Hy-Tec Industries Pty Ltd - Maxi Concrete Contract Determination
  
Date11/19/2021
Volume390
Part7
Page No.1316
DescriptionVCD - Variation of Contract Determination
Publication No.C9334
CategoryContract Determination
Award Code 1923  
Date Posted11/22/2021

spacer image spacer image

spacer image Click to download*
spacer image

(1923)

SERIAL C9334

 

Hy-Tec Industries Pty Ltd - Maxi Concrete Contract Determination

 

INDUSTRIAL RELATIONS COMMISSION OF NEW SOUTH WALES

 

Application by Hy-Tec Industries Pty Ltd.

 

(Case No. 180627 of 2021)

 

Before Commissioner Stanton

30 September 2021

 

VARIATION

 

1.        Delete clause 2, Hy-Tec to Pay Current Rates, Surcharges and Fees of Schedule 1, of the determination published 15 January 2016 (378 I.G. 1599) and insert in lieu thereof the following:

 

2.  Hy-Tec to Pay Current Rates, Surcharges and Fees

 

2.1      Subject to clause 2.3 of this Schedule, Hy-Tec will:

 

(a)       pay to the Contract Carriers the out of hours surcharges set out in the table at subclause 2.2 below;

 

(b)      continue to pay to the Contract Carriers all other:

 

(i)       Rates;

 

(ii)      surcharges (except for any out of hours surcharges); and

 

(iii)     fees, on the basis they were paid to the Contract Carriers as at the date this Contract Determination was made; and

 

(c)       continue to apply the periodic rise and fall formula on the basis it was applied to all Rates, Surcharges and Fees from the date this Contract Determination is varied.

 

2.2      Table of Out of Hours Surcharges

 

6 Wheeler

Surcharge

Application

Amount

Surcharge 1

Monday to Friday after 5.00am and up to and including 6.00am

$9.53 per m3 (min 3.0 m3)

 

Monday to Friday from 5.00pm and before 7.00pm

 

Surcharge 2

Monday to Friday from 7.00pm and up to and including 5.00am

$15.24 per m3 (min 3.0 m3)

 

Before 6.00am on a Saturday

 

Surcharge 3

Saturday 1.00pm to 5.00pm

$15.24 per m3 (min 3.0 m3)

Surcharge 4

Saturday after 5.00pm

$22.54 per m3

Surcharge 5

Sunday

$22.54 per m3

Surcharge 6

Public Holiday

$30.05 per m3

 

8 Wheeler

Surcharge

Application

Amount

Surcharge 1

Monday to Friday after 5.00am and up to and including 6.00am

$8.46 per m3 (min 3.6 m3)

 

Monday to Friday from 5.00pm and before 7.00pm

 

Surcharge 2

Monday to Friday from 7.00pm and up to and including 5.00am

$13.55 per m3 (min 3.6 m3)

 

Before 6.00am on a Saturday

 

Surcharge 3

Saturday 1.00pm to 5.00pm

$13.55 per m3 (min 3.6 m3)

Surcharge 4

Saturday after 5.00pm

$20.05 per m3

Surcharge 5

Sunday

$20.05 per m3

Surcharge 6

Public Holiday

$26.74 per m3

 

2.3      The Rates and/or Surcharges and Fees and/or the rise and fall formula referred to in clauses 2.1 and 2.2 of this Schedule may be changed subject to:

 

(a)       agreement between Hy-Tec and the Contract Carrier Executive; or

 

(b)      variation of this Contract Determination in accordance with the Industrial Relations Act 1996.

 

2.        This variation shall commence to operate on and from 5 July 2021.

 

 

 

J. D. STANTON, Commissioner

 

 

____________________

 

 

Printed by the authority of the Industrial Registrar.

 

 

 

* to download attachment
  
IE UsersRight click the attachment - Click 'Save Target As' - Select a location - Click 'Save'
Netscape UsersRight click the attachment - Select 'Save Link As' - Select a location - Click 'Save'