Transport Industry - Car Carriers (NSW) Contract
Determination
INDUSTRIAL RELATIONS
COMMISSION OF NEW SOUTH WALES
Application by Transport Workers' Union of New South Wales, Industrial Organisation of Employees.
(Case No. 4509 of 2023)
Before Commissioner Sloan
|
21 February 2023
|
VARIATION
1. Insert after
clause 9 in the Arrangement, of the award published 11 July 2008 (366 I.G. 274)
following new clause:
10. Additional
Payments in Respect of Fuel
2. Substitute the amount
$306.44 with $318.61 wherever it appears in paragraph (a) of sub-clause (i) of clause 7, Other Conditions.
3. Substitute the
amount $367.17 with $381.75 wherever it appears in sub-clause (vii) of clause
8, Conditions.
4. Insert after
clause 9, Leave Reserved, of the award, the following new clause:
10. Additional Payments in Respect of Fuel
10.1 A principal contractor must pay an
additional fuel levy (the fuel levy), which shall be a percentage of
remuneration payable under this contract determination calculated in accordance
with the following formula:
[((Current
Fuel Cost) minus (Base Fuel Cost)) divided by the Base Fuel Cost] multiplied by
[the Base Fuel Percentage].
Where:
"Current
Fuel Cost" is either:
(a) In the case of a contract carrier who
buys fuel, the current monthly average of per litre rates for fuel according to
the most recent AIP NSW State average for the price of diesel; or
(b) In the case of a contract carrier who is
provided fuel by the Principal Contractor, the cost charged by the Principal
Contractor to the Contract Carrier for the provision of that fuel.
"Base
Fuel Cost" is $1.26 per litre (excluding GST)
"Base
Fuel Percentage" is the Reset Weighting percentage given to fuel in the
Car Carriers Adjustment Calculations Table contained in Schedule 1
By way of
example, if the price of fuel were 200.6 (excluding GST) the formula would be
applied as follows:
(200.60 - 126.09)
divided by 126.09 = 0.5909 x 15.95% = 9.42%
10.2 The fuel levy will be calculated by the
Principal Contractor on a monthly basis. The Principal
Contractor will advise Contract Carrier of the quantum of the fuel levy on a monthly basis and the basis of the calculation. If the
Contract Carrier (or his or her representative) does not dispute the accuracy
of the calculation of such rates within 7 days of receiving notification of an
adjustment to the fuel levy, then regardless of any error in calculations, the
fuel levy, as calculated will be payable until the Contract Carrier (or his or
her representative) advises that the fuel levy has been incorrectly calculated.
5. Substitute the percentage
0.81% with 1.84% where it appears in sub-clause
(ii) of Schedule 1, Rates of Remuneration.
6. Delete
sub-clause (vii) of Schedule 1, Rates of Remuneration and insert in lieu
thereof the following:
(vii) The rates
contained within this schedule shall take effect from the first full pay period
commencing on or after 21 February 2023:
Car Carriers Contract Determination Rate Adjustment
|
Percentage variation = 3.972
|
Category
|
Old Value
|
New Value
|
% Change
|
Current Weighting
|
New Weighting
|
Reset Weighting
|
Wages
|
849.10
|
889.1
|
4.71
|
42.03
|
44.01
|
42.33
|
Capital
|
102.6
|
107.30
|
4.58
|
13.36
|
13.97
|
13.44
|
Insurances
|
139.30
|
145.10
|
4.16
|
13.02
|
13.56
|
13.04
|
Registration
|
133.80
|
137.50
|
2.77
|
5.34
|
5.49
|
5.28
|
R&M
|
120.50
|
128.00
|
6.22
|
6.23
|
6.62
|
6.36
|
Tyres
|
114.80
|
128.00
|
11.50
|
1.14
|
1.27
|
1.22
|
Fuel
|
126.09
|
126.09
|
0.00
|
16.58
|
16.58
|
15.95
|
Admin
|
119.70
|
128.60
|
7.44
|
2.30
|
2.47
|
2.38
|
|
|
|
|
100.00
|
103.972
|
100.00
|
7. Delete Tables
"A", "B", "C", "D", "E" and
"F" of Schedule I and insert in lieu thereof the following:
Table A (Including
2% Trailer Hire)
Local Work
|
Zone Rates per Car Carriage - Prime Mover
|
Zone
|
1 Car Capacity $
|
3 Car Capacity $
|
4 Car Capacity $
|
5 Car Capacity $
|
6 Car Capacity $
|
1 Car Tilt $
|
1
|
39.37
|
62.38
|
82.47
|
102.29
|
112.98
|
46.04
|
2
|
59.48
|
92.76
|
116.90
|
141.60
|
154.96
|
69.57
|
3
|
76.24
|
117.45
|
144.44
|
175.60
|
191.89
|
89.10
|
4
|
89.61
|
137.78
|
171.81
|
209.65
|
228.62
|
104.80
|
5
|
99.68
|
165.79
|
199.27
|
243.64
|
265.55
|
116.54
|
Rates Per Car Delivered
|
Zone
|
1 Car Capacity $
|
3 Car Capacity $
|
4 Car Capacity $
|
5 Car Capacity $
|
6 Car Capacity $
|
1 Car Tilt $
|
1
|
39.37
|
20.80
|
20.63
|
20.54
|
18.82
|
46.04
|
2
|
59.48
|
30.92
|
29.22
|
28.31
|
25.82
|
69.57
|
3
|
76.24
|
39.05
|
36.13
|
35.10
|
30.70
|
89.10
|
4
|
89.61
|
45.93
|
42.97
|
41.93
|
38.13
|
104.80
|
5
|
99.68
|
55.27
|
49.81
|
48.72
|
44.27
|
116.54
|
Vehicle
|
Standing and Running Rate per Hour
$
|
Standing Rate per Hour
$
|
1 car
|
50.26
|
38.97
|
3 car
|
60.83
|
48.32
|
4 car
|
68.76
|
54.98
|
5 car
|
72.93
|
57.58
|
6 car
|
78.86
|
62.94
|
1 car tilt
|
58.74
|
45.02
|
Intrastate Work
|
Vehicle
|
Standing and Running Rate cents per Km
|
1 Car
|
96.84
|
3 Car
|
138.70
|
4 Car
|
153.57
|
5 Car
|
170.39
|
6 car
|
183.19
|
7 car
|
185.07
|
1 car tilt
|
113.61
|
|
|
|
|
|
|
|
|
|
|
Table B - Local
Work
Local Work
|
Zone Rates per Car Carriage - Prime Mover
& Trailer
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt $
|
1
|
40.98
|
69.89
|
93.39
|
118.19
|
129.51
|
49.89
|
2
|
61.92
|
103.98
|
132.14
|
163.13
|
179.95
|
75.38
|
3
|
79.36
|
131.32
|
163.24
|
202.15
|
222.82
|
96.60
|
4
|
93.27
|
158.47
|
194.35
|
241.45
|
265.55
|
113.63
|
5
|
103.76
|
185.83
|
225.41
|
280.56
|
308.63
|
126.34
|
Rates Per Car Delivered
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt $
|
1
|
40.98
|
23.31
|
23.36
|
23.64
|
21.55
|
49.89
|
2
|
61.92
|
34.65
|
33.05
|
32.63
|
29.99
|
75.38
|
3
|
79.36
|
43.77
|
40.80
|
40.43
|
37.15
|
96.60
|
4
|
93.27
|
52.83
|
48.59
|
48.27
|
44.27
|
113.63
|
5
|
103.76
|
61.95
|
56.35
|
56.09
|
51.40
|
126.34
|
Vehicle
|
Standing and Running Rate per Hour
$
|
Standing Rate per Hour
$
|
1 car
|
52.30
|
40.91
|
3 car
|
68.19
|
48.93
|
4 car
|
71.31
|
51.60
|
5 car
|
83.96
|
59.90
|
6 car
|
91.53
|
77.32
|
1 car tilt
|
63.68
|
49.28
|
Intrastate Work
|
Vehicle
|
Standing and Running Rate cents per Km
|
1 Car
|
95.22
|
3 Car
|
147.80
|
4 Car
|
164.11
|
5 Car
|
182.25
|
6 car
|
190.25
|
1 car tilt
|
117.24
|
|
|
|
|
|
|
|
|
|
|
Table C (Including 2% Trailer Hire)
Local Work
|
Zone Rates per Car Carriage - Prime Mover
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt $
|
1
|
39.82
|
63.13
|
84.32
|
104.40
|
114.90
|
46.01
|
2
|
60.19
|
93.91
|
119.49
|
143.98
|
157.64
|
69.46
|
3
|
77.18
|
118.58
|
147.58
|
177.74
|
195.01
|
89.06
|
4
|
90.75
|
143.21
|
175.68
|
213.10
|
232.40
|
104.72
|
5
|
100.89
|
167.86
|
203.78
|
247.77
|
269.79
|
116.50
|
Rates Per Car Delivered
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt $
|
1
|
39.82
|
21.03
|
21.06
|
20.90
|
19.16
|
46.01
|
2
|
60.19
|
31.29
|
29.86
|
28.80
|
26.26
|
69.46
|
3
|
77.18
|
39.54
|
36.90
|
35.54
|
32.49
|
89.06
|
4
|
90.75
|
47.73
|
43.94
|
42.61
|
38.75
|
104.72
|
5
|
100.89
|
55.98
|
50.96
|
49.55
|
44.98
|
116.50
|
Vehicle
|
Standing and Running Rate per Hour
$
|
Standing Rate per Hour
$
|
1 car
|
50.89
|
38.93
|
3 car
|
61.60
|
48.31
|
4 car
|
70.89
|
54.97
|
5 car
|
74.13
|
57.56
|
6 car
|
80.14
|
62.85
|
1 car tilt
|
58.73
|
44.98
|
Intrastate Work
|
Vehicle
|
Standing and Running Rate cents per Km
|
1 Car
|
99.17
|
3 Car
|
142.60
|
4 Car
|
161.31
|
5 Car
|
177.00
|
6 car
|
190.43
|
1 car tilt
|
113.54
|
|
|
|
|
|
|
|
|
|
|
Table D (Including
2% Trailer Hire)
Local Work
|
Zone Rates per Car Carriage - Prime Mover
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt
$
|
Base rate
|
220.14
|
304.55
|
339.34
|
371.59
|
400.71
|
257.18
|
1
|
244.11
|
333.57
|
372.14
|
410.07
|
438.51
|
285.19
|
2
|
268.07
|
362.57
|
404.90
|
441.14
|
476.11
|
313.24
|
3
|
292.01
|
391.59
|
437.69
|
475.90
|
513.70
|
341.22
|
4
|
316.01
|
420.61
|
470.44
|
510.69
|
551.30
|
369.27
|
5
|
369.91
|
485.85
|
544.22
|
588.95
|
635.90
|
432.27
|
Rates Per Car Delivered
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt
$
|
Base rate
|
220.14
|
101.53
|
84.82
|
74.32
|
66.82
|
257.18
|
1
|
244.11
|
111.18
|
93.04
|
81.27
|
73.08
|
285.19
|
2
|
268.07
|
120.86
|
101.25
|
88.22
|
79.35
|
313.24
|
3
|
292.01
|
130.53
|
109.42
|
95.18
|
84.40
|
341.22
|
4
|
316.01
|
140.20
|
117.62
|
102.14
|
91.89
|
369.27
|
5
|
369.91
|
161.94
|
136.04
|
117.80
|
105.97
|
432.27
|
Vehicle
|
Standing and Running Rate per Hour
$
|
Standing Rate per Hour
$
|
1 car
|
47.92
|
37.16
|
3 car
|
58.02
|
46.07
|
4 car
|
65.57
|
52.43
|
5 car
|
69.54
|
54.91
|
6 car
|
75.20
|
60.02
|
1 car tilt
|
56.02
|
42.93
|
Intrastate Work
|
Vehicle
|
Standing and Running Rate cents per Km
|
1 Car
|
92.35
|
3 Car
|
132.26
|
4 Car
|
146.44
|
5 Car
|
162.49
|
6 car
|
174.68
|
1 car tilt
|
108.34
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table E (Including
2% Trailer Hire)
Local Work
|
Zone Rates per Car Carriage - Prime Mover
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt
$
|
Base rate
|
220.14
|
320.80
|
358.60
|
395.04
|
422.47
|
269.57
|
1
|
245.08
|
353.36
|
396.17
|
435.07
|
466.10
|
299.94
|
2
|
270.04
|
385.86
|
433.23
|
475.09
|
509.76
|
350.26
|
3
|
294.95
|
418.38
|
470.32
|
515.12
|
553.41
|
360.66
|
4
|
319.88
|
450.89
|
507.39
|
555.15
|
597.06
|
391.00
|
5
|
376.01
|
524.07
|
590.82
|
645.21
|
695.27
|
459.35
|
Rates Per Car Delivered
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt
$
|
Base rate
|
220.14
|
106.93
|
89.78
|
79.01
|
70.41
|
269.57
|
1
|
245.08
|
117.79
|
99.02
|
87.02
|
77.68
|
299.94
|
2
|
270.04
|
128.64
|
108.32
|
95.03
|
84.94
|
349.63
|
3
|
294.95
|
139.48
|
117.58
|
103.00
|
92.23
|
360.66
|
4
|
319.88
|
150.31
|
126.86
|
111.04
|
99.51
|
391.00
|
5
|
376.01
|
174.70
|
147.71
|
129.05
|
115.89
|
459.35
|
Vehicle
|
Standing and Running Rate per Hour
$
|
Standing Rate per Hour
$
|
1 car
|
49.86
|
39.01
|
3 car
|
65.03
|
46.66
|
4 car
|
74.16
|
53.67
|
5 car
|
80.06
|
57.11
|
6 car
|
87.28
|
66.35
|
1 car tilt
|
60.73
|
47.00
|
Intrastate Work
|
Vehicle
|
Standing and Running Rate cents per Km
|
1 Car
|
90.80
|
3 Car
|
140.93
|
4 Car
|
156.50
|
5 Car
|
173.80
|
6 car
|
181.42
|
1 car tilt
|
111.80
|
|
|
|
|
|
|
|
|
|
|
Table F (Including
2% Trailer Hire)
Port Kembla
Local Work
|
Zone Rates per Car Carriage - Prime Mover
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt
$
|
Base rate
|
224.01
|
311.19
|
352.47
|
382.75
|
413.18
|
257.02
|
1
|
248.27
|
340.56
|
385.98
|
418.13
|
451.41
|
290.75
|
2
|
272.54
|
369.92
|
419.49
|
453.45
|
489.62
|
328.17
|
3
|
296.79
|
399.30
|
452.99
|
488.82
|
527.82
|
341.07
|
4
|
321.05
|
428.69
|
486.51
|
524.19
|
566.35
|
369.06
|
5
|
375.61
|
494.76
|
561.92
|
603.73
|
652.05
|
432.06
|
Rates Per Car Delivered
|
Zone
|
1 Car Capacity
$
|
3 Car Capacity
$
|
4 Car Capacity
$
|
5 Car Capacity
$
|
6 Car Capacity
$
|
1 Car Tilt
$
|
Base rate
|
224.01
|
103.72
|
88.12
|
76.55
|
68.85
|
257.02
|
1
|
248.27
|
113.51
|
96.50
|
83.60
|
63.43
|
290.75
|
2
|
272.54
|
123.31
|
104.89
|
90.70
|
81.61
|
328.17
|
3
|
296.79
|
133.09
|
113.25
|
97.76
|
87.96
|
341.07
|
4
|
321.05
|
142.91
|
121.63
|
104.84
|
94.35
|
369.06
|
5
|
375.61
|
164.92
|
140.49
|
120.74
|
108.67
|
432.06
|
Vehicle
|
Standing and Running Rate per Hour
$
|
Standing Rate per Hour
$
|
1 car
|
48.53
|
37.11
|
3 car
|
58.74
|
46.06
|
4 car
|
67.03
|
52.42
|
5 car
|
70.70
|
54.90
|
6 car
|
76.43
|
59.94
|
1 car tilt
|
56.01
|
42.90
|
Intrastate Work
|
Vehicle
|
Standing and Running Rate cents per Km
|
1 Car
|
94.57
|
3 Car
|
135.98
|
4 Car
|
153.83
|
5 Car
|
168.79
|
6 car
|
181.60
|
1 car tilt
|
108.28
|
|
|
|
|
|
|
|
|
|
|
8. Delete the
table in Schedule 2, Procedure and Time for Adjustment of Rates and Amounts,
and insert in lieu thereof the following:
Component
|
Benchmark
|
Current Index
$
|
Current Weighting
|
Wages
|
Road Transport
and Distribution Award 2010, Grade Three Transport Worker
|
889.1
|
42.33
|
Capital
|
ABS Consumer
Price Index (CPI), Transportation Group, Motor Vehicles
|
107.3
|
13.44
|
Insurances
|
ABS CPI Financial
and insurance services, Insurance Services
|
145.1
|
13.04
|
Registration
|
ABS CPI,
Transportation Group, Other Motoring Charges.
|
137.5
|
5.28
|
Repairs & Maintenance
|
ABS CPI,
Transportation Group, Motor Vehicle Repair and Servicing
|
128
|
6.36
|
Tyres
|
ABS CPI,
Transportation Group, Motor Vehicle Parts and
Accessories
|
128
|
1.22
|
Fuel
|
AIP NSW State
Average for the Retail Price of diesel (excluding GST), calculated by
determining the average of the weekly figures between the end of the quarter
relating to the last variation and the end of the quarter prior to any new
variation. Such calculations must only take into consideration figures for
each relevant full quarter of the year. The end of quarters are as follows:
December 31, March 31, June 30 and September 30.
|
126.09
|
15.95
|
Administration
|
ABS CPI, All
Groups, Sydney
|
128.6
|
2.38
|
Total
|
|
|
100.00
|
9. This variation
will take effect on and from the first full pay period commencing on or after
21 February 2023.
D. SLOAN, Commissioner
____________________