tonnes
or more
|
$0.33
|
Rigid-carrying capacity over 12 and
including 14 tonnes
|
$0.33
|
Rigid-carrying capacity over 10 and
including 12 tonnes
|
$0.33
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.33
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.33
|
Rigid-carrying capacity over 2 and including 5 tonnes
|
$0.33
|
Rigid-carrying capacity less than 3 tonnes
|
|
From the first
full pay period
commencing on or after 10 November 2023:
Class of Vehicle
|
Per hour
|
$
|
Bogie Axle
Prime Mover
|
$0.31
|
Single Axle Prime Mover
|
$0.31
|
Rigid-carrying capacity over 14 tonnes
or more
|
$0.31
|
Rigid-carrying capacity over 12 and
including 14 tonnes
|
$0.31
|
Rigid-carrying capacity over 10 and
including 12 tonnes
|
$0.31
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.31
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.31
|
Rigid-carrying capacity over 2 and including 5 tonnes
|
$0.31
|
Rigid-carrying capacity less than 3 tonnes
|
|
A.6.2 A Principal
Contractor will not be required to make any such payment in circumstance where
the Principal Contractor provides the Contract Carrier with the certain type of
workwear and/or personal protective equipment
A.7 Additional amounts
A.7.1 Ropes and Gear Allowance
A Contract Carrier who, in order to
perform a contract of carriage, is required to supply tarpaulins, ropes, gates,
chains and dogs for use in a Contract of Carriage must be paid the following
allowance per day or part day during which the equipment is used for the
purpose of the Contract of Carriage:
(a) From the first
full pay period on or after 12 February 2024: $5.01
(b) From the first
full pay period on or after 10 November 2023: $4.78
A.7.2 Twistlock Allowance
A Contract Carrier who, in order to
perform a Contract of Carriage, is required to fit his trailer with twistlocks for the carriage of I.S.O. containers must be
paid the following allowance per day or part day during which the equipment is
used for the purpose of the Contract of Carriage:
(a) From the first
full pay period commencing on or after 12 February 2024: $3.76
(b) from the first
full pay period commencing on or after 10 November 2023: $3.58
A.7.3 Mechanical Lifting
Equipment Allowance
A Contract Carrier
who, in order to perform
a contract of carriage, is required to supply rear or side- loading mechanical devices, shall be paid the following
allowance for each day (and proportionately
for part of a day) during which the equipment is used for the purpose of the
Contract of Carriage:
From the first full pay period commencing on or
after 12 February 2024:
Equipment type
|
Per day
|
$
|
Rear-Lift Platform up to and including 3,000 lbs capacity
|
$6.00
|
Rear-Lift Platform up to and including 6,000 lbs capacity
|
$8.24
|
Side loading device
|
$26.49
|
From the first
full pay period
commencing on or after 10 November 2023:
Equipment type
|
Per day
|
$
|
Rear-Lift Platform up to and including 3,000
lbs capacity
|
$5.72
|
Rear-Lift Platform up to and including 6,000
lbs capacity
|
$7.85
|
Side loading device
|
$25.26
|
SCHEDULE B - WATERFRONT AND CONTAINER DEPOTS
1. The following conditions and allowances shall apply to contracts of carriage performed in or in connection
with Container Depots and Waterfront areas, in addition to all other conditions
provided for by this Contract Determination but in substitution for the rates
in Schedule A.
From the first full pay period commencing on or
after 12 February 2024:
Class of Vehicle
|
Rate
|
Rigid Vehicle
|
|
Not less than 8 and not greater than 10 tonnes
|
$67.85
|
Not less than 10 and not greater than 12 tonnes
|
$74.65
|
Not less than 12 and not greater than 14 tonnes
|
$74.29
|
Not less than 14 tonnes
|
$77.06
|
Single Axle Prime Mover
|
$72.65
|
Bogie Axle Prime Mover
|
$79.62
|
From the first
full pay period
commencing on or after 10 November 2023:
Class of Vehicle
|
Rate
|
Rigid Vehicle
|
|
Not less than 8 and not
greater than 10 tonnes
|
$66.47
|
Not less than 10 and not
greater than 12 tonnes
|
$72.92
|
Not less than 12 and not
greater than 14 tonnes
|
$72.58
|
Not less
than 14 tonnes
|
$75.86
|
Single Axle
Prime Mover
|
$71.66
|
Bogie Axle
Prime Mover
|
$78.88
|
The above rates of remuneration are calculated using
the following formula:
(Hourly Rate
x 221 x 7.6) + (Km Rate x 23,500)
(221 x 7.6)
where Hourly Rate and km Rate are the relevant
per hour and per km rates for a 6 year+ vehicle
in Schedule A - Rates of Remuneration.
This formula is based on a minimum distance travelled
of 23,500 km per annum on contracts of carriage performed in or in connection
with Container Depots and Waterfront areas.
2. Trailer Allowance:
A Contract Carrier who, in order
to perform a contract of carriage,
is required to supply one of the trailers listed below (irrespective of
axle configuration), shall be paid the following allowance for each day, (or part
of a day) during the equipment is so used:
From the first full pay period commencing on or
after 12 February 2024:
|
Rate A - Subsidy
|
Rate B - No Subsidy
|
40 ft Skel trailer
|
$58.60 per day
|
$59.80 per day
|
40 ft General Purpose trailer
|
$58.60 per day
|
$62.98 per day
|
Dog or Pig trailer
|
$43.87 per day
|
$47.12 per day
|
Pup trailer
|
$29.29 per day
|
$31.48 per day
|
20 ft Skel trailer
|
$52.75 per day
|
$56.69 per day
|
From the first
full pay period commencing on or after 10 November
2023:
|
Rate A - Subsidy
|
Rate B - No Subsidy
|
40 ft Skel trailer
|
$55.42 per day
|
$56.55per day
|
40 ft General Purpose trailer
|
$55.42per day
|
$59.55 per day
|
Dog or Pig trailer
|
$41.48 per day
|
$44.56 per day
|
Pup trailer
|
$27.70 per day
|
$29.77 per day
|
20 ft Skel trailer
|
$49.88 per day
|
$53.61 per day
|
3. Towing rates:
A Contract Carrier,
whose vehicle is in the performance
of a
contract of carriage, is required to tow one of the
trailers listed below
(irrespective of axle configuration), shall be paid the following allowance for each
hour (pro-rata for part of an hour) during which such trailer is towed:
From the first full pay period commencing on or
after 12 February 2024:
40 ft trailer
|
$3.37 per hour
|
$3.29 per hour
|
Dog/Pig trailer
|
$6.61 per hour
|
$6.44 per hour
|
Pup trailer
|
$4.88 per hour
|
$4.76 per hour
|
From the first
full pay period
commencing on or after 10 November 2023:
40 ft trailer
|
$3.19 per
hour
|
$3.11 per
hour
|
Dog/Pig trailer
|
$6.25 per
hour
|
$6.09 per hour
|
Pup trailer
|
$4.61 per
hour
|
$4.50 per
hour
|
4. Adjustment of
the allowances and rates in Clause 3 and 4 of this Schedule shall be by
application of the movement of the Consumer Price Index (All Groups), Sydney.
5. Contract Carriers
who perform work pursuant
to this Schedule shall have paid on their behalf
by principal contractors who are
members of the NSW Road Transport Association contributions into the TWU
Superannuation Fund in the amounts
prescribed by the Transport Industry (State) Superannuation Award.
6. Clause 3, Savings clause,
of this Determination shall apply to the above rates and conditions.
SCHEDULE C - PROCEDURE AND TIME FOR ADJUSTMENTS OF RATES
C.1 Procedure for adjustment of rates
C.1.1 The rates prescribed in Schedules B and C shall be adjusted with effect from 1 June and 1 December
each year or as provided in this Schedule.
C.1.2 The union shall
make application to the IRC for a variation in rates and amounts in sufficient
time for the variation to be made on or before
1 June and 1 December
each year. Notwithstanding anything contained in this Schedule, a variation shall not be
retrospective in operation but shall operate from a date not earlier than the date upon which it is made.
C.1.3 The parties
to this determination shall confer
with a view to reaching
agreement on the variation. In the
absence of agreement, the rates and amounts shall be determined by the IRC in accordance with the Method of Adjustment outlined in this Schedule.
C.1.4 The adjustment to be made from 1 December shall take into account all movements in costs occurring and indices published up to the preceding 31 October and the adjustment from 1 June shall
take into account all movements in costs
occurring and indices published up to the preceding 30 April.
C.1.5 Each variation after the first variation
shall be based upon the rates and amounts in the immediately preceding variation.
C.1.6 If any one of the
below listed components, except for fuel,
changes such that it causes an increase in the total remuneration of 5 per cent
or more from the date of the last variation, an interim adjustment may be made.
C.1.7 The components of remuneration shall be adjusted
upwards or downwards according to the following schedule:
Component
|
Method of Adjustment
|
1. Total Labour Costs
|
Adjust according to the actual percentage change in the Minimum Weekly Rate for the relevant Transport Worker Grade
in the Road
Transport and Distribution Award 2010.
|
2. Fuel
|
Adjust according to the percentage change
in the Australian Institute of Petroleum NSW State weekly
average for the retail price
of diesel, excluding GST.
|
3. Capital
|
Adjust by reference to the average
percentage change in the TransEco Road Freight Cost
Indices Report: Shorthaul cost change of Capital.
|
4. Service and Parts
|
Adjust by reference to the average
percentage change in the TransEco Road Freight
Cost Indices Report: Shorthaul cost change of Maintenance.
|
5. Registration, Licensing and Insurances
|
Adjust by reference to the average
percentage change in the TransEco Road Freight Cost
Indices Report: Shorthaul cost change of Insurance.
|
6. Training and compliance
|
Adjust by reference to the average
percentage change in the TransEco Road Freight Cost Indices Report:
Shorthaul
cost change of Admin.
|
7. Miscellaneous Fixed
Costs
|
Adjust by reference to the average
percentage change in the TransEco Road Freight Cost
Indices Report: Shorthaul cost change of Admin.
|
C.1.8 The procedure outlined in subclause
E.1 does not apply to Light Vehicle
Rates.
C.2 Cost Recovery
for variations in the Price of fuel
C.2.1 Due to the changeable
nature of the pricing of fuel, including significant fluctuations in the price of fuel, it is necessary that variations to rates of remuneration to take
into account changes
in the price of fuel occur in a timely and efficient manner.
C.2.2 Any party to this determination may make an application to the IRC to vary rates of remuneration to account
for changes in the price of fuel on the following basis:
(a) an application to vary rates of
remuneration for changes in the price of fuel may be made at any time,
provided that the date upon which any rate adjustment is sought to become
operative is at least one calendar month after the last occasion upon which a
fuel rate adjustment became operative;
(b) it is not a requirement
of any such application that the rate adjustment sought for fuel only be one
which is either below or above any minimum threshold amount; and
(c) the benchmark
for the price of fuel shall be the Australian Institute of Petroleum NSW weekly
average for the retail price of diesel for the week ending immediately prior to
the date of filing the application, excluding GST.
C.2.3 The parties to
this determination shall take all necessary steps to enable an application made
pursuant to this Schedule to be
heard and determined at the earliest possible time, including but not limited to, consenting to have the IRC hear and determine
any such application within 48 hours from the initial listing of the
application.
SCHEDULE D - NOMINATED CONTRACT
DETERMINATION
The Nominated
Contract Determinations are:
1.
Transport Industry
- Car Carriers (N.S.W.) Contract
Determination;
2.
Transport Industry
- Concrete Haulage
Contract Determination;
3.
Transport Industry - Excavated Materials Contract Determination;
4.
Transport Industry
- Quarried Materials
Contract Determination;
5.
Transport Industry
- Waste Collection and Recycling Contract
Determination;
6.
Hanson Construction Materials Pty Limited Concrete
Carriers Contract Determination;
7.
Transport Industry
- Courier and Taxi Truck Contract Determination;
8.
Transport Industry
- Concrete Haulage
- Mini Trucks Contract Determination;
9.
Transport Industry
- Readymix Holdings
Pty Ltd Concrete Cartage Contract
Determination;
10.
Boral Transport Limited Haulier Contract
Determination;
11.
CEVA Logistics (Australia) Pty Ltd (NSW Vehicle
Logistics Local Fleet)
Contract Determination;
12.
Readymix Holding Pty Ltd Sydney Concrete
Carriers Contract Determination;
13.
Readymix Holdings Pty Ltd Country Concrete
Carriers Contract Determination;
14.
Transport Industry
- Quarried Materials, &c., Carriers Interim
Contract Determination;
15.
Australian Liquor Marketers Pty Limited Carriers Contract Determination;
16.
Boral Country
- Concrete and Quarries Contract
Determination;
17.
Boral Resources (NSW) Pty Limited
Sydney Metropolitan Concrete
Contract Determination;
18.
Transport Industry
- Metromix Concrete
Haulage Contract Determination;
19.
Transport Industry
- Allied Express
TWU Interim Contract
Determination;
20.
Couriers Please
Pty Ltd Contract Determination;
21.
Transport Industry
- Mayne Logistics Contract Determination;
22.
Transport Industry
- Penrith City Council Contract
Determination;
23.
Boral GST Protocol (Facilitation and Compliance) Contract Determination;
24.
TNT Domestic & International Express Ancillary Contract Determination, The;
25.
Superior Premix Contract Determination No. 2;
26.
Superior Premix
Contract Determination - Blacktown City Council Project;
27.
Transport Industry
- General Carriers
(The Smith Family)
Contract Determination;
28.
Boral Transport Limited Quarried Materials Minimum Load Contract Determination; and
29.
Monier Roofing Limited and Reliance Roof Tiles Pty Ltd Contract
Determination.
SCHEDULE E - SUPERANNUATION CONTRIBUTION ARRANGEMENTS
This Schedule is intended to ensure Principal
Contractors are not subject to the cost of both providing rates
that compensate for superannuation costs and separately making
contributions upon a contract carrier’s behalf.
E.1 ARRANGEMENT BY AGREEMENT
E.1.1 A Principal
Contractor and Contract Carrier may enter an arrangement whereby the Principal
Contractor makes superannuation
contributions for the benefit of the Contract Carrier.
E.1.2 A Principal Contractor
may deduct from any remuneration payable to the Contract Carrier an amount no
greater than the contributions that the Principal Contractor is required to
make under such an arrangement.
E.2 Any such arrangement must be reduced
to writing and must set out:
E.2.1 the amount
of the contribution (whether as a fixed amount, a percentage of the Contract
Carriers remuneration, or a combination of both);
E.2.2 in what period the contributions will be made (monthly, quarterly
etc.); and
E.2.3 when the deductions are to be made.
E.3 Within 28 days
of making superannuation contributions for a Contract Carrier’s benefit, the
Principal Contractor must provide the Contract Carrier with a written statement
setting out the amount of contributions made and the
account into which they have been paid.
E.4 ARRANGEMENT BY DIRECTION
E.4.1 A Principal Contractor may implement a
superannuation arrangement without the agreement of a Contract Carrier if:
E.4.2 the Contract
Carrier is not an incorporated entity; and
E.4.3 the Principal
Contractor has a reasonably held belief that the payment of superannuation
contributions for the benefit of the Contract Carrier is required to reduce a
Superannuation Guarantee Charge liability that would otherwise accrue to the
Principal Contractor.
E.5 An arrangement entered into in accordance with subclause 2.1 is subject
to the following terms:
E.5.1 any deductions
from a Contract Carrier’s remuneration must be made in the same pay period for
which the Contract Carrier is remunerated for the relevant cartage work;
E.5.2 superannuation
contributions must be made no later than 28 days after the end of the quarter
in which the relevant cartage work was performed; and
E.5.3 superannuation contributions must be paid into:
(a) a complying superannuation fund chosen
by the Contract Carrier;
(b) the Contract
Carrier's stapled superannuation fund (if the Contract Carrier
does not choose
a fund or if the
Principal Contractor is not able to make contributions
to the chosen fund); or
(c) TWUSuper (in the absence of a chosen
or stapled superannuation fund into which the
Principal Contractor can make contributions).
E.6 Within 28 days
of making superannuation contributions for a Contract Carrier’s benefit, the
Principal Contractor must provide the Contract Carrier with a written statement
setting out the amount of contributions made and the
account into which they have been paid
E.7 Any disputes
concerning the operation of this Schedule are to be dealt with using the
dispute resolution procedures at clause 26.
SCHEDULE F - TEMPORARY FUEL SURCHAGE
F.1 APPLICATION
F.1.1 This Schedule
applies to all Contracts of Carriage to which Part 4 of this Determination
applies, other than Contracts of Carriage performed by a Light Vehicle.
F.2 BACKGROUND
F.2.1
This Schedule was introduced by the IRC in
Matter No. 2022/77087 as a temporary measure to respond to significant fluctuations in the price of fuel arising from the war in Ukraine
and the temporary
inability for Contract Carriers to claim fuel tax
credits.
F.3 THE SURCHARGE
F.3.1 In addition to
all other amounts set out in this Determination, a Principal Contractor must
pay a Contract Carrier an additional amount (the Temporary Fuel Surcharge).
F.3.2 For pay periods
commencing between 19 February 2024 and 17 March 2024, the Temporary Fuel
Surcharge shall be:
Vehicle Carrying Capacity
|
Surcharge (per
km)
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$0.10
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.12
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.17
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$0.17
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$0.17
|
Rigid-carrying capacity over 14 tonnes
or more
|
$0.22
|
Single Axle Prime Mover
|
$0.22
|
Bogie Axle
Prime Mover
|
$0.27
|
For pay periods commencing between 15 January 2024 and
18 February 2024, the Temporary Fuel Surcharge shall be:
Vehicle Carrying
Capacity
|
Surcharge (per km)
|
Rigid-carrying capacity over 3 and including 5 tonnes
|
$0.11
|
Rigid-carrying capacity over 5 and including 8 tonnes
|
$0.13
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$0.19
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$0.19
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$0.19
|
Rigid-carrying capacity over 14 tonnes or more
|
$0.25
|
Single Axle Prime Mover
|
$0.25
|
Bogie Axle Prime Mover
|
$0.30
|
F.3.3 Where Schedule
C (which deals
with waterfront and container depots)
applies to a Contact of Carriage, the Principal Contractor may elect to pay the following Temporary Fuel Surcharge in lieu
of the amount in clause 3.2:
For pay periods commencing between 19 February 2024 and
17 March 2024:
Vehicle Carrying Capacity
|
Surcharge (per
km)
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$2.45
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$2.45
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$2.45
|
Rigid-carrying capacity over 14 tonnes
or more
|
$3.14
|
Single Axle Prime Mover
|
$3.15
|
Bogie Axle
Prime Mover
|
$3.82
|
For pay periods commencing between 15 January 2024 and
18 February 2024:
Vehicle Carrying
Capacity
|
Surcharge
(per hour)
|
Rigid-carrying capacity over 8 and including 10 tonnes
|
$2.71
|
Rigid-carrying capacity over 10 and including 12 tonnes
|
$2.71
|
Rigid-carrying capacity over 12 and including 14 tonnes
|
$2.71
|
Rigid-carrying capacity over 14 tonnes or more
|
$3.47
|
Single Axle Prime Mover
|
$3.49
|
Bogie Axle Prime Mover
|
$4.23
|
F.4 REVIEW
F.4.1 The Temporary
Fuel Surcharge shall be reviewed
on a monthly
basis.
F.4.2 The Temporary Fuel
Surcharge shall be calculated by updating the fuel component of the Cost Model
with the mean of all weekly retail
diesel prices (NSW State Average)
published by the Australian Institute of Petroleum
for weeks ending in the prior calendar month.
F.4.3 Parties shall calculate the Temporary Fuel Surcharge and provide the results to the IRC by the second Monday
of each calendar month.
F.4.4 The
revised Temporary Fuel Surcharge will apply from the third Monday in each calendar
month.
F.4.5 As the Temporary Fuel Surcharge responds
to fluctuations in fuel prices,
it may increase or decrease
from time to time.
F.5 OTHER PROVISIONS
F.5.1 The Temporary Fuel Surcharge may be offset by any payments made to a Contract Carrier
in excess of the amounts
prescribed elsewhere in this Determination.
F.5.2 Leave is reserved
for any party
to apply to vary the operation of this Schedule
in circumstances where the Principal Contractor:
(a) provides the Contract Carrier
with fuel, either
for free or at a cost below the prevailing market rate;
(b) directly reimburses the Contract Carrier
for some or all of their fuel costs;
or
(c) otherwise compensates the Contract
Carrier for their
fuel costs.
____________________
Printed by
the authority of the Industrial Registrar.