1. Delete
paragraph (e) of subclause (2) of clause 6, Wages, of the award published 12
September 1997 and reviewed award published 25 February 2000 (313 I.G. 709) as
varied, and insert in lieu thereof the following:
2. Delete Table
1 - Rates of Pay of Part B, Monetary Rates, and insert in lieu thereof the
following:
3. Delete Item
Nos. 1 to 54 and 73 of Table 2 - Other Rates and Allowances, of Part B,
Monetary Rates, and insert in lieu thereof the following:
Item
|
Clause No.
|
Brief Description
|
Amount $
|
No.
|
|
|
|
1
|
6(2)(a)(i),(ii),
(iii)
|
Journeyman Plumber (Other than Ship’s Plumber) -
|
|
|
|
Industry Allowance
|
19.70 per week
|
|
|
Tool Allowance
|
20.30 per week
|
|
|
Supplementary Payment
|
52.10 per week
|
|
|
Special Allowance
|
7.70 per week
|
|
|
Registration Allowance
|
0.52 per hour
|
|
6(2)(b)
|
Amount deducted from hourly rate of journeyman
|
|
|
|
plumber for Drainer
|
0.05
|
2
|
6(2)(c)(i),(ii),
|
Ship’s Plumber -
|
|
|
(iii),(iv)
|
Industry Allowance
|
10.40 per week
|
|
|
Tool Allowance
|
20.30 per week
|
|
|
Supplementary Payment
|
52.10 per week
|
|
|
Special Allowance
|
7.70 per week
|
|
|
Registration Allowance
|
0.52 per hour
|
|
6(2)(d)(iii)(a)
|
Ships Plumbers Apprentice
|
4.35 per week
|
3
|
7(i)(a)
|
Plumber’s Licence
|
0.68 per hour
|
4
|
7(i)(b)
|
Gasfitter’s Licence
|
0.68 per hour
|
5
|
7(i)(c)
|
Drainer’s Licence
|
0.58 per hour
|
6
|
7(i)(d)
|
Plumber’s and Gasfitter’s Licence
|
0.91 per hour
|
7
|
7(i)(e)
|
Plumber’s and Drainer’s Licence
|
0.91 per hour
|
8
|
7(i)(f)
|
Gasfitter’s and Drainer’s Licence
|
0.91 per hour
|
9
|
7(i)(g)
|
Plumber’s, Gasfitter’s and Drainer’s Licence
|
1.25 per hour
|
10
|
7(ii)
|
Licensed Drainer
|
0.58 per hour
|
11
|
7(iii)(a)
|
Lead Burner
|
0.59 per hour
|
12
|
7(iii)(b)
|
Lead Burner in Chemical Works
|
0.81 per hour
|
13
|
7(iii)(c)(1)
|
Oxyacetylene or Electric Welding Certificate
|
0.42 per hour
|
|
|
Minimum Payment
|
2.95 per day
|
14
|
7(iii)(c)(2)
|
Certificate Holder performing welding to AS4041 - 1998
|
0.61 per hour
|
|
|
Minimum
|
4.68 per day
|
15
|
7(iii)(d)
|
Computing quantities or make-up estimates
|
0.45 per hour
|
16
|
8(i)
|
Tool Allowance Apprentices
|
20.30 per week
|
17
|
9
|
Leading Hands -
|
|
|
|
In charge of up to two employees
|
0.61 per hour
|
|
|
In charge of three to five employees
|
0.73 per hour
|
|
|
In charge of six to ten employees
|
0.95 per hour
|
|
|
In charge of ten or more employees
|
1.20 per hour
|
18
|
10
|
Employed on any chokage or oil chokage etc.
|
5.05 per day
|
19
|
11(i)
|
Wet Work
|
0.45 per hour
|
20
|
11(ii)
|
Insulation Material
|
0.55 per hour
|
21
|
11(iii)
|
Cold Work
|
0.45 per hour
|
22
|
11(iv)
|
Work on WC’s, urinals, soil or waste pipes where used
|
|
|
|
principally by venereal patients
|
0.55 per hour
|
23
|
11(v)
|
Hot Work -
|
|
|
|
Between 46 and 54 degrees Celsius
|
0.43 per hour
|
|
|
Exceeding 54 degrees Celsius
|
0.55 per hour
|
24
|
11(vi)
|
Work with second-hand materials of an unusually dirty
|
|
|
|
or offensive nature
|
0.45 per day
|
25
|
11(vii)
|
Employed inside buildings where chlorine gas and/or
|
|
|
|
hydrogen sulphide gas re-manufactured
|
0.56 per day
|
26
|
11(viii)
|
Engaged on electric welding applicable to plumbing
|
0.12 per hour
|
27
|
11(ix)
|
Operator of explosive powered tools
|
1.06 per day
|
28
|
11(x)(a)
|
Work in maximum security
|
1.13 per hour
|
29
|
11(x)(b)
|
Work in geriatric hospital
|
0.31 per hour
|
30
|
11(xi)
|
Roof Repairs
|
0.63 per hour
|
|
|
Minimum Payment
|
0.63
|
31
|
11(xiii)
|
Employed in mental institutions
|
0.38 per hour
|
32
|
11(xiv)
|
Engaged in tunnel and sewer work and in underground
|
0.46 per hour
|
|
|
shafts exceeding 3 metres in depth
|
|
33
|
11(xv)
|
Engaged on alterations or repairs to boilers, flues,
|
|
|
|
furnaces, retorts and kilns
|
1.19 per hour
|
34
|
11(xvi)
|
Engaged on the construction of chimneys and air shafts
|
|
|
|
where construction exceeded 15 metres in height
|
0.45 per hour
|
|
|
Additional amount for work above each further 15
|
|
|
|
metres
|
0.45 per hour
|
35
|
11(xvii)
|
Employees required to work in a bosun’s chair or on a
|
|
|
|
swinging scaffold -
|
|
|
|
First 4 hours
|
3.23
|
|
|
For each hour thereafter
|
0.67 per hour
|
36
|
11(xviii)
|
Work on any structure at a height of more than 12.2
|
|
|
|
metres
|
0.45 per hour
|
37
|
11(xix)
|
Employees in sanitary works
|
4.95 per day
|
38
|
11(xx)
|
Employees in slaughtering yards
|
0.30 per hour
|
39
|
11(xxii)(a)
|
Employees working west and north of and excluding
|
|
|
|
State highway No. 17 etc, up to the Western Division
|
0.73 per day
|
40
|
11(xxii)(b)
|
Employees working in the Western Division
|
1.19 per day
|
41
|
11(xxii)(c)
|
Employees working in the southern districts
|
1.19 per day
|
42
|
11(xxiii)
|
Engaged in cramped position or without sufficient
|
|
|
|
ventilation
|
0.55 per hour
|
43
|
11(xxiv)
|
Employees required to use materials containing asbestos
|
|
|
|
or to work near asbestos
|
0.55 per hour
|
44
|
11(xxv)
|
Towers Allowance -
|
|
|
|
Exceeding 15 metres - for all work above 15 metres
|
0.45 per hour
|
|
|
For work above each further 15 metres
|
0.45 per hour
|
45
|
11(xxvi)(c)
|
Toxic Substances -
|
|
|
|
Employees using
|
0.55 per hour
|
|
|
Employee working in close proximity
|
0.45 per hour
|
46
|
11(xxx)(d)
|
Engaged in asbestos eradication
|
1.49 per hour
|
47
|
12(i)
|
Employees working in ballast tanks, oil tanks and side
|
0.55 per hour
|
|
|
tanks
|
|
48
|
12(ii)
|
Employees working in ship’s bilges or under engine
|
|
|
|
room or boiler room flooring
|
0.41 per hour
|
49
|
12(iii)
|
Employees working in and around diesel engines
|
0.41 per hour
|
50
|
12(iv)
|
Employees working in a confined space
|
0.58 per hour
|
51
|
12(v)(1)
|
Employees working inside a hull
|
0.70 per hour
|
52
|
12(v)(2)
|
Employees working in torpedo compartments, ballast
|
|
|
|
tanks, oil tanks, below floor plates
|
1.26 per hour
|
53
|
12(vi)
|
Plumber in pipe laundry
|
0.90 per hour
|
54
|
13(iii)
|
Multi-story Allowance -
|
|
|
|
from commencement to 15th floor
|
0.36 per hour
|
|
|
from 16th to 30th floor
|
0.43 per hour
|
|
|
from 31st to 45th floor
|
0.67 per hour
|
|
|
from 46th to 60th floor
|
0.85 per hour
|
|
|
from 61st floor onwards
|
1.07 per hour
|
73
|
43(ii)
|
First Aid Allowance
|
1.90
|
4. This
variation shall take effect from the first pay period to commence on or after
16 August 2002.
Printed by the authority of the Industrial Registrar.